HomeMy WebLinkAboutMINUTES - 06211988 - 1.89 TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF FLOOD
CONTROL
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: June 21, 1988
SUBJECT: Drainage Area 56, Lindsey Detention Basin Project,
Project No. 7566-6D8462-86, Oakley Area
Specific Request(s) or Recommendation(s) & Background &
Justification
RECOMMENDED ACTION:
APPROVE and ACCEPT the "Easement for Storm Drain Undercrossing of
Contra Costa Canal at MP 6.71, Central Valley California" from the
U.S. Bureau of Reclamation and,
AUTHORIZE the Chief Engineer to sign the easement document on
behalf of the Flood Control and Water Conservation District.
FINANCIAL IMPACT:
None
REASONS FOR RECOMMENDATION/BACKGROUND:
The easement is needed to allow the installation of the outfall
line from the Lindsey Detention Basin under the Contra Costa
Canal, operated by the Bureau of Reclamation.
CONSEQUENCES OF NEGATIVE ACTION:
Continued on attachment: yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on: June 21, 1988
Approved as Recommended X Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
X Unanimous(Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN.
Absent: Abstain:
Attested June 21 , 1988
Orig. Div. : PW(Constr) Phil Batchelor
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Design Administrator
PW Accounting
Contractor
BJK/sa:clw ByXs�L� �, , DEPUTY
bo:28.t6