HomeMy WebLinkAboutMINUTES - 03221988 - 2.13 2.13
The Board of Supervisors of Contra Costa County, California
Adopted this Order on March 22, 1988 , by the following vote:
AYES: Supervisors Powers, Fanden, McPeak, Torlakson, Schroder
NOES: None
ABSENT: None
ABSTAIN: None
SUBJECT: Tiered Landfill Application Review Process
IT IS BY THE BOARD ORDERED that the report dated March 18, 1988, of the
Director of the Community Development on the tiered landfill application review process is
CONTINUED to March 29, 1988, at 10:30 a.m.
1 hereby certify that this is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: March 22, 1988
PHIL BATCHELOR,Clerk of the Board of
Supervisors and County Administrator
By, 0, 2Z Deputy Clerk
CC: Director,CDD
County Counsel
CONTRA COSTA COUNTY
COMMUNITY DEVELOPMENT DEPARTMENT
DATE: March 18, 1988
TO: Board of Supervisors
FROM: Harvey E. Bragdon
Director of Commun'
SUBJECT: Tiered Landfill Ap lication Review Process
BACKGROUND
For the Board of Supervisors' meeting of March 8th, the Board
received a package of staff-prepared memoranda addressing several
referrals on waste disposal issues. One memorandum, dated March
2nd, was entitled "Expediting the Permit Process" . As its title
indicates, it was concerned with the possible means of reducing
the timelines of the existing environmental,._,_and. --application
review process. During the discussion of the "March 2nd
memorandum, the Board further directed staff to report on the
steps and timelines that would pertain to processing a landfill
through a tiered process. This memorandum responds to the
Board' s direction.
Although the matter of expediting the landfill approval process
was raised in connection with the proposed Marsh Creek landfill,
to the extent possible both this and the March 2nd memoranda
address issues and procedures that could apply to other proposed
waste disposal facilities as well.
This memorandum differs from the March 2nd memorandum chiefly in
that this one is primarily concerned with a 2-tier
(policy/development plan) review process focused on early
application acceptance and early review of policy-plan (General
Plan and Solid Waste Management Plan) amendments, while the March
2nd report was primarily concerned with describing the existing
landfill application review process and indicating how that
process might be expedited. The March 2nd report is attached to
this report because the earlier document contains descriptions of
(our) nine phases of activity leading to the creation of a new
landfill, which are applicable to both reports (but two-tiered in
this report) , and because the timelines of the two-tier process
are based on the timelines of the "expedited" process described
in the original memorandum. Simple timeline comparisons of the
two-tier process with the "expedited" and conventional processes
may be made by comparing Table A in this report with Table 1 in
the March 2nd report.
"Tiering" here takes its name from a tiered process for the
preparation of Environmental Impact Reports allowed by the
state' s CEQA Guidelines. However, both the environmental review
and the processing of applications for a proposed landfill would
be tiered in the process described in 'this memorandum. The first
tier would be the review and consideration of a landfill' s
policy-level applications (GPA and CoSWMP amendments) along with
a policy-oriented generalized Environmental Impact Report. The
second tier, in this case, would be the review and consideration
of the landfill as a development project (Land Use Permit; and
Rezoning and Agricultural Preserve Cancellation, if required) .
It is noted that tiering under the state' s CEQA Guidelines, is a
concept rather than a kind of EIR. Generally, the kinds of
tiered EIR' s that might be used for a waste disposal project
could be either a Program EIR, if the project consists of a
number of parts and if information exists .;to.::-.address the overall
project, or a Staged EIR, if the project requires multiple
approvals and if the initial EIR is to proceed from generalized
information. Since the aspect of developing an initial EIR for
the proposed Marsh Creek landfill partially on the basis of the
available "reconnaissance-level" information was raised at both
the Board of Supervisors ' meeting of March 8th and the Internal
Operations Committee meeting the day before, it is assumed that
if the Board is interested in having the prospective applicant
proceed with a tiered process, a Staged EIR process would be the
. more appropriate of the two.
The purposes of a tiered application process, then, would be:
1. To give a proposed landfill early official status as a
project by accepting applications for a General Plan
Amendment and a County Solid Waste Management Plan prior to
the applicant' s completion of lengthy geo-technical studies
and engineering work on the landfill development project.
Page 2
TABLE A
Summary Table
TIERED APPLICATION PROCESS
FOR A SANITARY LANDFILL PROJECT
(Minimum Timeline)
First Tier Second Tier ***
(Policy Plans) (Development Project)
EIR, GPA, CoSWMP EIR, Land Use Permit,
Solid Waste Facilities
Phase Permit
Pre-Application
A. Site Selection ( 12 months) 0 months
B. Pre-Application 3 months 0 months
Activities
Subtotals 3 months 0 months
Project Processing Phases
I . Project Review 2 months 0 months
Start-Up
II . Draft EIR 3 months 2 months
Development
III . Draft EIR 2 months 2 months
Review
IV. Planning Commission 2 months 2 months
Permit Review
V. Board of Supervisors 1 month 1 month
Project Hearings **
VI . Responsible Agency 0 months 9 months
Referrals & Final Design
Subtotals 10 months 16 months
Post-Approval Activities
(Construction Phase) 0 months 11 months
Totals 13 months 27 months
Combined Totals 40 months
*It is assumed that the site has been selected and development
rights obtained prior to the start of the first tier.
Processing the County Solid Waste Management Plan Amendment
through the cities and the California Waste Management Board to
final adoption before starting the second tier would introduce a
delay of at least 3 months between the tiers.
If the landfill will require a new or additional transfer
station, a "third tier" transfer station, development project
could be processed simultaneously with the landfill development
project ( if it would be consistent with the policy plans) .
caz/a:tablea.cht
Page 3
2. To ascertain, as early as possible, whether a proposed
landfill location would be locally acceptable. This would
be determined by processing the two policy-level
applications, for the General Plan Amendment and County
Solid Waste Management Plan, and an appropriate ( first tier)
Environmental Impact Report, to adoption by the Board of
Supervisors. The County Solid Waste Management Plan
Amendment (with the first tier EIR) also would be referred
to the cities and to the California Waste Management Board
following adoption by the Board of Supervisors.
3 . And, possibly, to provide reasonable assurance to a landfill
applicant that a development project for a landfill
facility, could be approved if it is based on the policy
approvals for the site location and can be shown to probably
be able to comply with state and regional agency regulatory
requirements for the applicable class of landfill before the
applicant makes expensive investments in geo-technical
studies and facility engineering.
TIERING TIMELINES
Table A describes how a tiered environmental and "permit" review
process could apply to a landfill project.
First Tier--Pre-application Phases
The Table assumes that the applicant already has acquired -the
title or rights to develop the proposed- site (nominally, an
effort that could take one or more years) . The applicant would
proceed to prepare generalized application submittals for a
General Plan Amendment and a Solid Waste Management Plan
Amendment. Since these submittals do not require extensive
geo-technical and engineering studies or lengthy water, air, or
habitat characterization studies, it is estimated that their
preparation could be accomplished in about 3 months.
