FROM: KEITH FREITAS, DIRECTOR OF AIRPORTS
Costa
°s - o
DATE: November 14, 2006 rA �oUx� County
SUBJECT: Contra Costa Airports - Authorization to Negotiate Ground Lease and Development Terms for
Approximately 11 Acres of County-Owned Land at the Buchanan Field Airport, Pacheco Area
(District IV).
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
AUTHORIZE the Director of Airports,or designee,to negotiate a long-term ground lease and development
terms between the County,as Landlord,and CCR Hangars,LLC as the Master Developer for approximately
11 acres of land on the north side of the Buchanan Field Airport and west of the Walnut Creek channel, as
recommended by the Airport Ad Hoc Subcommittee.
II. FINANCIAL IMPACT:
There is no negative impact on the General Fund.The Airport Enterprise Fund could realize lease and other
revenues and the County General Fund could realize sales tax and other revenues if a lease is successfully
negotiated.
Continued on Attachment: X SIGNATURE: kz�
RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
L�ACPPROVE OTHER
SIGNATURES L.
ACTION OF B77 ON 1,Va, APPROVED AS RECOMMENDED_OTHER
VO OF SUPERVISORS I hereby certify that this is a true and correct copy of an action
VV UNANIMOUS(ABSENT taken and entered on the minutes of the Board of Supervisors on
AYES: NOES: the date shown.
ABSENT: ABSTAIN:
ATTESTED: X4 �`v"6 e— y
JOHN CULLEN,Clerk of the Board of Supervisors and County
Orig.Div: County Airports Administrator
Contact: Beth Lee(925)646-5722
cc: County Administrator
Auditor-Controller
Community Development
Public Works Director By ,Deputy
Federal Aviation Administration ff
SUBJECT: Authorization to Negotiate Ground Lease for Buchanan Field 11-Acre Parcel
DATE: November 14, 2006
PAGE: 2
III. Reasons for Recommendations and Background:
The north development site is approximately 11 acres of land owned by the County and located west of the
Walnut Creek channel as shown on the attached map. The parcel is proximate to the Buchanan Field
runways and is designated for aviation use on the Buchanan Field Master Plan. The parcel is under the
jurisdiction of the Buchanan Field Airport and entirely within the unincorporated County.
On March 7, 2006,the Contra Costa County Public Works—Airports Division received a letter of interest
from a private party to develop the approximately 11 acre project on the subject site. The proposed
development concept included aviation uses such as various sizes of aircraft hangars and some public use
and office space.
In accordance with prior discussions with the Federal Aviation Administration's (FAA) Airports District
Office(ADO)regarding development at Buchanan Field,the County notified existing commercial tenants at
Buchanan Field and Byron Airport to solicit other competitive interest in the property. The development
solicitation letter and publication process provided a response deadline of April 3,2006,for all competitive
interests in the approximate 11 acre parcel to be submitted to the County Airport Office. The County
received three (3) additional letters of interest in developing this property.
On June 13, 2006, the Board of Supervisors (Board) authorized staff to undertake a master developer
selection process and, if competitive interest remained after submittal of the development deposit and
added project information, then a Selection Committee would be convened. A Selection Committee
would consist of County staff and representatives from the Airport businesses and surrounding
neighborhood (members of the Aviation Advisory Committee would fill these roles). The Selection
Committee would assist Airport staff in the review, interview (if deemed necessary) and selection of the
preferred Master Developer.
Airport staff subsequently sent the four interested parties a request for further information that required a
$25,000 development deposit and a response deadline of August 17, 2006. The County received two
information packets and development checks from CCR Hangars and Silver Pacific Aviation.
Airport staff and the Selection Committee reviewed the additional submittals and then interviewed the
two proposal teams. Both teams were excellent and worthy of consideration which made the ranking
determination difficult for Selection Committee members. The proposal ranking outcome was
determined by the following factors:
• Project concept(size and mix of aviation hangars)
• Project design and associated level of proposed investment
• Schedule and timing for construction of improvements and infrastructure
Applying the above factors, the proposal submitted by CCR Hangars was top ranked by the Selection
Committee. Silver Pacific was ranked a close second in overall interview ranking points.
On October 30, 2006, the Board's Airport Ad Hoc Subcommittee held a public meeting regarding this
project at the Airport Offices. A brief history, background and review of the selection process used for
SUBJECT: Authorization to Negotiate Ground Lease for Buchanan Field 11-Acre Parcel
DATE: November 14, 2006
PAGE: 3
ranking and selecting a master developer were provided. Interested parties then had the opportunity to
state their issues and concerns. Upon conclusion of this meeting, CCR Hangars remained the top ranked
developer and Silver Pacific ranked second for developer negotiation considerations.
Negotiation of lease terms would expand economic development activity at the Buchanan Field Airport,
provide additional revenues to the Airport Enterprise Fund, and allow Contra Costa County to expand
aviation related business available at the airport. A business proposal must be consistent with the Airport
Master Plan and General Plan for consideration. The proposed aviation development is consistent with the
existing Buchanan Field Airport Master Plan.Additionally,the proposed development is also consistent with
the analysis and needs assessment being performed for the updated Airport Master Plan.
IV. Consequences of Negative Action:
Delay in selecting a master developer and initiating the lease development and environmental review
processes will result in a delay of developing vacant land at Buchanan Field Airport and may negatively
impact the Airport Enterprise Fund and County General Fund.
V PROPOSED AREA OF
C/ O DEVELOPMENT
W i
W Q = 1.3 Acres
3 \ t Q = 12.7 Acres
Q = 19.2 Acres
s < Q = 12.4 Acres
Q = 11.0 Acres
kX Q = 12.7 Acres
. Q = 2.2 Acres
J Q = 0.7 Acres
e
�' Iy Q = 3.3 Acres
CDha
����• %.^�a, oho � sf' Sc
:� o0
\1 N
sayer O �'s
0 1000
d �+' 0 FEET 2000
1,= 1000'
ccA-area-e�oo
Shutt Moen ACREAGE CALCULATION OVERVIEW
BUCHANAN FIELD AIRPORT
A=ociatts
July 2000