HomeMy WebLinkAboutRESOLUTIONS - 01012001 - 2001-179 TO: Board of Supervisors
FROM: John Sweeten, County Administrator
DATE: March 21, 2001
SUBJECT: Family Law Center Project, 751 Pine Street, Martinez
Authorization No. 4033-4408; Project No. 0928-W H408B
RESOLUTION NO. 2001/ 179
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATION(S)
A. RATIFY issuance of the bid addendum extending bid opening date to April 19,2001 forthe above
project.
B. Forthe reasons listed below, DIRECT the County Administrator or his designee(with assistance
from County Counsel) to prepare, for the Board's consideration, an additional bid addendum
requiring the negotiation of a project labor agreement on the terms described below.
FINANCIAL IMPACT
There is no anticipated impact to the General Fund. Bond proceeds of$11.5 million have been set aside
for this project. The debt service for these bonds is covered primarily from revenues generated from
Courthouse Construction and Criminal Justice Construction Funds.
BACKGROUND/REASONS FOR RECOMMENDATIONS
On January 23,2001,the Board approved plans and specifications for the Family Law Center and directed
the solicitation of construction bids for the project. The project consists of a two-story steel frame structure,
approximately 40,000 square feet in area,and is estimated to cost$11.5 million. Pursuant to the Board's
direction, the project was advertised, and bids originally were schedule to be submitted and opened on
March 22, 2001.
On March 15, 2001, Addendum No. 2 was issued to extend the bid opening date to April 19, 2001. It is
recommended that the Board ratify that bid addendum.
This Board has directed the preparation and presentation of this resolution for its further consideration
concerning the above subject and related matters. Forthe following reasons, it is desirable to require the
negotiation of a project labor agreement for this project:
CONTINUED ON ATTACHMENT: X YES SIGNATURE
RECOMMENDATION OF COUNTY ADMINISTRATOR _ RECOMMENDZ0NOF'BQif*fr—ffE
_ APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON marcli 27 . 2001 APPROVED AS RECOMMENDED XA OTHER
See the attached Addendum for Board action.
VOTE OF SUPERVISORS I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
XX UNANIMOUS(ABSENT — — — — — ) AND ENTERED ON THE MINUTES OF THE BOARD
AYES: NOES: OF SUPERVISORS ON THE DATE SHOWN.
ABSENT: ABSTAIN:
ATTESTED: JOHN SWEETEN, CLERK OF THE BOARD OF
Contact: George Roemer,(925)335-1055 SUPERVISORS AND COUNTY ADMINISTRATOR
Ong.Dept.: County Administrator's Office
cc: County Counsel
Auditor/Controller
GSD Accounting-Terry Mann O n March 27 , 2001
Contra Costa Building&Construction Trades Council
O'Brien Kreitzberg(Via CAO)
mann v lark
Family Law Center Project, 725 Court Street, Martinez Authorization No. 4033-4408
March 21, 2001 Project No. 0928-W H408B
BACKGROUND/REASONS FOR RECOMMENDATIONS (continued)
(a) It is estimated that this construction project will require 17 months and will involve numerous
contractors and employees in different trades.
(b)Satisfactory performance will require a skilled and properly trained work force to construct the
project because the project must be completed on time so that the court will be available to provide much-
needed judicial services to the citizens of the County.
(c)Satisfactory performance will also require that construction proceed without the disruptions that
can occur on long-term projects both from external labor relations problems and from the frictions that often
arise when a large number of contractors and their employees work in close proximity to one another on
a job site.
(d)In the private sector, project labor agreements have been used for years on large constructions
projects to achieve satisfactory performance and the economic benefits that result from having a
guaranteed source of skilled workers and from avoiding disruptions in work.
(e) The United States Supreme Court held in Building & Construction Trades Council V.
Associated Builders& Contractors of Mass./R.1., Inc. (1993)507 U.S. 218 (Boston Harbor), that public
entities can enjoythe substantial benefits that project labor agreements can provide and the public entities
may"choose a contractor based on that contractor's willingness to enter into a pre-hire [project labor]
agreement." The validity of project labor agreements also has been upheld by the California Supreme
Court in Associated Builders & Contractors, Inc. v. San Francisco Airports Commission (1999) 21
CalAth 352.
(f)In orderto ensure satisfactory and timely completion of the project, it is necessarythat County
staff charged with the fiscal administration and responsibility for this construction project take all
appropriate actions necessary to assure that this construction project will not exceed its budget in any
manner because of the requirements of this resolution.
(g) Based upon testimony and materials previously received and matters otherwise know to the
Board and its members, the is an urgent need to expeditiously construct this court facility.
