TO: BOARD OF SUPERVISORS ��-�- `-��' C ra
FROM: MAURICE M. SHIU PUBLIC WORKS DIRECTOR Costa
Ot �:itamnr'4�,-
DATE: January 8, 2008 - _ -�iti���
Sp'4-COUTz'� County
SUBJECT: Regional Transportation Improvement Program Application for the Iron Horse Trail Pedestrian
Overcrossing Project at Treat Boulevard, Contra Costa Centre (formerly the Pleasant Hill BART Station
area). (Regional Transportation Improvement Program) (District IV)
Co. Project No.: 0662-6R4078; Federal Project No.: BRLS 5928 (048)
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
RECOMMENDED ACTION:
ADOPT Resolution No. 2008/Z approving and authorizing the Public Works Director, or designee,to submit a
Regional Transportation Improvement Program(RTIP)application to the Metropolitan Transportation Commission
(MTC) for $245,845 in funding from the 2008 RTIP for the Iron Horse Trail Pedestrian Overcrossing Project at
Treat Boulevard, Contra Costa Centre (formerly the Pleasant Hill BART Station area). (District IV)
FISCAL IMPACT:
There is no impact to the County General Fund. This application will allow the County to receive $245,845 from
the RTIP, funded by RTIP funds (100%).
CONTINUED ON ATTACHMENT: ❑x SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMIT
APPROVE OTHER
r
SIGNATURE(S): /
ACTION OF BO ON APPROVED AS RECOMMENDED ✓ OTHER
VOTE O�SUPERVISORS: I HEREBY CERTIFY THAT THIS IS A TRUE AND CORRECT
✓/ COPY OF AN ACTION TAKEN AND ENTERED ON
UNANIMOUS(ABSENT /I�7'7 Ci ) MINUTES OF THE BOARD OF SUPERVISORS ON THE
AYES: NOES: DATE SHOWN.
ABSENT: ABSTAIN:
MSS:RS:kp
G:\Design\Correspondence\CURRENT PROJECTS\IHT Ped Bridge at Treat\Board ATTESTED
Order\BO 01-01-08 STIP Resolution.doc
Originator Public Works(Design) JOIWCULLEN,C VRK OF TME BOARD OF
Contact: Neil Leary(313-2278) SUPERVISORS
cc: J.Chen,Public Works—Design
P.Denison—Acct.
E.Kuevor—CAO
Auditor-Controller BY: DEPUTY
SUBJECT: Regional Transportation Improvement Program Application for the Iron Horse Trail Pedestrian
Overcrossing Project, Contra Costa Centre (formerly the Pleasant Hill BART Station area).
(Regional Transportation Improvement Program) (District IV)
Co. Project No.: 0662-6R4078; Federal Project No.: BRLS 5928 (048)
DATE: January 8, 2008
PAGE: 2 of 2
REASONS FOR RECOMMENDATIONS AND BACKGROUND:
On June 10,2003,the Board of Supervisors approved the design of the pedestrian overcrossing at Treat Boulevard.
This project provides for pedestrian and bicycle safety when crossing the heavily traveled Treat Boulevard. The
bridge will also link discontinuous sections of the Iron Horse Trail.
As the Regional Transportation Planning Agency for the Bay Area, the Metropolitan Transportation Commission
(MTC) is responsible for developing regional project priorities for the State Transportation Improvement Plan
(STIP) for the nine counties of the Bay Area. The RTIP is the region's proposal to the state for STIP funding. By
submitting the RTIP application to the MTC,the County's Iron Horse Pedestrian Overcrossing Project will be part
of MTC's RTIP submittal to the state and thus be eligible to receive$245,845 in funding from the 2008 RTIP. The
2008 RTIP application indicated that MTC requires the local government to show local support of this project. By
authorizing the Public Works Director to submit an RTIP application,the Board of Supervisors will be complying
with the MTC's requirement and show local support for this project.
CONSEQUENCES OF NEGATIVE ACTION:
If the application is not approved, the County will not be eligible to receive $245,845 from the RTIP funds.
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Resolution on January 8, 2008 by the following vote:
AYES: Gioia,Uilkema, Bonilla,
Glover and Piepho
NOES: None
ABSENT: None
ABSTAIN: None
RESOLUTION NO. 2008//19
SUBJECT: APPROVE and AUTHORIZE the Public Works Director, or designee, to submit a
Regional Transportation Improvement Program (RTIP) application to the
Metropolitan Transportation Commission(MTC) for$245,845 in funding from the
2008 RTIP for the Iron Horse Trail Pedestrian Overcrossing Project at Treat
Boulevard, Contra Costa Centre (formerly the Pleasant Hill BART Station area).
