HomeMy WebLinkAboutMINUTES - 06041985 - 1.2 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on June 4, 1985 by the following vote:
AYES: Supervisors Powers , Schroder, McPeak, Torlakson Fanden
NOES: None
ABSENT: None
ABSTAIN: None
SUBJECT: Increase in Contract Contingency Fund and Authorization to
Execute Contract Change Order No. 5 for San Pablo Avenue Slide Repair,
Project No. 0671-6R6701-83, Crockett Area.
The Public Works Director having recommended that he be authorized
to execute Contract Change Order No. 5 for the San Pablo Avenue Slide
Repair Project to compensate the contractor, Huntington Brothers, Inc. ,
for additional work necessary to complete the project; and
The Public Works Director having further recommended that the
contract contingency fund for San Pablo Avenue Slide Repair be increased
by $10,000.00 to provide additional funds for the increase in various
contract items of work and the execution of Contract Change Order No. 5.
The Public Works Director has reported that said change order
and previous change orders collectively exceed $25,000.00 and that all
costs are reimbursed by the Federal Government.
IT IS BY THE BOARD ORDERED that the recommendations of the
Public Works Director are APPROVED.
1 hereby certify tha:this Is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: M 4 1985
PHIL DATCHELOR, Clerk o:the Board
of Supervisors and County Administrator
By A .DC.P,.=Y
Orig. Dept. Public Works Department
Design and Construction Division
cc: County Administrator
County Auditor-Controller
Public Works Director
Design and Construction Division
Accounting Division
SANPABLOBO.T5
1 . Huntington Bros Inc Change order #5 apprvd
2 . San Pablo Ave ,81ide repair Crockett