First Tier--Project Processing Phases
The preparation and processing of a first tier Environmental
Impact Report through the County Planning Commission to the
Commission' s receiving the Final EIR Response Document is
estimated to require a minimum of 7 months from the ac eptance of
the GPA and COSWMP applications. Table A allows 2 months for the
County Planning Commission to approve the Final EIR, hear and
approve the GPA, prepare and adopt findings, and transmit the
Final EIR and GPA to the Board of Supervisors, and 1 month for
the Board to schedule a hearing, hold it, and approve the Final
EIR and GPA.
Page 4
Table A assumes that the County Solid Waste Management Commission
will have considered the COSWMP Amendment and transmitted it to
the Board of Supervisors in time for the Board to consider it
along with the GPA.
Subsequently (before beginning the second tier, or by the
beginning of the second tier but no later than the last
phase--Phase VI--of the second tier) the COSWMP Amendment, and
certified EIR, would be referred to the cities and the California
Waste Management Board for their approvals. If their concurrence
is wanted before beginning the second tier, at least another 3
months would have to be added to the process. Approval of the
CoSWMP by the cities and CWMB would add the site to the CoSWMP,
and no further city approvals would be necessary (unless a city
would be a Responsible Agency under CEQA for other purposes) .
First Tier--Post-Approval Activities
There would be no construction associated with the completion of
the first tier.
Second Tier--Pre-applicati.on Activities
Table A shows no elapsed time for second tier pre-application
activities. It is assumed that the applicant-, would. be preparing
the geo-technical, engineering, and development design work
necessary for a Land Use Permit application and regulatory agency
EIR review during the first tier period. Unless that work
resulted in substantial changes to the concept of the landfill
that was the basis for the first tier EIR, or substantial changes
were imposed on the project through the Planning Commission' s or
Board of Supervisors' approvals of the GPA or COSWMP amendments,
the second tier processing activities should be able to immedi-
ately follow the first tier.
As noted on Table A, if the landfill required a new or additional
transfer station, a "third tier" transfer station development
project could proceed through the process consecutively with the
landfill development project. This assumes that the transfer
station is provided for in the General Plan and CoSWMP.
Second Tier--Project Processing Phases
The second tier project processing phases would be concerned with
the review and consideration of a development project for the
landfill, through the instrument of a Land Use Permit
application, (and other land use applications that the project
may require) . The applicant would initiate the tier by
Page 5
submitting the detailed Comprehensive Project Description ( less
policy items) outlined in the March 2nd memorandum and the
development applications. A second tier Environmental Impact
Report focused on the development project and on the needs of the
regulatory and service agencies (CEQA Responsible Agencies) that
would have to use the EIR in making their own discretionary
decisions on the project would have to be prepared and processed
in the required manner. About 4 months (minimum) would be
required to take the CEQA process to the point where the County
Planning Commission could begin to hear the Land Use Permit and
any other land use applications. From that point, Table A allows
2 months for the Commission to approve a Final EIR (with Response
Document) , hear and consider the LUP and related entitlements,
prepare conditions and findings, and act to transmit the project
to the Board of Supervisors. Table A shows the minimum time of 1
month for the Board to schedule, hear, and act on the project.
Nine months is allocated for the applicant to complete final
geo-technical and design work required for regulatory agency
permits and off-site improvements; obtain the regulatory agency
permits; obtain off-site improvement approvals from other
jurisdictions; prepare final plans for County approval; and
obtain County and California Waste Management Board approvals of
a Solid Waste Facilities Permit (operations permit) .
Second Tier--Post-Approval Activities
Table A allows only a minimum 11 months for constructing the
landfill to a stage when it many receive wastes and for making
the necessary off-site improvements.
RECOMMENDATIONS
If the Board of Supervisors wants to have the proposed Marsh
Creek landfill project (or any subsequently proposed landfill
project) reviewed and considered through the tiered process
outlined in this memorandum, the Board should:
1. Make a finding that there are special circumstances
pertaining to the proposed Marsh Creek landfill project that
justify a tiered approach to the review and consideration of
the project; namely, that the imminent need for landfill
capacity in Contra Costa County warrants early County and
city decisions on the acceptability of the site location,
Page 6
that the time necessary for the applicant to prepare the
site-specific information required for a development project
application and regulatory agency applications would result
in an undesirable delay in the County' s acceptance of an
initial application, and that it is expected that any review
and consideration process would result in an interval of
more than 2 years between the initial approval of the
project and the start of construction. (The finding should
be made to justify the tiered process under the California
Environmental Quality Act which otherwise would call for an
initial EIR to address the whole project in detail. The 2
year interval is a criterion for justifying a Staged EIR. )
2. Direct staff to notify the prospective applicant of the
Board' s preference and to request that the applicant agree
to the tiered application process.
3 . Waive the July 10, 1984, waste disposal facility application
processing procedures for the proposed project on an
individual basis ( staff does not recommend rescinding the
1984 procedures because they are used for a variety of waste
disposal facility applications, including applications for
hazardous waste facilities) .
4. Direct staff to develop criteria for first:,' tier (policy plan
amendment) applications. (Certain criteria, such as those
addressing policies, plans, and regulations, can be taken
directly from the existing Comprehensive Project Description
criteria attached to the March 2nd memorandum, while other
submittal criteria for such subjects as traffic, services,
and design will have to be bifurcated and generalized for a
first tier project description submittal.
COMMENT
The minimum timelines outlined in this memorandum, as was
previously noted for those presented in the March 2nd memorandum,
are predicated on ideal circumstances and complete cooperation.
.During the Board of Supervisor' s discussion on the March 2nd
memorandum Board members correctly observed that the
environmental-application review process is subject to public and
governmental interactions which are not under the control of the
County, and that these have great influence over the ultimate
timelines. As examples, Responsible Agencies do add their CEQA
needs (which may be based on new regulatory requirements) to the
process, the volumes of public comments on the environmental
Page 7
documents and applications are not predictable, opponents can
exercise delaying tactics, and a project may require information
or even service from another project (possibly from the proposed
Delta Expressway in the case of the Marsh Creek Landfill) . As a
result both the County and the applicant should expect to be
flexible enough to deal with unexpected events in processing a
new landfill application.
Attachment: March 2, 1988, Memorandum to Board of Supervisors
Cz/vl
caz/draft.rpt
Page 8
CONTRA COSTA COUNTY
COMMUNITY DEVELOPMENT DEPARTMENT
TO: Board of Supervisors D TE: March 2, 1988
FROM: Harvey E. Bragdon,
Director of Community Developme
SUBJECT: Expediting the Landfill Permit Process
BACKGROUND
The Board of Supervisors, at its February 23, 1988, meeting, directed staff to
report on the feasibility of expediting the process that the County now uses to
process applications for sanitary landfills. This memorandum has been prepared
in response to the Board order.
