HomeMy WebLinkAboutMINUTES - 10122004 - C71 TO: BOARD OF SUPERVISORS
FROM: MAURICE SHIU, PUBLIC WORKS DIRECTOR
DATE: October 12, 2004
SUBJECT: CONTINUE the emergency action originally taken by the Board of Supervisors on
August 17, 2004, regarding the repair of San Pablo Avenue Bridge at Rodeo Creek,
Rodeo area. (100% Local Road Funds) (District Il) Project No. 0672-6U2522
Specific Request(s) or Recommendation(s) & Background & Justification
i. RECOMMENDED ACTION:
Continue the emergency action taken by the Board of Supervisors on August 17, 2004,
pursuant to Public Contract Code Sections 22035 and 22050, to repair of the San Pablo
Avenue Bridge at Rodeo Creek, as recommended by the Public Works Director, Rodeo
area.
0.
Continued on Attachment: X SIGNATURE:
, ECOMI4 ENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
-APPROVE OTHER
SIGNATURES)
ACTION OF SOON APPROVED AS
RECOMMENDS OTHER
E OF SUPERVISORS
UNANIMOUS(ABSENT� )
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct
RT:AK:kd copy of an action taken and entered on the
C:Maint\KlmtB0\B010-12
Orig.Div: Public Works(Design Division) minutes of the Board of Supervisors on the
Contact: R.Tavenier(313-7006) date Shown.
cc: M.Hollingsworth,Design
M.Carlson,Construction
A.Knapp,Maintenance
ATTESTED:
John Sweeten, Clerk of the Board of
Supervisors and County Administrator
By
/Deputy
SUBJECT: CONTINUE the emergency action originally talon by the Board of Supervisors on August
17, 2004, regarding the repair of San Pablo Avenue Bridge at Rodeo Creek, Rodeo area.
(100%, Local Road Funds) (District li) Project No. 0672-6U2522
DATE: October 12, 2004
PAGE: 2
11. FINANCIAL IMPACT:
Total Work Order i $71,000. Low bid contract cost is $39,329. Project will be funded by 100%
Local Read Funds.
Ill. REASONS FOR RECC3MMENDATIONIBACKGROUND:
A. On August 17, 2004, the Board of Supervisors declared an emergency and authorized the
Public Works Director to proceed with the most expeditious manner to repair the San Pablo
Avenue Bridge at Rodeo Creek, rodeo area.
B. Repair status:
1. Public Works has awarded the project to the low bidder, E.E. Gilbert Construction.
2. Construction began on September 27, 2004.
IV. CONSEQUENCES OF NEGATIVE ACTION:
Non-concurrence of the above recommendation will delay repair of the bridge structure until 2005,
which could cause the structure to continue to degrade. Continued degradation could result in
further increased repair costs and possible loss to portions of the bridge.