(District IV)
WHEREAS, Contra Costa County is submitting an application to the Metropolitan
Transportation Commission (MTC) for $245,845 in funding from the 2008 Regional
Transportation Improvement Program (RTIP) for the Iron Horse Pedestrian Overcrossing Project
for the MTC 2008 RTIP, as authorized by MTC by Resolution 3825; and
WHEREAS, SB 45 (Chapter 622, Statutes 1997) substantially revised the process for
estimating the amount of state and federal funds available for transportation projects in the state and
for appropriating and allocating the available funds to these projects; and
WHEREAS, as part of that process, MTC is responsible for programming projects eligible
for Regional Improvement Program funds, pursuant to California Government Code Section
14527(b), for inclusion in the RTIP, and submission to the California Transportation Commission,
for inclusion in the State Transportation Improvement Program; and
I hereby certify that this is a true and correct copy of an
action taken and entered on the minutes of the Board of
NL:RS: Supervisors on the date shown.
G:\Design\Correspondence\CURRENT PROJECTS\IHT Ped Bridge at Treat\Board
Order\BO 01-01-08 STIP Resolution.doc
ATTESTED:
Orig.Dept.: Public Works(Design) JOHN CULLEW,Clerk of thAoard of Supervisors and
Contact: Neil Leary,(925)313-2278 County Administrator
cc: J.Chen,Public Works—Design
By ,Deputy
RESOLUTION NO. 2008/,/,�2
SUBJECT: APPROVE and AUTHORIZE the Public Works Director, or designee, to submit a
Regional Transportation Improvement Program(RTIP)application to the Metropolitan
Transportation Commission(MTC)for$245,845 in funding from the 2008 RTIP for the
Iron Horse Trail Pedestrian Overcrossing Project at Treat Boulevard, Contra Costa
Centre (formerly the Pleasant Hill BART Station area). (District IV)
DATE: January 8, 2008
PAGE: 2
WHEREAS, MTC will review and include, if approved, 2008 RTIP projects in the federal
Transportation Improvement Program (TIP); and
WHEREAS, MTC has requested eligible transportation project sponsors to submit
applications nominating projects to be programmed for Regional Improvement Program funds in the
RTIP; and
WHEREAS,applications to MTC must be submitted consistent with procedures,conditions,
and forms it provides transportation project sponsors; and
WHEREAS,CONTRA COSTA COUNTY is a sponsor of transportation projects eligible for
Regional Improvement Program funds; and
WHEREAS,the RTIP project fact and fund sheet of the project application,attached hereto
and incorporated herein as though set forth at length,lists the project,purpose,schedule and budget
for which CONTRA COSTA COUNTY is requesting that MTC program Regional Improvement
Program funds for inclusion in the RTIP; and
WHEREAS, Part 2 of the project application, attached hereto and incorporated herein as
though set forth at length,includes the certification by CONTRA COSTA COUNTY of assurances
required by SB 45 in order to qualify the project listed in the RTIP project nomination sheet of the
project application for programming by MTC; and
WHEREAS,as part of the application for 2008 RTIP funding,MTC requires any resolution
adopted by the responsible implementing agency to state that the project will comply with the
procedures specified in the"Timely Use of Funds Provisions and Deadlines"(MTC Resolution No.
3825, Attachment 1, Pages 14-15, and as may be further amended).