The current process described herein is essentially generic--it was developed in
connection with the Acme landfill expansion project, it was applied to the
Kirker Pass and East Contra Costa landfill projects recently taken to the Board
(it now reflects some lessons learned from those projects) , and it would apply
to any new landfill project. Every project is unique in some respects,
however. Recognizing this, the memorandum does make some specific references to
a Marsh Creek landfill which is the only "new" landfill which,-has--,beem announced.
by a sponsor and to staff's knowledge preparations are being made to develop an
application.
The application process described in this memorandum is largely derived from
State laws, such as the State Planing Law, including. the Permit Streamlining
Act, and the California Environmental Quality Act (CEQA) , and State regulations,
and local ordinances and policies. Among -the latter, the Board .of Supervisors' -
1984 policy on landfill applications, adopted Ju-1y 10, 1984,- establishes some of
the specific policies referred to herein, such .as the applicant's provision of a
- Comprehensive Project Description and the start of the County's review process
through an application for a Board-authorized General Plan-review.
ORGANIZATION
- Table 1 summarizes the timelines of both the existing permit review process
and an expedited process.
- The Conclusions section summarizes the findings of the memorandum.
- The Potentials for Expediting Processing section describes nine phases of
project development, briefly identifies the existing process, identifies
possible time-saving measures,and identifies the ramifications of applying the
measures.
- Table 2 enumerates the activities and work products which comprise the nine
phases of project development in terms of the existing process.
- The attachment, the most recent version of specifications for the preparation
of a Comprehensive Project Description, referenced to the proposed Marsh Creek
landfill, is provided for the Board' s information.
Page 2
g
CONCLUSIONS
There is possibility, on paper, of reducing the minimum. time required to prepare
and process a landfill application from about 40 months (following site acquisi-
tion) , which at the low end of a preparation time range, to about 33 months, or
a reduction of about 18 percent. See Table 1. About four months of the 7-month
reduction would occur in activities carried out by the. project sponsor both
prior to submitting an application and after its approval by the Board of Super-
visors. About three months of the timeline estimated to be reducible by expedi-
ting the process would be in activities directly under the control of the
County.
The 33-month expedited timeline shown on Table 1 could be achieved if
circumstances are ideal and if cooperation is complete. This. statement is
qualified for a number of reasons: 1) large segments of the process are not
under the direct control of the County (legal time requirements, the sponsor,
regulatory agency requirements,. and city actions are all involved and sometimes
control segments of the .processing critical path) ; 2) both the process and the
project may depend on information or actual improvements produced by other
projects; 3) public concerns are expected to result in more hearings, more
questions to be answered, and more demands for additional information from the
County Planning Commission and Board of Supervisors than the low end of the
regular schedule provides.
The existing process is already "fast-tracked" to a considerable degree in that
documents required in later phases of project review are deve-loped, as secondary
activities, where practicable, of earlier phases.
POTENTIALS FOR EXPEDITING PROCESSING
Phase A, Site Selection
Phase A is a pre-application stage-which does not directly -involve the partici-
pation of County staff for A private-sector landfill project. - Any prospective
applicant, however, will benefit from the previous work done by the County and
other public agencies which is reflected in the County Salid Waste Management.
Plan and several site identification studies. The latter include the 1984-5
Central Contra Costa Sanitary District/Contra Costa County Study, the 1986
Southeast County Landfill Siting Study, and the records of the 1987 Blue Ribbon
Task Force effort.
Phase B, Pre-Application Activities
Phase B is an application preparation stage which almost entirely involves work
by the project sponsor, although several County and other public agencies will
have to be contacted to obtain plans and other information. The three most time
consuming activities are performing geo-technical studies (geology and hydrolo-
gy) , designing the landfill facility itself to a preliminary engineering level,
and determining the nature and extent of needed off-site improvements.
Page 3
TABLE 1
SUMMARY TABLE
EXISTING AND EXPECTED
LANDFILL APPLICATION PROCESSING PROCEDURES
Existing Process* Expedited Process**
(Range in Months) (months)
Phase Low to High Low
Pre-Application
A. Site Selection 12 mo. - 24 mo. 12 mo.
B. Pre-Application Activities 6 mo. - 12 mo. 3 mo.
Subtotal 18 mo. - 36 mo. 15 mo.
Project Processing Phases
I. Project Review 2 mo. - 3 mo. 2 mo.
Start-Up
II. Draft EIR 4 mo. - 6 mo. 3 mo.
Development
III. Draft EIR 3 mo. - 6 mo. 2 mo.
Review
IV. Planning Commission 2 mo. - 3 mo. 2 mo.
Permit Review
V. Board of Supervisors 1 mo. - 2 mo. 1 mo.
Project Hearings
VI. Responsible Agency 10 mo. - 24 mo.. 9 mo.
Referrals & Final Design
Subtotal 22 mo. - 44 mo. - - 19 mo.
Post-Approval Activities
(Construction Phase) 12 mo. - 24 mo. 11 mo.
Totals 52 mo. - 104 mo. 45 mo.
Totals Less Site Selection 40 mo. - 68 mo. 33 mo.
*See Table 2 for description of existing process.
** See Potentials for Expedited Processing in text.
Page 4
The primary product of Phase B is a Comprehensive Project Description to accom-
pany a project application. Staff has updated the specifications for a landfill
Comprehensive Project Description, as they would apply to a Marsh Creek land-
fill, and provided it to the project sponsor. A copy is attached to this memo-
randum. By following the specifications, the sponsor should be able to more
expeditiously develop a proposal for application to the County.
Tables 1 and 2 indicate a nominal range of 6 months to 12 months to accomplish
Phase B. The shorter figure assumes. that the sponsor will make a concerted
effort to perform the work and encounter no major impediments, such as bad
weather which would prevent heavy equipment for borings and trenching from being
taken into the field. The longer figure, which may be too short, envisions
contingencies such as the need for year-long water characterization or air move-
ment studies to meet regulatory agency needs for coverage in the project's
Environmental Impact Report. A considerable portion of the Comprehensive
Project Description is devoted to project design and operating requirements of a
Regional Water Quality Control Board, the Bay Area Air Quality Management Dis-
trict, and the California Waste Management Board.
The opportunities for expediting the preparation of a Comprehensive Project
Description obviously vary from site to site. The preparation mode does, howev-
er, have on attribute which is amenable to fast tracking, which is that the
process is under the direct control of the sponsor. The sponsor may elect to
hire more specialists or pay premiums for round-the-clock work. If everything
went well, the optimal 6-month preparation time might be reduced to 3 months.
Phase I, Project Review Start-Up Time
Phase I covers the period from the submission of an initial project application,
for a General Plan Amendment, through the California Quality Act Environmental
Impact Report notification and scoping stage, to the contracting of an EIR con-
sultant. (Experience indicates that an EIR will be required for a new landfill. )
It is during the scoping stage that the County will ..be informed of the regulato-
ry agencies' and other Responsible Agencies' needs for subject matter content in
the project's Environmental Impact Report.
There is little opportunity to expedite this phase of work from the range of 2
months to 3 months listed in Tables 1 and 2 because 1 month is taken up by a
mandatory minimum public review period of the CEQA Notice of Preparation. Actu-
ally, the 2-month timeline is only remotely possible, but unrealistic, unless
staff can devote full time to the effort and no delays are encountered.
