HomeMy WebLinkAboutMINUTES - 06021987 - 1.2 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: June 2, 1987
SUBJECT: Approve Contract Change Order No. 4 for the Castro Ranch Road Curve Adjustment
Project, No. 0671-6R6713-83, Richmond/ Pinole Area.
Specific Request(s) or Recommendation(s) & Background & Justification
RECOMMENDED ACTION:
AUTHORIZE the Public Works Director to execute Contract Change Order No. 4 to Heide &
Williams, Inc . in the amount of $26,750, to provide for miscellaneous changes in the planned
work for the Castro Ranch Road Curve Adjustment Project, Project No. 0671-6R6713-83.
FINANCIAL IMPACT:
The project contingency funds are sufficient to cover the change order costs.
REASONS FOR RECOMMENDATION/BACKGROUND:
The cumulative total of this and previous contract change orders exceeds $25,000, requiring
Board approval . Design changes were necessitated by unanticipated conflicts with various
site conditions.
CONSEQUENCES OF NEGATIVE ACTION:
The lack of approval would preclude the payment of the contractor for work required for the
successful completion of the contract.
Continued on attachment: yes Signature:
Recommendation of County Administrator Recommendati f Boara Co ittee
Approve Other:
Signature(s):
Action of Board on: JUN 2 1987 Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS ON DATE SHOWN.
Absent: Abstain:
Attested JUN 2 1987
Orig. Div.: Public Works (Construction) Phil Batchelor