NOW,THEREFORE,BE IT RESOLVED,that CONTRA COSTA COUNTY approves the
assurances set forth in Part 2 of the project application,attached to this resolution; and be it further
RESOLUTION NO. 2008/ l0
SUBJECT: APPROVE and AUTHORIZE the Public Works Director, or designee, to submit a
Regional Transportation Improvement Program(RTIP)application to the Metropolitan
Transportation Commission(MTC)for$245,845 in funding from the 2008 RTIP for the
Iron Horse Trail Pedestrian Overcrossing Project at Treat Boulevard, Contra Costa
Centre (formerly the Pleasant Hill BART Station area). (District IV)
DATE: January 8, 2008
PAGE: 3
RESOLVED, that CONTRA COSTA COUNTY will comply with the provisions and
requirements of the"Timely Use of Funds Provisions and Deadlines"(MTC Resolution No. 3825,
Attachment 1, Pages 14-15, and as may be further amended), that the Iron Horse Trail Pedestrian
Overcrossing Project will be implemented as described in the complete application and in this
resolution and,if approved,for the amount programmed in the MTC federal TIP,and that CONTRA
COSTA COUNTY and the Iron Horse Trail Pedestrian Overcrossing Project will comply with the
requirements as set forth in the 2008 RTIP Policies and Procedures(MTC Resolution No.3825);and
therefore be it further
RESOLVED,that CONTRA COSTA COUNTY has reviewed the project and has adequate
staffing resources to deliver and complete the project within the schedule set forth in the RTIP
project fact and fund sheet of the project application, attached to this resolution; and be it further
RESOLVED,that CONTRA COSTA COUNTY is an eligible sponsor of projects in the State
Transportation Improvement Program; and be it further
RESOLVED, that CONTRA COSTA COUNTY is authorized to submit an application for
State Transportation Improvement Program funds for the Iron Horse Trail Pedestrian Overcrossing
Project; and be it further
RESOLVED, that there is no legal impediment to CONTRA COSTA COUNTY making
applications for Regional Improvement Program funds; and be it further
RESOLVED, that there is no pending or threatened litigation which might in any way
adversely affect the proposed Iron Horse Trail Pedestrian Overcrossing Project, or the ability of
CONTRA COSTA COUNTY to deliver such project; and be it further
RESOLVED,that CONTRA COSTA COUNTY authorizes its Executive Director,General
Manager, or designee to execute and file an application with MTC to program Regional
Improvement Program funds into the RTIP, for the projects,purposes and amounts included in the
project application attached to this resolution; and be it further
RESOLVED,that a copy of this resolution shall be transmitted to MTC in conjunction with
the filing of the CONTRA COSTA COUNTY application referenced herein.
RESOLUTION NO. 2008/ 0
RTIP Project Application
Part 2: Certification of Assurances
The implementing agency certifies that the project for which Regional Improvement Program funding is
requested meets the following project screening Criteria. Please initial each.
1. The project is eligible for consideration in the RTIP. Pursuant to Streets and Highways Code Section
164 (e), eligible projects include improving state highways, local roads,public transit, intercity rail,
pedestrian,and bicycle facilities, and grade separation,transportation system management,
transportation demand management, soundwall projects,intermodal facilities, and safety.
2. Forthefunds requested,no costs have/will be incurred prior to adoption into the STIP by the CTC.
�
3. A Project Study Report(PSR) or PSR equivalent has been prepared for the projec �PP�
4. The project budget included in Part 2 of the project application effects current costs updated as of the
date of application and escalated to the appropriate year.XY7
5. The project is included in a local congestion management program(CMP). (Note: For those counties
that have opted out of preparing a CMP in accordance with Government Code Section 65088.3, the
project must be consistent with the capital improvement program adODtecLpursuant to MTC's funding
agreement with the countywide transportation planning agency.)
6. The year of funding for any design,right-of-way and/or construction phases has taken into j
considerat' a time necessary to obtain environmental clearance and permitting approval for the
proj ect.
7. The project is fully funded. CPQ'��l�enredy M-K-D�,
8. For projects with STIP federal funds,the implementing agency agrees to contact Caltrans and
schedule and cgzr3Plete a field review within six months of the project being adopted or amended into
the TIP.
9. For STIP construction funds,the implementing agency agrees to send a copy of the Caltrans LPP 01-
06"Award Information for STIP Projects—Attachment A"to MTC and the CMA,upon award.
10. The implementing agency agrees to be available for an audit of STIP funds,if requested.
The implementing agency also agrees to abide by all statutes,rules and regulations applying to the State
Transportation Improvement Program(STIP), and to follow all requirements associated with the funds
programmed to the project in the STIP.
These include,but are not limited to:
1. Environmental requirements: NEPA standards and procedures for all projects with Federal funds;
CEQA standards and procedures for all projects programmed with State funds.
2. California Transportation Commission(CTC)requirements for transit projects, formerly associated
with the Transit Capital Improvement(TCI)program. These include rules governing right-of-way
acquisition,hazardous materials testing, and timely use of funds.
3. Federal Transit Administration(FTA)requirements for transit projects as outlined in FTA regulations
and circulars.