An assist for minimizing the timeline--keeping it closer to the 2-month end of
the range than exceeding the 3-month end--would be to recruit a consultant by
single-source selection rather than by the usual competitive method. The
project sponsor would have to agree to single source selection. Given the very
high cost of landfill EIR's, staff would be reluctant to use single-source
selection.
Page S
Phase II, Draft EIR Development
Phase II covers the development of the Draft Environmental Impact Report from
the beginning of the consultant's efforts, through the internal review of draft
materials, to the publication of the document. It is essentially staff and
consultant work, although the sponsor (the sponsor's technical staff and consul-
tants) typically is called on the provide additional information.
The time frame for Phase II is shown as a range of four months to six months in
Tables 1 and 2. The shorter period is based on a normal core period of three
months for the consultant to produce an administrative (internal review) draft
and another month to review, revise, and publish the report. The longer period
allows a 4-month time for the consultant to produce the administrative draft,
which is a more realistic assignment for evaluating a complex project, and two
months for reviews, revisions, and publication. It is noted that none of the a
waste disposal project DEIR's have been prepared in four months, and some have
required considerably more than six months.
Long preparation periods frequently result .when the completion of the project
EIR is dependent on the availability of external documents. The most recent
example of an "outside" document extending EIR's (for hazardous waste '
facilities) is the new Health Risk Assessment, which is being required by the
air quality agencies such as the Bay Area Air Quality Management District even.
as the standards and procedures for its preparation are being determined. New
landfills may require Health Risk Assessments because of the minute amounts of
toxics present in landfill gases. The availability of the forthcoming Delta
Expressway EIR also could affect the length of time required to prepare an EIR
for the Marsh Creek landfill if this proposed thoroughfare is intended to be
used for access to the landfill. Another cause of delay, particularly for sites
in remote areas, could be performing studies on threatened and endangered plant
and animal special pursuant to federal and state laws.
Setting aside the unknowns and the unpredictable, there is a possibility of
expediting Phase Il if the sponsor's Comprehensive Project Description is very
thorough, if the EIR consultant team is experienced in landfill evaluating and
with Contra Costa County, and if both the consultant and the County staff can
give the project their undivided attention. This obviously would increase prep
aration costs. The amount of time that-might be bought would be no more than
one month at the short end of the range (i.e. , possibly down to three months) to
a two month reduction at the high end (i.e. , down to four months) .
. Phase III, Draft Environmental Impact Report Review
Phase III is essentially a "public" phase of the project review process in that
it provides for a public review and comment period for the DEIR, for a public
hearing(s) , and the preparation of a Response Document providing written re-
sponses to comments received which address environmental issues pertaining to.
the project. The phase also has a built-in "fast-track" aspect in that applica-
tions for Land Use Permits (as well as for Agricultural Preserve Cancellations
and Rezonings, if required) are filed then and staff typically prepares the
paperwork preparatory to taking these items to hearings in Phase IV.
Page 6
Tables 1 and. 2 shows a 3-month to 6-month time range for Phase III. There is
little opportunity to reduce the former figure because half the time is taken up
by a mandatory minimum 45-day public review period for the DEIR. To expedite
the process, however, the public hearing on the DEIR is usually held near . the
end of the 45-day period.
Ostensibly, the 3-month timeline might be reduced to 2 months by a combination
of dispensing with the public hearing (which is optional under CEQA, and typi-
cally for a controversial project introduces large amounts of comments late in
the review period) , the provision of overtime monies for the EIR consultant to
prepare the response document, short turn-around submission of technical infor-
mation requested of the sponsor, and exclusive devotion to the. project by
assigned County staff.
In our experience, it is difficult to meet a 3-4 month schedule for the phase
when a project is complex, highly technical, and controversial like a landfill.
The volume of comments is hard to foresee, as is the level of difficulty. in
responding to them. Some additional technical work is frequently done to fur-
ther test or substantiate the DEIR's conclusions. Often, the Planning Commis-
sion itself initiates inquiries after public testimony has been completed,
necessitating an EIR Addendum.
Also, it must be recognized that the phase is subject to delaying tactics by
project opponents, such as proliferating basic questions into scores of inqui-
ries. If the comment-and-response effort exceeds that contemplated by the
consultant's contract, the contract would have to be amended through a Board of
Supervisors' action, which itself takes time to process
As noted, the existing landfill review process contemplates that the sponsor
will file for the project's Land Use Permit and related planning approvals late
in Phase III. One reason for having the application(s) submitted then rather
than earlier is to enable the sponsor to have the benefit of most of the EIR
work to fine-tune the development pian and operating program proposed in the
Land Use Permit application to include EIR mitigation measures and suggestions.
PP g -
Another reason for not accepting- the Land Use Permit application earlier is that -
the Land Use Permit is-a "development project" which .is legally-subject to 12 to
15- -month processing constraints, and this is too optimistic a timeline from the
beginning of an EIR (with the. acceptance of a General Plan Amendment). to the
Board of Supervisors' adoption of a Land Use Permi-t. Waiting until this phase-
to receive the Land Use Permit application does not lose time for the project.
Phase IV, Planning Commission Permit Review
Phase IV, the County Planning Commission's consideration of the project's Land
Use Permit (and Agricultural Preserve Cancellation and Rezoning, if applicable)
normally would begin when the Commission is ,able to approve the Final Environ-
mental Impact Report--that is, when the Commission and the public have all the
EIR information available to them. Often, the Land Use Permit and related items
are placed on the Commission agenda along with the approval of the Final EIR.
This means that the preparation of notices (in Phase III) preceded the hearing
by almost a month.
Page 7
In the cases of the Central, Kirker Pass, and East Contra . Costa landfill
projects, the applicants introduced their projects before the final EIR's were
completed (but after the EIR hearings were closed) and hearings were held on
"model" sets of conditions before the staff-recommended Land Use Permit condi-
tions of approval were introduced and heard. That process was used to draft
approval conditions not available at that time and was atypical.
The 2-month to 3-month timeline for Phase IV in Tables 1 and 2 is quite short
when it is understood that hearing notices must be prepared and provided to
newspapers at least 2 weeks in advance of the initial public hearings, that a
staff report (often extensive for a landfill) must be prepared and provided to
the Commission, that the Commission may need to hold more than one hearing, that
the Commission may request more information from the sponsor or staff (often .
considerable) and that extensive findings must be prepared for a project, after -
the conclusion of public testimony, before a project can be acted on (if it is
to be approved) by the Commission..
In short, there is no practicable way of reducing the 2-month low-range timeline
shown on Tables 1 and 2 because it already depends on noticing and paperwork
previously performed in Phase III.
Phase V, Board of Supervisors Project Hearings
In Phase V, the Board of Supervisors is asked to confirm .the County Planning
Commission's approval of the project's Environmental Impact Report (complete its
certification) , adopt the amendments to the County General. Plan and Solid Waste
Management Plan, approve a Rezoning and related actions if required, approve the
Land Use Permit, and adopt appropriate findings. The phase begins immediately
after the Planning Commission's adoption of findings and ends with the filing of
a CEQA Notice of Determination.
