HomeMy WebLinkAboutMINUTES - 04121988 - 1.61 TO: REDEVELOPMENT AGENCY 1-061 FROM: PHIL BATCHELOR, EXECUTIVE DIRECTOR i DATE: April 12 , 1988 SUBJECT: APPROVE Contract Change Order No. 7 for the Pleasant Hill BART Station Area Street Improvements Project, Phase IIB, Project No. 7891-6X5591-85. Specific Request(s) or Recommendation(s) & Background & Justification RECOMMENDED ACTION: APPROVE Contingency increase of $150, 000, and AUTHORIZE the Chief Engineer to execute Contract Change Order No. 7 to Gallagher & Burk, Inc. of Oakland, Ca. , in the amount of $51, 272 , to provide for changes in the planned work for the Pleasant Hill BART Street Improvements Project, Phase IIB, Project No. 7891-6X5591-85. FINANCIAL IMPACT: Funds are available from Assessment District 1983-1 and development fees for the Pleasant Hill. BART Specific Plan area. Costs required for utility changes ($5, 300) are to be reimbursed by the responsible utility. Continued on attachment: yes Signature: Recommendation of Executive Director Recommendationof Agency Committee Approve Other: Signature s Action of Agency on: April 12, 1988 Approved as Recommended X Other Vote of Commissioners I HEREBY CERTIFY THAT THIS IS A TRUE AND CORRECT COPY OF AN ACTION TAKEN X Unanimous(Absent 1 ) AND ENTERED ON THE MINUTES OF THE Ayes: Noes: REDEVELOPMENT AGENCY ON DATE SHOWN. Absent: Abstain: Attested April 12, 1988 Orig. Div. : Red-evelopmen-t(Const) -_ PIA1 Bat6helor _ . cc: Redevelopment Director Agency Secretary _ Auditor-Controller Chief Engineer -- By , DEPUTY LT/sa bo: 12 .t4 REASONS FOR RECOMMENDATION/BACKGROUND: The Agency is constructing major street improvements for the Pleasant Hill BART Specific Plan area. This contract change order provides for changes which are required because of unanticipated conflicts with various utilities and/or adjacent projects. It also provides for work not included in the original contract and necessary for the completion .of the Specific Plan improvements. This change order provides for compensation to the contractor for which are required to complete the project. Because this change order and the previously approved change order collectively exceed $25, 000, Agency approval is required. CONSE UENCES OF NEGATIVE ACTION: Failure to approve the change order will significantly delay construction of the improvements as well as impact public access to the Pleasant Hill BART Station.