SUBJECT: Sanitation District No. 19 (Discovery Bay)
Change Order No. 5 to Construction Contract with
Alan- A. Bradford Company (7393-6X5263)
On October 25, 1983, the Board of Supervisors, as Ex Officio Governing
Board of Contra Costa County Sanitation District No. 19, awarded a contract
to Alan A. Bradford Company, for the Construction of Standby Engine at Water
Well No. 2.
Change Order No. 5 is described as follows:
EXTRA WORK AT AGREED PRICE:
1. Pull, dissemble, repair, and replace pump as necessary; modify well head
shaft; assemble pump; replace pump; and reconnect to water system.
2. Furnish and install control valve in right angle drive cooling water supply
line.
3. Delete modification to site drain.
4. Delete sidewalk repair at pump station D.
5. Delete replacement of A.C. paving over underground diesel tank.
6. Delete insulation on exhaust piping.
7. Delete fire extinguisher.
8. Site work resulting from flooding of excavation at relocation of 10-inch
gate valve by open valve.
Extend the contract by 49 calendar days.
The Public Works Director, as Ex Officio District Engineer, recommends
that the Board approve Change Order No. 5, and authorize the Public Works Director,
to execute said Change Orders and increase the project cost by $15,093.
IT IS BY THE BOARD ORDERED that the recommendation of the Public Works
Director is APPROVED.
I hereby certify that this to a'rue and correct copy of
an actions takers and entered on the minutea of the
Board of Supe-.v:sora on the da:o shown.
ATTES TED: MAR 5 1985
PHIL BATCHELOR. Clerk of the Board
of (Supervisors and County Admin!strator
By ` • Deputy
Orig. Dept.: Public Works - EC
(EJS:cl) sdl9.bo.co5.t3
cc: County Administrator
Auditor-Controller
Public Works-Accounting