The low-end timeline of one month shown in Tables .1 and 2 for the phases (1
month to 2 months) is not reducible. It- assumes that staff will -make--pre-
arrangements with the Cl-erk of the Board to reserve a hearing date, that the
Planning-Commission's findings will be largely adequate, and that the Board will
need to hold only one hearing. (By way of--contrast, the Kirker Pass Waste
Management Landfill and East Contra Costa Sanitary Landfill
g y projects went to' the
Board in late July, 1987, and were originally scheduled for final decision in
mid-December, 1987. )
Phase VI, Responsible Agency Referrals and Final Design '
Phase VI covers the period between the Board of Supervisors' approval of the
planning entitlements for a landfill and the administrative approval of its
final design plan and the issuance of its Solid Waste Facilities Permit (opera-
tions permit) through the County Health Services Department. An important
aspect of the phase is that the cities and regulatory agencies require the Coun-
ty's certified Environmental Impact Report in order to act on the project.
Page 8
e
Tables 1 and 2 show a 10-month to 2-year timeline for Phase VI. The length of
the range reflects the uncertainty over how long it will take the project spon-
sor to prepare highly technical submittals to various regulatory agencies and
how long it will take these agencies to approve the submittals. Concurrent
actions include the approval of the Solid Waste Management Plan by the cities
and by the California Waste Management Board. It is only near the end of Phase
VI, when the County is reviewing the final development plan (Development and
Improvements Plan) and preparing the Solid Waste Facilities Permit that the
"critical path" is under the control of the County. Expediting Phase IV, then,
is largely up to the project sponsor.
The project sponsor possibly can accelerate the time required for Phase VI by
establishing working relationships with regulatory agency staffs prior to Phase
VI and by carrying out final studies and. by preparing detailed plans while the
project's Solid Waste Management Plan Amendment is being considered by the cit-
ies and the California Waste Management Board.
It is conceivable that the project sponsor can bring about a somewhat shorter
Phase VI by the early preparation of the various submittals to the regulatory
agencies and the County, but not much below the 10-month short-end timeline
(say, by about a month) .
Post-Approval Activities
The final phase in the landfill development lies between the California Waste
Management Board's review of a project(s) Solid Waste. Facilities Permit and the
opening of the landfill. This is basically the construction phase, although
public agencies are involved in inspection activities and in some construction
permit approval activities. --
Table 1 shows a 1-year to 2-year timeline for this phase, but estimating a time-
line without Land Use Permit conditions of approval and construction plans is
highly speculative. Every landfill's construction program Es__
- unique. The -- _
critical path for construction -is likely to -be the installation of off-site =
improvements rather than site development itself. - The particular construction
that is likely to be--the most troublesome is the improvement of off-site access
roads between a freeway and the landfill entrance to accommodate heavy transfer
van trucks, but the extension of water service, if-required, can be difficult t&
accomplish too.
In the case of the proposed Marsh Creek landfill, a major question at this time
is when the "Delta Expressway" will be available for use if this proposed
thoroughfare is to accommodate landfill traffic between the present State High-
way 4 freeway and Marsh Creek Road.
Another major question is the availability of an East County transfer station.
It is doubtful that self-hauler traffic can be allowed direct access to a Marsh
Creek landfill, and it is likely that the distance to the Marsh Creek location
justifies transferring solid waste from route collection vehicles to transfer
vans as well. Either the landfill sponsor or the East County collector could
provide an East County facility (or facilities) but there is no currently
proposed transfer station.
Page 9
It is noted that the County probably will be placing into operation several .new
or enhanced. waste management and inspection programs during this phase. This
assumes that the project's Land Use Permit conditions of approval and, possibly,
Development -Agreement will contain similar provisions to those developed for the
Kirker Pass and East Contra Costa landfill projects.
Since this construction phase is largely at the initiative of the sponsor, and
subject to such things as seasons, the weather, and possible dependence on other
projects, the ability of the County to influence its duration is slight. None-
theless, if everything else fell into place with unusual. alacrity, County staff
might be able to expedite inspections and organize programs affecting a landfill
(since the financial support for these activities will be provided by the spon-
sor) and shorten the schedule by, say, a month.
TABLE 2
EXISTING LANDFILL APPLICATION
PROCESSING PROCEDURE
Nominal Time Line
PRE-APPLICATION PHASES (18 mo - 36 mo)(1)
PHASE A Sponsor CCCCDD Staff(2) 12 mo. - 24 mo.
SITE 'Investigate sites 'Perform site studies
SELECTION 'Select site 'Provide information
°Buy%option site
PHASE B Sponsor CCCCDD Staff 6 mo. - 12 mo.
PRE-APPLICATION °Perform site- °Identify application
ACTIVITIES specific studies requirements appro-
°Prepare Compre- priate to site
hensive Project
Description Board of Supervisors
°Submit General Plan
Amendment review 'Authorize staff to
authorization conduct a General
request Plan Amendment
review
--------------------------- ------------------------------------------------
PROJECT PROCESSING PHASES (22 mo. - 44 mo. )
PHASE I Sponsor CCCCDD Staff 2 mo. - 3 mo.
PROJECT REVIEW 'Submit Compre- °Review-_Comprehensive
START-UP hensive- Project Project Description
Description for completeness.
'Submit General °Accept General Plan
Plan Amendment Amendment application -
application 'Perform initial CEQA
°Submit request for review (assume EIR) .
Solid Waste Man- 'Prepare CEQA Notice
agement Plan of Preparation
Amendment package and file
°Comment on EIR with State Clearing-
consultant selection house (maximum 30
and EIR scoping. days) .
'File NOP with State
Clearinghouse (maximum
30-day response period)
PHASE I Sponsor CCCCDD Staff
°Recruit EIR consultant.
'Scope EIR with
Responsible Agencies
and public.
Board of Supervisors
°Transmit Solid Waste
Management Plan
Amendment request to
Solid Waste Commission.
°Execute EIR consultant
contract.
PHASE II Sponsor CCCCDD Staff .4 mo. - 6 mo.
DRAFT EIR °Provide additional 'Manage consultant
DEVELOPMENT information, as preparation of Draft
needed. EIR.
°Critique consultant's
drafts.
°Manage review of
Administrative Draft,
DEIR.
OApprove and publish
DIER.
PHASE III Sponsor CCCCDD Staff 3 mo. - 6 mo.
DEIR °File Land Use 'Prepare notices
P -
REVIEW Permit -(etc. ) (3) °Distribute DEIR
applications OFile CEQA_Notice
for Phase 4 of Completion
°Provide informa- (minimum 45-day
tion DEIR Review and
Comment period) .
'Notice DEIR completion
and public hearing.
'Prepare staff reports.
°Produce hearing
transcript.
