HomeMy WebLinkAboutRESOLUTIONS - 01011997 - 1997-199 c
File: 340-96028.4.1
THE BOARD OF SUPERVISORS
CONTRA COSTA COUNTY,CALIFORNIA
Adopted this Order of April 22, 1997 by the following vote:
AYES: Supervisors Rogers, Uilkema, Gerber, Canciamilla, Desaulnier
NOES: None
ABSENT: None
RESOLUTION NO. Z/199
SUBJECT: Approving Plans and Specifications for
Oak Grove Park,White Oak Court, Oakley
for Oak Grove Neighborhood Association
(CP#97-18)
Authorization No. WPE788
WHEREAS plans and specifications for Oak Grove Park, White Oak Court, Oakley for Oak Grove
Neighborhood Association have been filed with the Board this day by the Director of General Services;
and
WHEREAS plans and specifications were prepared by Site Development Consultants; and
WHEREAS the Consultant's cost estimate for the initial construction contract is $55,275.00, base
bid; and
WHEREAS the Board has obtained the general prevailing rates of wages, which shall be the
minimum rates paid on this project; and
WHEREAS the Board hereby finds that the project is exempt from Environmental Impact Report
requirements as a Class 1 Categorical Exemption under County Guidelines and directs the Director of
Community Development to file a Notice of Exemption with the County Clerk;
IT IS BY THE BOARD RESOLVED that said plans and specifications are hereby APPROVED.
Bids for this work will be received on May 22, 1997 at 2:00 p.m., and the Clerk of this Board is directed
to publish a Notice to Contractors in accordance with Section 22037 of Pe Mlic Contract Code, inviting
bids for said work, said Notice to be published in n ra Cos a s.mes
. The Director of General Services is directed to mail notices to
the construction trade journals specified in Section 22036 of the Public Contract Code at least 30 days
before the date of opening the bids; and
IT IS FURTHER RESOLVED that the Director of General Services, or his designee, is
AUTHORIZED to issue bid Addenda, as needed, for clarification of the contract bid documents,
provided the involved changes do not significantly increase the cost estimate for the initial construction
contract.
1 hereby cattlfy that ft N a V a SW aetnet �/
an aetton taken and ar W on Me mi Ira
Now of&* Nan On so data ahoaat.
.
C19Cletvyk .t+he bo
Rdynln1abaw
Orig.Dept.: General Services Dept. -Architectural Division
cc: General Services Department
Architectural Division
G.S. Accounting
File: 340-96021A.5
Auditor-Controller
Community Development
Dennis Barry
Consultant(Via A.D.)
Public Works Department(Via ASD)
HA1996\3409602\002006SB.wPD
GB:1s