HomeMy WebLinkAboutMINUTES - 01102006 - C.91 TO: REDEVELOPMENT AGENCY F. Contra
Costa
FROM: JOHN SWEETEN, EXECUTIVE DIRECTOR County
DATE: January 10, 2006
SUBJECT: Advisory Body Annual Report-Bay Point Redevelopment Project Area Committee
SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) &BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
ACCEPT the 2005 Advisory Body Annual Report for the Bay Point Redevelopment Project Area
Committee (PAC).
FISCAL IMPACT
No General Funds were utilized. Redevelopment Agency funds are used to staff the PAC.
BACKGROUND/REASONS FOR RECOMMENDATIONS
Board policy requires that regular and ongoing board,commission,or committees shall annually report
on its activities,accomplishments,membership attendance,required training/certification,and proposed
work plan or objectives for the following year. The annual report is included at Attachment A.
CONTINUED ON ATTACHMENT: X YES SIGNATURE
RECOMMENDATION OF EXECTUTIVE DIRECTOR
RECOMMENDATION OF AGENCY COMMITTEE
APPROVE (OTHER
SIGNATURES
ACTION OF BOA ON0� VD o(o APPROVED AS RECOMMENDED 4--OTHER
VOTE OF COMMISSIONERS I HEREBY CERTIFY THAT THIS IS A TRUE
._UNANIMOUS (ABSENT ) AND CORRECT COPY OF AN ACTION
AYES: NOES: TAKEN AND ENTERED ON THE MINUTES
ABSENT: ABSTAIN: OF THE REDEVELOPMENT AGENCY ON
THE DATE SHOWN
Contact: Maureen Toms, CDD -335-7236 ATTESTED
Ot Z Io /O�
cc: Redevelopment Agency JOHN SWEETEN, AGENCY SECRETARY
County Administrator AND COUNTY ADMININISTRATOR
Clerk of the Board
BY
DEPUT
T
Attachment A
Advisory Body Name: Bay Point Redevelopment Project Area Committee
Advisory Body Meeting Time/Location: 2nd Wednesday of each month at 7:00 pm
Ambrose Community Center, Board Room
3165 Willow Pass Road
Bay Point,CA 94565
Chair: Debra Mason
Staff person: Maureen Toms
Reporting Period: 2005
I. Activities: The Bay Point Redevelopment Project Area Committee (PAC) continued its work in
reviewing various development proposals, including two mixed-use developments on Willow Pass Road,
various single-family residential subdivisions, continuation of the North Broadway infrastructure and
residential project, and Waterfront and Specific Plan implementation.
II. Accomplishments: As described above, the PAC has had some major accomplishments, including the
near completion of the North Broadway Residential Project; implementation of the Bay Point Waterfront
Plan, and the issuance of a request for qualifications/proposals for the Orbisonia Heights neighborhood,
which is part of the Pittsburg/Bay Point BART Station Area Specific Plan.
III. Attendance: The terms for all seats for the Bay Point Project Area Committee expired June 30, 2003.
Those PAC memberspreviously serving continue to serve until replaced. The current PAC members
have fully participated in meetings , workshops, and subcommittees, as needed. Only six of the seven
seats were filled for the entire)year, due to the resignation of one of the members in April 2004. One
member (Hilleen Schwartzenberger) attended six of the ten meetings in 2005 and another member
(Sterling Stevenson) attended seven of the ten meetings in 2005. Every meeting held in 2005 had a
quorum.
IV. TraininpjCertification: The PAC members participated in the required training in 2002. By January 8,
2003, all members had submitted their training certifications to staff.
V. Proposed Work Plan/Oboectives for Next Year: The work plan/objectives for next year include
working on the implementation of the Waterfront Plan and Pittsburg/Bay Point BART Station Area
Specific Plan. Implementation of the Specific Plan involves the issuance of a Request for Developer
Qualifications/Proposals, reviewing developer qualifications, developing a sbort-list of the developers to
submit proposals,and selecting a developer for the Orbisonia Heights project.
The PAC will also continue tO implement the Community Group Funding Program for neighborhood
beautification projects initiated by volunteer groups in Bay Point. This activity will both enhance the
physical image of Bay Point, and develop the capacity and financial resources of community groups.