HomeMy WebLinkAboutMINUTES - 07171984 - 1.3 � - 3
THE BOARD OF SUPERVISORS OF .CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on July 17, 1984 by the following vote:
AYES: Supervisors Powers , Fanden , Schroder, Torlakson
NOES: None
ABSENT: Supervisor McPeak
ABSTAIN: None
SUBJECT:
In the Matter of Approving Agreement )
No. 4-0922-C with the State of California, )
Department of Transportation (Caltrans) )
for Traffic Signal Construction, State )
Route 4 and Neroly Road, Antioch Area, )
Project No. 0662-6R4265-84 )
)
WHEREAS, County and State contemplate installing a traffic control
signal system at the intersection of State Route 4 and Neroly Road, a
split jurisdictional intersection; and
WHEREAS, funding has been obtained for said project by State from
the Federal Aid Hazard Elimination and Safety (HES) fund, which fund
requires 10% local matching; and
WHEREAS, said agreement, provides the manner in which the project
will be constructed, financed and maintained; and
WHEREAS, Contra Costa County' s share of the local funds which are
provided in the road budget, is estimated at $15,200.
THEREFORE, upon recommendation of the Public Works Director, the
Board declares the agreement is approved and authorizes the Chair to
sign the agreement on behalf of Contra Costa County.
I hefaby co"that this is a true and correct copy of
an cation taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: g �---
J.A. OLI�so iN, COUNTY CLERK
and OR o ficto Ctefk of the Board
my *Deputy
bo.sig.t7 (TLD:jal 7.5.84)
ORIG. DEPT. : Public Works
Transportation Planning
cc: State of California (Caltrans.))(via Public Works)
Public Works Accounting
v"County Auditor
000003