'Produce EIR Response
Document
'Prepare GPA for Phase IV
°Prepare Solid Waste
Management Plan amend-
ment for Phase IV.
PHASE III Sponsor County Planning Commission
°Hold EIR public. hearing(s) .
°Acton Final EIR.
PHASE IV Sponsor CCCCDD Staff 2 mo. - 3 mo.
PLANNING . 'Present project. 'Prepare and distribute
COMMISSION °Provide informa- public hearing notices.
PERMIT tion. °Prepare staff report(s) .
REVIEW 'Prepare responses to
County Planning
Commission inquiries.
°Prepare resolutions,
findings, and trans-
mittal document.
County Planning Commission
'Conduct permit hearings.
°Act on permit applications.
°Adopt findings on EIR,`
permits.
County Solid Waste Commission
'Review CoSWMP amendment
request.
'Transmit recommendation
to Board of Supervisors.
PHASE V Sponsor Clerk of the Board 1 mo. - 2 mo.
BOARD OF °Present project.;. . . 'Prepare-and .distribute
SUPERVISORS 'Provide informa- public hearing notices.
PROJECT tion. _ORecord hearings.
HEARINGS 'Prepare decision-
documents.
CCCCDD Staff
°Prepare and present
staff report(s)
°Respond to the Board
inquiries.
°File CEQA Notice of
Determination.
Board of Supervisors
°Conduct public hearing(s) .
°Act on Final EIR, GPA, CoSWMP
and LUP (etc. ) applications.
PHASE VI Sponsor Board of Supervisors 10 mo - 24 mo
RESPONSIBLE °Provide Final EIR 'Transmit Solid Waste
AGENCY to Responsible Management Plan
REFERRALS & Agencies. Amendment to cities r
FINAL DESIGN °Present project to and California Waste
cities and Management; support
California Waste reviews.
Management Board.
'Carry out additional CCCCDD Staff
studies and design
improvements, as 'Review studies and
required by County final design plan.
and regulatory 'Prepare implementation
agencies. agreements.
OSubmit permit °Approve final design
applications to plan.
regulatory agencies.
°Prepare and provide Health Services Dept.
final design plan
to County. 'Participate in project
Submit Solid Waste reviews.
Facilities Permit °Prepare, approve, and
application to transmit Solid Waste
County; support Facilities Permit.
permit before
California Waste Public Works Dept.. .
Management Board.
OObtain LAFCO °Participate in project
approvals, if reviews.
required. °Review proposed off-
OObtain necessary site improvements.
construction permits
-- and approvals. --
POST-APPROVAL ACTIVITIES (12 mo. - 24 mo. )
Sponsor County Staff
°Install off-site improvements. 'Obtain inspection specialist (e.g. ,
°Install on-site improvements. geo-technical inspector) .
°Obtain necessary waste stream °Manage inspection program.
commitments. °Review%implement resource recovery,
°Initiate applications for associated out-reach, and other programs required
facilities (i.e. , transfer station) by Land Use Permit Permit and Solid
if not a component of the primary Waste Facilities Permit.
project.
(1) "Nominal" in this case is an expected optimal time range which is based on
experience. It is neither the minimum which can be plotted on a flow
chart, nor the worst case.
(2) The County Community Development Department is identified as the lead
department; other County departments, particularly the County Administra-
tor, County Counsel, Health Services, and Public Works, will be signifi-
cantly involved.
(3) "Etc." could include the cancellation of an Agricultural Preserve and the
approval of a Rezoning, if necessary.
CAZ:jn
6d:expedite.txt
• y
3%2%88 INFOh"tAT����
CRITERIA FOR
SOLID WASTE FACILITY
COMPREHENSIVE PROJECT DESCRIPTION
[MARSH CREEK LANDFILL VERSION]
PURPOSE
The Comprehensive Project Description is a project application report consisting
of development, operations and closure plans and support information and stud-
ies. It is prepared by the applicant, for submission to the Community Develop-
ment Department, as a part of an initial application for a solid waste (or
hazardous waste) disposal facility in the unincorporated area of Contra Costa
County.
The purpose of the Comprehensive Project Description is to help. assure that a
project submitted for processing will be well considered, technically feasible,
economically reasonable, and environmentally suitable, and will be accompanied
by substantiating information to facilitate its review.
The heart of the Comprehensive Project Description is a waste disposal facility ,
designed to the preliminary engineering- level in compliance .with applicable
local, state, and federal plans, laws- and regulations. The facility design is
to be based on the specific physical characteristics of the site and its vicini-
ty and on reasoned expectations of wastestream and service area feasibilities.
The Comprehensive Project Description is to identify and describe off-site
improvements and facilities needed to support the on-site facility.
The Comprehensive Project Description needs to be adequate for developing an
Environmental Impact Report for local planning applications (which may include a
General. Plan Amendment, a Solid Waste Management Plan Amendment, an Agricultural
Preserve Cancellation, a Rezoning, and a Land Use Permit) , responsible agency
approvals,. and a Solid Waste Facilities Permit.
03�vltl�tf:; 7Y ' '
P.
In the development of an Environmental Impact Report for a waste disposal
project, the Comprehensive Project Description is intended to enable County
staff and the County's consultants to perform an independent review of the
sponsor's proposals and analyses rather than perform original work. (In prac-
tice, the EIR preparers often perform some original work as well as ask the
sponsor to supplement the Comprehensive .Project Description. )
PROJECT SUMMARY STATEMENT
Provide a conceptual description of the proposed project, emphasizing the rea-
sons the sponsor is proposing the project, what waste disposal services the
project would provide, why the site was selected, why the project design was
selected, and why the project would be expected to be feasible.
The project summary may be a separate document, or designed to be distributed as
a separate "Executive Summary" document.
PROPERTY DESCRIPTION
1. Provide a legal property description of the proposed project site.
2. Provide a list of assessors'. .parcels comprising the site.
3. Provide a scaled area map of parcels comprising .the site and of adjoining
ownerships (within 300 feet as a minimum) . See APPLICATION AND SUBMITTAL.
4. Provide proof of the sponsor's eligibility to make the requisite applica-
tions for the project.
2 _
• Y
" SSAry 4 _ S
PUBLIC AGENCY CONTRACTS
1. Contact the County Community Development Department for information on the
County General Plan, the Solid Waste Management Plan, and relevant ordi-
nances and policies. Contact the County Public Works Department and Health
Services Department.
2. Contact other public agencies expected to exercise discretionary control
over the proposed project to identify their requirements and processing
processes.
3. Ascertain which public agencies may require an Environmental Impact Report,
or Statement, to act on the proposed project (i.e. , identify potential
Responsible Agencies for CEQA purposes) .
4. Provide a list of public agency contacts, including the persons' names,
titles, addresses, and telephone numbers.
PLANS, POLICIES, AND REGULATIONS
1. Provide a list of the public agency plans, policies, laws and regulations
that were utilized in the preparationof the Comprehensive Project Descrip-
tion. The.--list should include measures directly pertaining to waste dis-
posal and measures pertaining to the planning and development of the site,
its environs, and the locales of off-site improvements.—
2. Identify, at appropriate places in the Comprehensive Project Description,
how the proposed project was designed to conform to the applicable plans,
policies, laws, and regulations.
