HomeMy WebLinkAboutMINUTES - 07161985 - 1.11 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on July 16, 1985 by the following vote:
AYES: Supervisors Powers , Torlakson and . Fanden
NOES: None
ABSENT: Supervisors Schroder and McPeak
ABSTAIN: None
SUBJECT:
Approval of the Final Map ) RESOLUTION NO. 85/407
and Subdivision Agreement )
for Subdivision 6561 )
Discovery Bay Area. )
The following documents were presented for Board approval this date:
The Final Map of Subdivision 6561, property located in the Discovery
Bay area, said map having been certified by the proper officials;
A Subdivision Agreement with Hofmann Company, subdivider, whereby
said subdivider agrees to complete all improvements as required in said
Subdivision Agreement within one year from the date of said agreement;
Said documents were accompanied by:
I. Security to guarantee the completion of road and drainage improve-
ments as required by Title 9 of the County Ordinance Code,
as follows:
A. Cash deposit (Auditor's Deposit Permit No. 95128, dated
June 27, 1985) in the amount of $8,700 made by Hofmann
Company.
B. Additional security in the form of a corporate surety bond
dated June 26, 1985, and issued by The American Insurance
Company (Bond No. 11110442) with Hofmann Company as
principal , in the amount of $865,900 for faithful performance
and $437,300 for labor and materials.
II. Letter from the County Tax Collector stating that there are
no unpaid County taxes heretofore levied on the property included
in said map and that the 1984-85 tax lien has been paid in full
and the 1985-86 tax lien, which became a lien on the first day
of March, 1985, is the same tax lien estimated for Subdivision
6560.
III. Security to guarantee the payment of taxes as required by Title
9 of the County Ordinance Code in the form of a surety bond, was
posted by Subdivision 6560, approved by this Board on May 7,
1985, and is on file with the Clerk of the Board.
NOW THEREFORE BE IT RESOLVED that said subdivision, together with
the provisions for its design and improvement, is DETERMINED to be con-
sistent with the County's general and specific plans;
RESOLUTION NO. 85/407
BE IT FURTHER RESOLVED that said Final Map is APPROVED and this Board
does not accept or reject on behalf of the public any of the streets,
paths, or easements shown thereon as dedicated to public use.
BE IT FURTHER RESOLVED that said Subdivision Agreement is also
APPROVED.
1 hereby certify tha:chis is a true and correct copy of
an action taken and entered on the minutes of tha
Board of Supervisors on the date shown.
ATTESTED: JUL 16 198
PHIL BATCHELOR,Clerk of the Board
of Supervisors and County Administrator
By ,Deputy
01
Originator: Public Works (ES)
cc: Director of Community Development
Public Works - Design/Construction
Road Projects
Hofmann Company
P.O. Box 907
Concord, CA 94522
The American Insurance Company
P.O. Box 5668
Concord, CA 94524
BO:16.t7
RESOLUTION NO. 85/407
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on July 16, 1985 by the following vote:
AYES: Supervisors Powers , Torlakson and Fanden
NOES: None
ABSENT: Supervisors Schroder and McPeak
ABSTAIN: None
SUBJECT:
Approval of the Road Improvement ) RESOLUTION NO. 85/413
Agreement for Subdivision 6561, )
Discovery Bay Area. )
The following document was presented for Board approval this date
for Subdivision 6561, property located in the Discovery Bay area.
A Road Improvement Agreement with The Hofmann Company, developer,
whereby said developer agrees to complete all improvements as required in
said Road Improvement Agreement within one year from the date of said
agreement;
Said document was accompanied by the following:
Security to guarantee the completion of road and drainage improvements
as required by Title 9 of the County Ordinance Code, as follows:
a. Cash deposit (Auditor's Deposit Permit No. 95405, dated July 2,
1985) in the amount of $2,040, made by The Hofmann Company.
b. Additional security in the form of:
A corporate surety bond dated July 1, 1985, and issued by The
American Insurance Company (Bond No. SC 11110443) with The
Hofmann Company as principal , in the amount of $201,960 for
faithful performance and $102,000 for labor and materials.
NOW THEREFORE BE IT RESOLVED that said Road Improvement Agreement
is APPROVED.
I hereby certify tha:IhIs is a hue and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: AUL 1,6 1985
PHIL BATCHELOR.Clerk of the Board
of Supervisors and County Administrator
ey .Deputy
Originator: Public Works (ES)
cc: Director of Community Development
Public Works - Design/Construction
Road Projects
The Hofmann Company
P.O. Box 907
Concord, CA 94522
The American Insurance Company
P.O. Box 5668
Concord, CA 94524
B0:16.t7
RESOLUTION NO. 85/413