HomeMy WebLinkAboutMINUTES - 06241986 - X.4 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on June 24, 1986 by the following vote:
AYES: Supervisors Fanden, Schroder , Torlakson and McPeak
NOES: None
ABSENT: Supervisor Powers
ABSTAIN:: None
SUBJECT: In the Matter of Award of Contract for Castro Ranch Road Curve
Adjustment, Project No. 0671-6R6713-83 , E1 Sobrante Area.
Bidder Total Amount Bond Amounts
Heide & Williams, Inc. $4369616.30 Payment $2189308.15
and Faith. Perf. $436,616.30
Heide & Williams General
Engineering, Hess Concrete Construction Co. , Inc.
A Joint Venture Eugene G. Alves Constr. Co. , Inc.
P.O. Box 2007 Fanfa, Inc.
Napa, CA 94558 Oliver De Silva
Gallagher and Burk, Inc.
Grade-Way Construction D. B. Construction
0. C. Jones & Sons Carone Brothers, Inc.
Bay Cities Paving & Grading, Inc. Roderick Constr. Co.
The above-captioned project and the specifications therefor being
approved., bids being duly invited and received by the Public Works Director;
and
The Public Works Director having reported that Grade-Way Construction
of Fremont, California presented the low bid of $365 ,956,30 but failed to
achieve the specified goals for Disadvantaged Business (DB) and Women's
Business Enterprise (WBE) participation nor did they demonstrate a satis-
factory good faith effort; and
The Public Works Director recommending that the bid listed first
above is the lowest responsible bid and this Board concurring and so
finding;
IT IS BY THE BOARD ORDERED, that the contract for the furnishing
of labor and materials for said work is awarded to said first listed
bidder at the listed amount and at the unit prices submitted in said
bid; and that said contractor shall present two good and sufficient surety
bonds as indicated above; and that the Public Works Department shall
prepare 'the contract therefor.
IT IS FURTHER ORDERED that, after the contractor' has signed the
contract and returned it together with bonds as noted above and any required
certificates of insurance or other required documents, and the Public
Works Director has reviewed and found them to be sufficient, the Public
Works Director is authorized to sign the contract for this Board.
IT IS FURTHER ORDERED that, in accordance with the project specifica-
tions and/or upon signature of the contract by the Public Works Director,
any bid bonds posted by the bidders are to be exonerated and any checks or
cash submitted for bid security shall be returned.
thereby certify therthfs Is it true and correct copy of
an action taken and entered on the rrshutet of the
Board of Suporvisors on the date shown.
Orig.Dept.: Public Works Department (D/C) ATTESTED: JUN 2 4 1989
PHIL. BATCHELOR, CIcrk c! :he Board
cc: County Administrator of Supervisors and Ccun:y Administrator
Auditor-Controller ,
P. W. Accounting By yS_4ZA �� , Deputy
Contractor
GC.bb
bo:24.t6