- 3 -
GENERAL PROJECTION CRITERIA
1. Assume a prime projection period of 30 years, beginning in 1990. Provide
5-year projections for the prime projection period. Subsequently, 10-year
intervals may be used (and more generalized assumptions utilized) through
the life of the facility.
2. Assume Central, East, and West County wasteshed scenarios unless others are
agreed upon. The applicant may propose other scenarios.
3. Population and related figures should be consistent with the County Solid
Waste Management Plan and cleared by the County's Planning Demographer.
WASTE VOLUMES AND CHARACTERIZATION
(The following items should be related to, or compared with, comparable informa-
tion in the County Solid Waste Management Plan. )
1. Provide sample waste constituent analyses for representative components of
the base wastestream. Special components should include large landscape
material loads, construction/large demolition debris loads, utilities'
ashes and sludges, and large-quantity commercial/industrial wastes,--which
are usually--transported directly to a landfill (not amenable to transfer
station operations) and which may be su-itable for special resource recovery
programs.
2. Identify wastes requiring special handling, such' as designated and infec-
tious wastes.
3. Provide waste stream projections by major constituent by wasteshed. Assume
no substantial resource recovery in base projections.
4. Analyze the anticipated effects of resource recovery on wastes received at
the landfill (include the effects of expected waste recovery programs at
the landfill) .
- 4 -
AIR QUALITY INFORMATION
1. Develop an air quality analysis and forecasting program in consultation
with the Bay Area Air Quality Management staff and County staff. The pro-
gram should identify data and methodological requirements for air quality
measurements and projections relative to applicable laws and regulations;
and it should specify measurement techniques and projection models the
applicant proposes to use. The items below are to be developed in accor-
dance with this program.
2. Provide base case (ambient) air quality and characteristics data, on an
annual basis, for the site and its vicinity The data should include
measurements of criteria pollutants.
3. Provide air movement (wind) .data for the site vicinity, and air movement
data for the site itself. The air movement data is to be used for litter
control planning as well as for dispersal analyses for particulates, other
criteria pollutants, and toxics (the latter if the Bay Area Air Quality
Management District (BAAQMD) or State Department of Health Services (SDOHS)
staff recommends inclusion) .
. Provide a Health Risk Assessment for the_proposed project, acceptable to
the Bay Area Air Quality District, or a letter from the BAAQMD stating that
- - a Health Risk Assessment will not be .required. -
5. Provide air, quality projections for the project site and its vicinity for
any level-of-service scenario, and applicable emission control installation
system (e.g. gas flaring, power generation) proposed by the applicant.
6. Provide odor generation and control analyses for the site and its vicinity.
7. Provide air quality projections for the transportation access roads pro-
posed to be used for the project. Provision of this item may be postponed
and subsequently provided, according to County specifications, for use in
the project's Environmental Impact Report.
5 -
ARCHAEOLOGICAL INFORMATION
1. Provide a document review of the site and its vicinity in consultation with
the Anthropology Laboratory of Sonoma State University.,
2. Provide .a reconnaissance field study of the site by a qualified archaeolo-
gist.
3. If the document review, or field study, indicates the presence, or probable
presence, of significant archaeological features, the- sponsor should- con-
sult with County staff to determine whether the information warrants more
detailed studies as part of the Comprehensive Project Description design
process or later during the development of the Environmental Impact Report.
ECONOMIC INFORMATION
1. Provide estimates of the costs of the primary waste disposal facility and
the costs of off-site improvements.
---2. Identify the proposed means of paying for-the proposed improvements.
3:-` .Provide estimates of the labor force that would be"employed--on the project
during construction and during operations.
4. Identify components of tipping fee costs, such as expected public agency
surcharges.
5. Provide information on. special pricing, if proposed, for wastestream compo-
nents such as wood and concrete.
6 -
y
GEOTECHNICAL INFORMATION
(The geotechnical study is intended to substantiate that the proposed site is
physically suitable for the development of a sanitary landfill pursuant to
County and State (e.g. , Regional Water Quality' Control Board and California
Waste Management Board) requirements. It is also the basis for the proposed
design of the landfill proper and aspects of the site's landscape design. It
may be assumed that a new landfill in Contra Costa County will be designed to
comply with the requirements of Subchapter 15, Chapter 3, Title 23 of the Cali-
fornia Administrative Code for a Class II facility. )
1. Provide topographic mapping, at no greater than 5-foot intervals within the
landfill footprint and its drainage area, of sufficient accuracy and detail
to prepare a development plan for the site (e.g. , for determining drainage,
cuts and fills, and grades) .
2. Provide field work (e.g. borings) and laboratory test results:
(a) Characterizing the bedrock underlying the site for waste disposal
facility purposes (including primary and secondary permeabilities) .
(b) Characterizing surfical materials for use as ordinary landfill cover
and low-permeability landfill cover__
(c) Locating and characterizing groundwater formations beneath the site
and in hydraulic continuity with the site.
3. Provide fieldwork to determine surface water flows on the site and within
related drainage basins. Estimate 50-year and 100-year design floods and
storms.
4. Identify and characterize permanent and intermittent ,standing water bodies
on the site.
5. Identify seismic features, such as active and inactive earthquake faults on
the property or in its immediate vicinity.
- 7 -
6. Estimate maximum probable and maximum credible design earthquakes for the
site.
7. Identify and characterize landslides and other features of geologic insta-
bility on the site.
HABITAT INFORMATION
1. Consult with the California Department of Fish and Game (and other agencies
if suggested by the DFG) to determine -potential habitat issues affecting
the project site.
2. Provide a base case study of plant and wildlife communities on the site.
The study should be performed under the direction of a qualified biologist.
3. Provide, in conjunction with the base case study, a description of the
effort taken to identify classified rare and endangered, or potentially
threatened, species.
NOISE INFORMATION -- _ - —
1. The sponsor need not provide a noise -study for the site and its access
roads as part of the Comprehensive Project Description because- noise can be
evaluated when the project's Environmental Impact Report is prepared (when
various* activity scenarios have been defined). However, the sponsor may
find there is a need to conduct noise studies for project design purposes.
If such noise studies are carried out, they should be provided to the
County as part of the Comprehensive Project Description.
8 -
v i
TRANSFER STATION ASSUMPTIONS (MARSH CREEK SITE)
1. Account for East County transfer station to serve the project for both
route collection vehicles and self-haulers in the project because:
a. As a minimum, an East County transfer station will be required to
serve East County self-haulers (for generally the same reasons as
self-haulers would be required to use a transfer station to dispose of
refuse at the East Contra Costa Sanitary Landfill, and because allow-
ing any direct self-hauler access would encourage the use of the west-
ern segment of Marsh Creek Road) .
b. The East County population distribution, road system and waste origin-
to-destination flow appear to be conducive to the location of a
transfer station in East County to serve route collection vehicles.