4. Federal Highway Administration(FHWA)and Caltrans requirements for highway and other roadway
projects as outlined in the Caltrans Local Programs Manual.
5. Federal air quality conformity requirements, and local project review requirements, as outlined in
the adopted Bay Area Conformity Revision of the State Implementation Plan(SIP).
10-5 o7
Transportation Enhancement (TE) Application (PSR Equivalent)
TE funds are federal funds and must follow federal funding guidelines and environmental (NEPA)
processes. All projects must have an approved eligible application prior to programming.
PART ONE: GENERAL PROJECT INFORMATION
RTIP TE On System _ITIP TE SHOPP TE
_ _Off System
PROJECT TITLE: Iron Horse Trail Pedestrian Overcrossing Project
IMPLEMENTING AGENCY Administrator/person with day- (Round dollars to nearest thousands)
to-day responsibility for implementing project(Name,title,
agency,address,phone,fax,email) TE FUNDS REQUESTED $246
Neil Leary, Senior Civil Engineer State Match $
Contra Costa County
255 Glacier Drive Local Match (if Required) $4,926
Martinez, CA 94553 TOTAL TE PROJECT COST $8,213
(925) 313-2278
(925)313-2333 TE is a stand-alone project.
nleary@pw.co.contra-costa.ca.us ❑ TE is part of a larger project.
Person who can answer questions about this PARTNER(S) (Name, title, agency, address, phone,fax)
application (Name,title, phone,fax, email)
Neil Leary, Senior Civil Engineer
(925)313-2278
(925)313-2333
nleary@pw.co.contra-costa.ca.us
IF TE IS AN ENHANCEMENT TO A LARGER PROJECT, DESCRIBE LARGER PROJECT(if larger project is programmed,
provide PPNo, EA, Project Title; if not currently programmed, describe the project)
In Contra Costa County Centre near Pleasant Hill BART Station: Iron Horse Trail Over-crossing is a bicycle and pedestrian
bridge over Treat Blvd,a major sub-regional arterial.
Total Project Cost$8,213,000
PROJECT SCOPE OF PROPOSED TRANSPORTATION ENHANCEMENT ACTIVITIES
(Describe the project's location, limits of work, size, etc. Not the justification or benefits).
The Iron Horse Trail Pedestrian Overcrossing Project is located in an incorporated area in Contra Costa County called Contra
Costa County Centre, between Walnut Creek and Pleasant Hill.The bridge will be in the vicinity of the Pleasant Hill BART
Station. It is a steel bridge that spans about 900 feet in length that would run along Jones Road and would over cross Treat
Blvd.
TE Application Page 1
Nov. 2007
NEED AND PURPOSE (Describe how is project above and beyond a standard transportation project)
The Iron Horse Trail overcrossing of Treat Blvd allows pedestrians and bicycle users to safely and efficiently cross a major
sub-regional arterial to access the BART facilities and future Transit Village project on the BART property, as well as adjacent
jobs and housing center.
RELATIONSHIP (TE projects must have a relationship to surface transportation; describe relation to surface transportation)
The Iron Horse Trail Pedestrian Overcrossing Project has been designed to maximize the access and relationship to the
Transit Village.The Overcrossing is a discrete link in the existing Iron Horse Trail system that goes from Pleasanton to
Concord. The Overcrossing would enhance other modes of travel (bicycling and walking) in a very busy area.
ALTERNATIVES CONSIDERED
WHICH OF THE 12 TE CATEGORIES DOES THE PROJECT ENCOMPASS? (May be more than one.)
http://www.dot.ca.gov/hq/TransEnhAct/TransEnact.htm
• Provision of facilities for pedestrians and bicycles
• Provision of safety and educational activities for pedestrians and bicyclists
PROJECT LOCATION MAPS (Provide Location Map of project in State/Region and Area Specific Map)
7E Application Page 2
Nov. 2007
Please see attached map
PART TWO: FUNDING
Prepared by: Neil Leary Title: Senior Civil Engineer
Agency: Contra Costa County Phone (925) 313-2278 FAX (925)313-2333
PROJECT COMPONENT COSTS (round to nearest $1,000s)
RTIP [TIP SHOPP
• E&P (PA&ED) $ $ $
• PS&E $ $ $
• Right of Way Capital $ $ $
• Right of Way Support* $ $ $
• Construction Support* $ $ $
Construction Capital $246 $ $
Proposed year of Construction 09/08 (MM/YY)
TOTAL PROJECT COSTS $8,213,000
*Right of way and construction support are for Caltrans implemented projects only
PRELIMINARY ITEM ESTIMATE-CONSTRUCTION CONTRACT ITEMS
Item Description Unit Quantity Unit Price Amount
PLEASE SEE ATTACHED COST ESTIMATE
CONTINGENCY(25%)
TOTAL CONSTRUCTION CONTRACT ITEMS
MAINTENANCE (The enhancement must be maintained in a functional and operational manner as its intended purpose for the
expected life cycle for the type of project. If it is not maintained in such a manner, reimbursement of all or a portion of the
enhancement funds may be required).
