HomeMy WebLinkAboutRESOLUTIONS - 01012000 - 2000-527 � IIIIIIiIIEIIIIEEii'�"EIEIIIIIIIIIIEIIIEIIIIIIIEI
CONTRA COSTA Co Recorder Cf f icer
STEPHEN L. WEIR, Clerk-Recorder
WHEN RECORDED, RETURN DOC— 2000--0256040-00
TO CLERK., BOARD OF Wednesday, NOV 15, 2000 13:19:40
FRE $0.00
SUPERVISORS Ttl Pd $0,00 Nbr-0000167616
1rc/RS/1-2
AJD File: 250-996310.1.1
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract with ) and NOTICE OF COMPLETION
R-E Corporation, dba: Reliance Enterprises ) (C.C. §3086, 30�93�}/527
Budget Line Item No. 6971-4614 ) RESOLUTION NO.
Authorizati n No. 0927-WH614B 1
The Board of Supervisors RESOLVES THAT:
The County of Contra Costa on March 21, 2000, contracted with R-E Corporation, dba:
Reliance Enterprises, for a Stand Alone Boiler for the Family Practice Center, Contra Costa
County Regional Medical Center, 2500 Alhambra Avenue, Martinez, Budget Line Item No.
6971-4614, Authorization No. 0927-WH614B, with St. Paul Fire and Marine Insurance
Company as surety, for work to be performed on the grounds of the County; and
The Director of General Services reports that said work has been inspected and complies with
the approved plans and specifications, and recommends its acceptance as complete as of
November 14, 2000; and recommends the withholding of$2,500.00 pursuant to a letter dated
October 30, 2000;
Therefore, said work is accepted as recommended above, and the Clerk shall file with the
County Recorder a copy of this Resolution and Notice as a Notice of Completion for said
contract; and the Director of General Services is directed to withhold monies otherwise due
pursuant to the letter dated October 30, 2000.
Time extension to the date of acceptance is granted as the work was delayed due to
unforeseeable causes beyond the control and without the fault or negligence of the
Contractor.
PASSED BY THE BOARD on November 14, 2000, by the following vote:
AYES: SUPERVISORS GIOIA, UIUMAA, DESAULNIER2 CANCI MILIA AND GERBER
NOES: NONE
ABSENT: NONE
HAI 999\2509963\9LO6353b.doc
Page 1 of 2
RESOLUTION NO. : 2000/527
CERTIFICATIONN and VERIFICATION
1 certify that the foregoing is a true and correct copy of a resolution and acceptance duly
adopted and entered on the minutes of this Board's meeting on the above date. 1 declare
under penalty of perjury that the foregoing is true and correct.
Dated: NOVEMBER 14, 2000 Phil Batchelor, Clerk of the
at Martinez, California. Board of Supervisors and
County Administrator
By
Originator: General Services Department - Architectural Division
cc: General Services Department
Architectural Division
Accountingg
File 250-9963/A.5
County Administrator's Office (Via A.D.)
Auditor-Controller (Via A.D.)
Contractor (Via A.D.)
Surety (Via A.D.)
Consulting Enggineer (Via A.D.)
County Recorder
RL:tb
HAI r
'"' Page 2 of 2