HomeMy WebLinkAboutRESOLUTIONS - 01011967 - 67-971 IN THE BOARD OF SUPERVISORS
OF
CONTRA COSTA COUNTY, NATE OF CALIFORNIA
In the Matter of Accepting and }
Giving Notice of Completion of ) RESOLUTION OF ACCEPTANCE,
Contract with Pacific is Western ) and N'O'TICE OF COMPLETION
Engineering Contractors, )
Project No. 1271-4227--66. } RESOLUTION No. 67/471
r
The Board of Supervisors of Contra Costa County RESOLVE$
that:
The County of Contra Costa on May g, 1967 contracted
with Pacific Western Engineering Contractors, Inc. , P. 0. Box 430,
Suisun City, California, for the construction and completion of storm
drains at various locations on Appian stay between. Santa Rita load and.
Fran Way, El Sobrante, California, with The Fidelity and. Casualty
Company of New York as surety; and
The Public Works Director reports that said work has
been inspected and, complies with the approved plans, special provi:»
dons, and standard, specifications, and recommends its acceptance as
complete as of November 8, 1967;
Therefore, said, work is accepted as completed on said
date, and the Clerk shall file with the County recorder a copy of this
Resolution and Notice as a Notice of Completion for said contract.
IT IS FURTHER RESOLITM that a thirty-eight {38} day
extension of contract time "is granted due to delays caused in the
relocation of public utilities, survey staking, and, detouring of
traffic which were beyond the control of the contractor.
IT IS FURTHER RESOI;',,rED that the contractor is assessed
liquidated damages for a balance of ten {1€3} working days overrun in
the allotted contract time limit. In accordance with the contract
terms the liquidated damages shall be _$140 per day for a total of
lsooo.
PASSED AND ADOPTED this 26th day of December, 1967, by
the following vete of the Boards
AYES: Supervisors Alfred M. Dias, James E. Moriarty,
Thomas John Coll, Edmund A. Linscheid.
NOES; Nome.
ABSENT: Supervisor James P. Kenny.
RESOLUTION No. 67 '971