Who will maintain?
What is the source of maintenance funds?
DDD Maintenance: Date:
TE Application Page 3
Nov. 2007
PART THREE: ASSURANCES
This page must be signed for the project to be considered for funding.
Project Implementing Agency possesses legal authority to nominate this transportation enhancement and to finance, acquire,
and construct the proposed project; and by formal action (e.g., a resolution)the Implementing Agency's governing body
authorizes the nomination of the transportation enhancement, including all understanding and assurances contained therein,
and authorizes the person identified as the official representative of the Implementing Agency to act in connection with the
nomination and to provide such additional information as may be required.
Project Implementing Agency will maintain and operate the property acquired,developed, rehabilitated, or restored for the life
of the resultant facility(ies)or activity. With the approval of the California Department of Transportation,the Implementing
Agency or its successors in interest in the property may transfer the responsibility to maintain and operate the property.
Project Implementing Agency will give the California Department of Transportation's representative access to and the right to
examine all records, books, papers,or documents related to the transportation enhancement activity.
Project Implementing Agency will comply where applicable with provisions of the California Environmental Quality Act,the
National Environmental Policy Act,the Americans with Disabilities Act,the Secretary of the Interior's Standards and Guidelines
for Archaeology and Historic Preservation, CTC Guidelines, FHWA Transportation Enhancement Guidance and any other
federal, state, and/or local laws, rules and/or regulations.
If TE funds or projects are used for other than the intended enhancement purposes as defined by federal or state guidelines,
the implementing agency may be required to remit all state and federal enhancement funds back to the state.
I certify that the information contained in this transportation enhancement activity application, including required attachments,
is accurate and that I have read and understand the important information and agree to the assurances on this form.
Signed / '� Date 12 —S-0-7-
(TEA
21S_0(TEA Administeri AgencR resentative)
Printed (Name and Title) Neil Leary, Senior Civil Engineer
Administering Agency Contra Costa County
G:\Design\Correspondence\CURRENT PROJECTS\IHT Ped Bridge at Treat\CCTA\STIP and TE Extension\TE Application Iron Horse Overcrossing at Treat Blvd.doc
Upon receiving an eligibility determination,a Project Nomination Sheet must be submitted to the District for programming.
TE Application Page 4
Nov. 2007
W
Y
Q
O �
O o O
= O
O �
Z
ZLLJ
Q
m ho
Q � _ w
a
0
Q ry
z
Q Q Q
m < w W U
I QW
o 0
�i O O Q -� 0 0
o Z WQ 00°
w < —
�5 Q �� --D o
� U�_j of ° 1
W < Q 0 u Z
yz LTJ L ' z
a z °0 0-
Q � Q
U Ctfm
o
cn
L W �
W J W
Q Wo W o O
COrr J o
l�J O —
Q mo Oo - —
u
Zs..
v
a.