2. If the landfill proposes to serve Central County, route collection vehicle
and self-hauler traffic may be assumed to arrive by transfer truck (e.g. ,
an Acme transfer station, or a South County station serving that area) .
3. If the landfill proposes to serve West County, route collection vehicle and
self-hauler traffic may be assumed to arrive by transfer truck (e.g. , a
-- transfer station in the vicinity the West Contra Costa Sanitary Landfill) .
TRAFFIC AND CIRCULATION INFORMATION _
1. Consult with CALTRANS, the County Community Development and Public Works
Departments, and potentially affected cities, to obtain information on
roads, transportation plans, and access and circulation problems.
2. Select one or more proposed access routes between the project site and a
freeway.
- 9 -
sflFC:i{o
3. Provide base case information, including traffic loadings, roadway develop-
ment, and pavement conditions on the proposed site - freeway access road(s)
and (to the extent applicable) on the freeways linking the service area(s)
to the access road(s) .
4. Provide traffic projections by 5-year intervals (see General Projection
Criteria and Transfer Station Assumptions) to forecast the effects of
directing project traffic to the freeways and access roads described in
Item #3. The traffic model selected should be capable of projecting vari-
ous service area scenarios, including whole County service, and projecting
traffic management scenarios. The model and the modeling data should be
available to the County and its EIR consultant to run scenarios other than
those provided by the sponsor.
5. Provide proposals for internal circulation, off-site road and intersection
improvements, and pavement improvements, in the Development and Improve-
ments Plan.
WATER SUPPLY INFORMATION
(Unless a local fire protection agency proposes more stringent requirements, use
the water supply and storage requirements--developed for the Central,- East--Contra --
Costa and. Kirker--Pass landfill projects by the Riverview Fire Protection Dis-
trict. ) - - -
1. Identify proposed water supply sources and estimate utilization for land-
fill operations, landscaping, fire protection, and hygiene and consumption.
2. Identify water transmission and storage installations and facilities, in-
cluding the locations and sizes of water storage tanks, in the Development
and Improvements Plan.
10 -
RM AT01,d hr
PRELIMINARY. DEVELOPMENT AND IMPROVEMENTS PLAN
(The preliminary Development and Improvements Plan consists of several component
plans described, as is appropriate, in plan texts, data, illustrations, and
graphic plans. The core of the Development and Improvements Plan is a prelimi-
nary engineered landfill design, related to the geotechnical study for the
project) .
The Preliminary Development and Improvements Plan should include the following
preliminary plan components:
a. Site Design Plan
Original and final site contours, including major cuts and fills
- Landfill design, including anti-pollution installations (leachate
collection, gas collection, liners, barriers) modules, lifts, and
final cover
Surface drainage system, including ditches and sedimentation ponds
Air and water monitoring installations
Buildings, and structures, including administrative, maintenance,
and entrance facilities, and vehicle parking
Resource recovery features, including landfill gas storage,
composting, ---
p g, chipping, recovered materials storage areas, and
abandoned vehicle storage (if applicable)
Water supply, including wells, mains, storage, and delivery features
Storage areas for cover
b. Transportation and Circulation Plan
(May be combined with the Site Design Plan and the off-site Improve-
ments Plan. )
- On-site roads and circulation features
- Off-site road rights-of-way and intersection improvements, slope
easements, and utility easements
- Pavement and other roadway improvements
- 11 -
A
C. Off-Site Improvements Plan
Water, sewer, gas, electrical improvements
d. Landscaping Plan
Planting, including preparation (landfill compost use encouraged) ,
species (drought-resistant, native species encouraged) , size, and
maintenance
-. Visual barriers, including landscape screens, permanent berms, and
lift-levelmitigation berms
- Habitat replacement and enhancement
e. Erosion and Sediment Control Plan
- Grading control program, including ground cover and reseeding.
Flow control installations, including curbs and restrictors
Sedimentation ponds
f. Site Services and Utilities Plan
- Fire protection
Water service
- - Sewering service
PRELIMINARY OPERATIONS PLAN
(The core of the Preliminary Operations Plan is an initial program indicating
how the facility operator proposes to comply with the provisions of Article 7,
Chapter 3, Division 7, Title 14, of the California Administrative Code, which
will become requirements of a Solid Waste Facilities Permit at the end of the
approval process. Additionally, some of the operating requirements will be
incorporated into the project' s Land Use Permit (LUP) as LUP Conditions of
Approval. )
12 _
The Preliminary Operations Plan should address:
a. Records keeping, including waste receipts (weighing) , and vehicle
maintenance.
b. Leachate handling.
c. Landfill gas monitoring
d. Cover requirements.
e. Bird and vector control
f. Litter control.
g. "Bad days" program (unusual wind) .
h. Load inspection and handling, including illegal loads, hazardous waste
constituents, and special load disposition.
i. Personnel and visitor safety.
j. Equipment maintenance. '
k. Emergency procedures and inspections.
1. Site security.
M. Sanitation.
n. Dust control. .
o. Working face requirements.
PRELIMINARY CLOSURE AND RE-USE PLAN
(The Preliminary Closure and Re-use Plan is an initial plan for closing the
facility in compliance with State law and for the site's re-use. )
The Plan should address:
a. Closure financing
b. Closure installations
C. Re-use concept
d. Post-closure monitoring
13
-
APPLICATION AND SUBMITTALS
1. Submit a letter to the Board of Supervisors requesting the Board to author-
ize the Community Development Department to conduct a review of the County
General Plan on the subject of amending the County General Plan to accommo-
date a sanitary landfill on the proposed site. (The Board previously
indicated that it would authorize landfill project reviews. )
2. Submit a letter to the Community Development Department requesting the
General Plan Amendment. Submit the Comprehensive Project Description with
the letter. Pay General Plan Amendment fees. Staff will notify the appli-
cant if the application is complete, or if it is not, what additional
information is required. (The acceptance of the application will initiate
the CEQA process. EIRs have been required for all previously submitted new
landfill projects. )
3. Submit a Plan Set of large-scale drawings to accompany the Comprehensive
Project Description. The plans should be capable of reduction to an inter-
mediate size for future project review and to 8 1/2" x 11" or 8 1/2 x 17"
page-size for use in the EIR and other communications (the page-size reduc-
tions will probably be used in the Comprehensive Project Description) . The
Plan Set will include the following maps and plans:
a. Location map -
b. Parcel map (showing adjoining ownerships) -C. Topographic map
d. Plant community map
e. Preliminary Development and Improvements Plan (may require more than
one sheet)
f. Off-site Improvements Plan
4. The applicant will provide such additional information as may be needed to
proceed with the Environmental Impact Report and .the project' s entitlements
during the review and hearing processes.
- 14 -
5. The application for the project's Land Use Permit (and other planning enti-
tlements) may be submitted when the project's Draft Environmental Impact
Report has been distributed. (The LUP proposal should consider the infor-
mation developed by the Draft EIR and, of course, will be subject to modi-
fications resulting from the Final EIR. )
CAZ:jn
6d:airqual.txt
15 -