TO: BOARD OF SUPERVISORS , AS THE GOVERNING BODY OF THE
CONTRA COSTA COUNTY FLOOD CONTROL AND WATER
CONSERVATION DISTRICT
FROM: J . MICHAEL WALFORD , CHIEF ENGINEER
DATE : March 15 , 1988
SUBJECT: Accept for Operation and Maintenance the Wildcat and
San Pablo Creeks Construction Contract # 1 , North
Richmond Area , Project #7527-6D-8604
Specific Request(s ) or Recommendation(s ) & Background &
Justification
I . RECOMMENDATION
With the exception of sediment removal , ACCEPT for operation and
maintenance the Wildcat and San Pablo Creeks Construction
Contract #1 , U . S . Army Corps of Engineers Project , No . DACWO5-
87-B-0001 .
II . FINANCIAL IMPACT
The annual maintenance cost is estimated to be $5 , 000 . 00 funded
as part of the Flood Control Zone 7 channel maintenance budget .
III . REASONS FOR RECOMMENDATION/BACKGROUND
On June 17 , 1986 the Board of Supervisors approved a Local
Cooperation Agreement with the Department of ,the Army for the
Wildcat and San Pablo Creeks Project . The Agreement obligated
the Flood Control District to maintain and operate the project
upon completion . On November 16 , 1987 the first element of the
work , the Wildcat and San Pablo Creeks Construction Contract #1.
Project No . DACW05-87-B- 0001 , was accepted as complete by the U .
S . Army Corps of Engineers . The Contract #1 improvements on
Wildcat Creek do not include the sediment debris basin (contained
in Contract #2 ) which is essential for the economic maintenance
of the channel . Therefore , it is recommended that the Flood
Control District limit its maintenance responsibility by
excluding sediment removal at this time .
Continued on attachment: X yes Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature (s ) :
Action of Board on : MAR 15 1988
Approved as Recomffended_C_ Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
Unanimous (Absent ) ACTION TAKEN AND ENTERED ON
yes : Noes : THE MINUTES OF THE BOARD OF
Absent: Abstain: SUPERVISORS ON DATE SHOWN .
Attested MAR 15 1988
Orig. Div . : Public Works (Design ) PHIL BATCHELOR ,
cc : County Administrator CLERK OF THE BOARD
Auditor-Controller OF SUPERVISORS AND
PW Accounting COUNTY AD14INISTRATOR
GC/bb
BO : 15 . t3 ,
By •
DEPUTY CLERK
IV . CONSEQUENCES OF NEGATIVE ACTION
Failure to accept the completed landscaping work would be cause
for the Corps of Engineers to stop further work on the Wildcat
and San Pablo Creeks Project.