-7 Dov
w o
� Q OV
O U
IrO
a_ -i
13NNVHD 133210 1nNIVM
�yJ Q
N
W
O
N N N N Q
(' O O U
O
llval 3S y0H z
N til
a N N NO U
cn '
z_ � `V � � O
3: O \ 0 3: N O N Y >
W C) T U N O
LLJ
3: 0
O j� N af
Q V xb C)
F-
z:
w o &O/v 089
z on
Ir
O<
a
Y Q
Q w
0 O
Iron Horse Trail Pedestrian Overcrossing
• Project Estimate 12/03/07
Item Bid Item Description Unit Quantity Unit Price Total
No. In Figures) In Figures]
1 Prepare water pollution control plan LS 1 $ 5,000.00 $5,000.00
2 Water pollution control LS 1 $ 20,000.00 $20,000.00
3 Construction area signs LS 1 $ 25,000.00 $25,000.00
4 Traffic controls stem LS 1 $ 120,000.00 $120,000.00
5 Channelizer surface mounted EA 28 $ 120.00 $3,360.00
6 Temporary railing (Type K LF 520 $ 30.00 $15,600.00
7 Temporary crash cushion EA 11 $ 400.00 $4,400.00
8 Modify minor concrete structure inlet and manhole EA 3 $ 1,800.00 $5,400.00
9 Relocate roadside sin EA 8 $ 250.00 $2,000.00
10 Clearing and grubbing LS 1 $ 12,000.00 $12,000.00
11 Roadway excavation CY 452 $ 15.00 $6,780.00
12 Swale excavation CY 22 $ 75.00 $1,650.00
13 Structure excavation, bride CY 222 $ 320.00 $71,040.00
14 Structure backfill, bride CY 42 $ 175.00 $7,350.00
15 Planting and irrigation LS 1 $ 190,000.00 $190,000.00
16 Asphalt Concrete TON 230 $ 150.00 $34,500.00
17 Permanent steel casing 60" LF 160 $ 500.00 $80,000.00
18 60"cast-in-drilled hole concrete piling LF 280 $ 850.00 $238,000.00
19 36"cast-in-drilled hole concrete piling LF 240 $ 300.00 $72,000.00
20 16"cast-in-drilled hole concrete piling LF 830 $ 40.00 $33,200.00
21 Minor concrete minor structure CY 93 $ 900.00 $83,700.00
22 Structural concrete bride CY 337 $ 765.00 $257,805.00
23 Precast concrete panel abutments SF 1,929 $ 28.00 $54,012.00
24 lElastomeric bearings abutment EA 4 $ 3,000.00 $12,000.00
25 Joint seal assembly MR=4") LF 20 $ 200.00 $4,000.00
26 Joint seal Type A MR=5/8" LF 20 $ 75.00 $1,500.00
27 Bar reinforcing steel bride LB 120,000 $ 1.20 $144,000.00
28 Fumish structural steel bride LB 323,015 $ 4.60 $1,485,869.00
29 Erect structural steel bride LB 323,015 $ 1.40 $452,221.00
30 lHanger cables LF 930 $ 25.00 $23,250.00
31 Roadside si n-one post EA 1 $ 1,000.00 $1,000.00
32 Clean and paint structural steel SF 10,000 $ 12.00 $120,000.00
33 18"reinforced concrete pipe LF 20 $ 300.00 $6,000.00
34 36"reinforced conctete pipe LF 37 $ 350.00 $12,950.00
35 Minor concrete miscellaneious construction CY 68 $ 500.00 $34,000.00
36 1 Minor concrete(exposed aggregate) _ SQFT 490 $ 10.00 $4,900.00
37 IMinor concrete brick veneer SQFT 80 $ 10.00 $800.00
38 113ridge deck drainage system _ LS 1 $ _16,000.00 $16,000.00
39 1 Projectile fence _ _ _ _ LF 370 $ 250.00 $92,500.00
40 Architectural railingY LF 1 1,690 $ 110.00 $185,900.00
41 Thermoplastic traffic stripe J LF 731 $ 15.00 $10,965.00
42 Thermoplastic pavement markin s SQFT 651 $ _ 25.00 $16,275.00
43 Pavement marker nonreflective _ EA 102 $ 10.00 $1,020.00
44 Signal and lighting Cit street modify LS 1 $ 138,000.00 $138,000.00
45 1 Lighting bride LS 1 $ 250,000.00 $250,000.00
46 Mobilization 10% LS 1 $ 435,600.00 $435 600.00
TOTAL $4,791,547.00
ROUNDED = $4,792,000.00
4% Cost Esacalation over one year $ 191,680
Construction Engineering (15% of total) $ 719,000
Contingency(10%of contract) $ 480,000
Design Consultant(ARUP) $ 1,135,150
Environmenal Permitting and County Design Management $ 500,000
($420,000 spent to date+ $80,000 Projected to Completion)
Relocate PG&E Power Poles $ 125,000
Purchase Real Property for Bridge, Maintenance Easement and
Aerial Rights for Power Line Relocation (includes Real Property $ 246,560
labor,fee title and easement costs,excludes condemnation)
Traffic Signal Relocation(Treat at Jones) $ 23,235
TOTAL $ 8,213,000