In orderto implement a project labor agreement for this project, it is recommended that the Board direct
the County Administrator and project staff(with the assistance of the County Counsel's office)to prepare
for the Board's further consideration a further bid addendum with substantially the following provisions:
(a)The apparent lowest responsible monetary bidder,as a condition of being awarded the contract,
shall negotiate a project labor agreement with the Contra Costa Building and Construction Trades Council
("Council") so that the contractor and its subcontractors can utilize the hiring halls maintained by the
Council's constituents and can utilize the Council and its constituents for resolving labor disputes during
the term of the project. The project labor agreement shall be negotiated with the Council within 14 days
after the bidder (general contractor) has been notified of its apparent status by the County;
(b)The project labor agreement shall cover all work on the project that is within the scope of the
contract between the County and the general contractor and shall run for the duration of the project;
(c) The project labor agreement shall include provisions for the following:
(1)recognition of the Council and/or its affiliates as the exclusive bargaining agent(s)for all workers
on thejob so that the general contractor knows who to deal with regarding any labor matters that may arise
during the course of construction;
(2)referral of workers from the hiring halls maintained bythe constituents of the Council in orderto
ensure a reliable source of skilled workers for the project;
Resolution 2001/179
-2-
Family Law Center Project, 725 Court Street, Martinez Authorization No. 4033-4408
March 21, 2001 Project No. 0928-WH408B
(3) a no-strike provision for the duration of the project and a final and binding grievance and
arbitration procedure in orderto prevent disruptions and delays of the project arising from internal/external
labor relations disputes, including jurisdictional disputes.
(d)The general contractor shall require all of its subcontractors, as a condition of working on the
project, to become parties to the project labor agreement.
(e)(1)In the event that the general contractor and the Council are unable to agree upon the terms
of a project labor agreement within the time limits set forth in paragraph 4(a)above,they shall immediately
proceed with arbitration of the matter in a timely fashion. The general contractor and Council shall
schedule a hearing before the arbitrator which shall be held within 10 days. The primary arbitrator to be
utilized will be specified in the bid addendum. The hearing shall be completed within a single day and if
post-hearing briefs are requested by either party they shall be filed within 3 days of the hearing. The cost
of the arbitrator and any court reporter shall be borne equally by the general contractor and the Council.
(2) The arbitrator shall decide the terms of the project labor agreement which shall include
provisions as described in paragraphs(c)and(d)above. In deciding the otherterms of the project labor
agreement,the arbitratorshall select in toto eitherthe last proposal made bythe general contractororthe
last proposal made by the Council.
(3)The arbitrator shall issue his written award within 7 days of the completion of the hearing and
send copies of it to the general contractor,the Council, and the County. The arbitrator's decision shall be
final and binding on the general contractor and the Council.
(4) If the general contractor refuses to proceed to interest arbitration or to be bound by the
arbitrator's award, itwill not be awarded the contract and the County may select a newgeneral contractor.
If the Council refuses to proceed to interest arbitration orto be bound bythe arbitrator's award,the general
contractor shall be excused from the requirement that it negotiate a project labor agreement with the
Council in order to be considered for award of the project contract.
Resolution No . 2001 /179
-3-
ADDENDUM TO ITEM SD.2
March 27, 2001
On this date, the Board of Supervisors considered ratifying the issuance of a bid
addendum extending the bid opening date for the Family Law Center Project, at
751 Pine Street, Martinez , and directing the issuance of a bid addendum requiring
negotiation of a project labor agreement. (Authorization No. 40033-4408; Project
No. 0928-WH408B).
Supervisor Uilkema opened the public hearing before the staff report on this item,
since members of the Judiciary were due back in court. The Board was in
agreement. The public hearing was opened, and the following people appeared to
speak:
The Honorable Peter Spinetta, Contra Costa County Superior Court;
Tom Steiner, Pacific Construction Corps., 1238 Laurel Lane, Lafayette;
Aram Hodess, Plumbers and Steamfitters Union 159; 1308 Roman Way,
Martinez;
Greg Feere, Contra Costa Building Trades Council, 935 Alhambra Avenue,
Martinez;
Bruce Fisher, West Coast Contractors, 2320 Courage Drive, #111, Fairfield;
Kevin Dayton, Golden Gate Chapter, Associated Builders and Contractors,
11875 Dublin Blvd., Ste C — 258, Dublin;
Eric Christen, Coalition for Employment in Construction, 2320 Courage
Drive, #I 10 Fairfield;
Derek Daymond, Sierra Bay Contractors, Inc., 4021 Port Chicago Highway,
Concord;
Frank Stephens, Western Electrical Contractor Association, 9719 Lincoln
Village, Sacramento;
Dale Peterson, IBEW 302, 1875 Arnold Drive, Martinez;
Tom Baca, V.P. Contra Costa Labor Council, 213 Midway Drive, Martinez;
Jim Hein, P.O. Box 6530, Concord; and
Linda Valdez, Horizon Sheet Metal, 4881 Sunrise Drive, Ste B, Martinez.
The public hearing was closed, and the Board discussed the issues. Following the
Board's discussion, Supervisor Gioia moved the staff report and Supervisor Gerber
seconded it.
The Board offered further comments, following those comments, the Board took
the following action:
CLOSED the public hearing; and APPROVED staff s
recommendations A and B.