HomeMy WebLinkAboutMINUTES - 01072003 - C1-C5 x TO: BOARD OF SUPERVISORS FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR DATE: January 7, 2003 SUBJECT: Approve Project Contingency Fund Increase for the Pacheco Boulevard Widening & Frontage Improvements Project, Project No. 0662-684297-02, Martinez area. District 11 Specific Request{s}or Recommendation{s}if Background&Justification I. Recommended Action: APPROVE project contingency fund increase of$3,000 for a new total of$13,050 effective January 7, 2003 in order to compensate the contractor, Say Cities Paving & Grading, Inc.for extra work due to unforeseen conditions. 11. Financial Impact: The project contingency funds are currently insufficient to cover the increased cost. The increase in contingency funds will be funded by 73% Measure C and 27%/ ,*?001-2002 Transportation F, Development Act. y Continued on attachment: X yes SIGNATURE: �, I RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE S F_1 ACTION OF BO d N: JANUARY 07 , , -9003 APPROVED AS RECOMMENDED XX OTHER_ VOTE OF SUPERVISORS xx UNANIMOUS (ABSENT ) I hereby certify that this is a true and correct copy of an AYES: NOES: action taken and entered on the minutes of the Board of ABSENT: ABSTAIN: Supervisors on the date shown. Contact: Mike Carlson,{925}313-2320 ATTESTED:_ JANUARY 07 , 2003 Brig.Div.: PW{Constr} JOHN SWEETEN, Clerk of the Board of Supervisors and cc: County Administrator Auditor-Controller County Administrator Public Works - Accounting r - Construction,R.Bruno By ., Deputy - Design a p Y Contractor Ra:tb G:\GRPDATA\CONSnBO\2003VAPPROVECONTINGENCYPACHECOWIDENING.DOC z� 7 SUBJECT: Approval of contract contingency fund increase for the Pacheco Boulevard Widening & Frontage Improvements Project. Project No. 0662-6R4297-02, Martinez area, District 11 DATE: JANUARY 7, 2003 PAGE 2 OF 2 III. Reasons for Recommendations and Background: Additional funding is needed to pay the contractor for extra work outside the original contractual agreement. The contractor encountered additional costs when the roadway was extended wider than the plans were originally designed. IV. Consequences of Negative Action: The lack of approval would prevent successful completion of this contract and preclude payment to the contractor for required work. _....__. ................................................. TO: BOARD OF SUPERVISORS FROM: MAURICE SHIU, PUBLIC WORKS DIRECTOR DATE: January 7, 2003 SUBJECT: AUTHORIZE the Public Works Director to advertise for bids for the Bailey Road Bridge Replacement Project in the Concord area. CDD-CP#99-62 Project No.: 0622.684249-95 Specific Request(s) or Recommendations) & Background & Justification 1. RECOMMENDEDACTION: AUTHORIZE the Public Works Director to ADVERTISE the project DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with Section 22037 of the Public Contract Code upon confirmation of project advertisement by the Public Works Director A .r 9i Continued on Attachment: X SIGNATURE x r::-RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE -APPROVE ® _OTHER SIGNATURE(S)aa�- ACTION OP B RON JANUARY 07 2(703 APPROVED COMMENDED__40THE'R 4 VOTE OF SUPERVISORS XX UNANIMOUS(ASSENT ) AYES: NOES: ABSENT: ABSTAIN: I hereby certify that this is a true and correct NL:mm copy of an action taken and entered on the G:tGrpData\DesigntBoard OrderstBO2003\ minutes of the Board'of Bailey Rd Bridge Replac 1-7-03.doc Supervisors on the date shown. Orig.Div: Public Works(Design Division) Contact: Neil Leary(313-)313-2278 C: E.Kuevor,CAO Auditor-Controller ATTESTED: JANUARY 07 2003 Community unity Development 3 PW Accounting John Sweeten, Clerk of the Board of Construction Supervisors and County Administrator By Dep -1 SUBJECT: APPROVE plans and specifications and AUTHORIZE the Public Works Director to advertise for bids for the Bailey Road Bridge Replacement Project in the Concord area. CDD-CP#99-62 Project No.: 17622-6R4249-95 DATE: January 7, 2003 PAGE: 2 I1. FINANCIAL IMPACT: The estimated contract cost of the project is$665,000, funded by Federal Highway Bridge Rehabilitation and Replacement Program (80%) and Local Road Funds (20%). III. REASONS FOR RECOMMENDATIONIBACKGROUND: The project is needed to replace a bridge that is classified as"functionally obsolete"and to provide a durable replacement structure using modern bridge construction materials. The Public Works Director will file with the Board of Supervisors the Plans and Specifications for the project at the time the project is advertised. The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with the Clerk of the Board and copies will be made available to any interested party upon request. The Board reviewed and approved the project on December 14, 1999 and found, on the basis of the initial study and all comments received, that there is no substantial evidence that the project will have a significant effect on the environment and adopted the Negative Declaration in compliance with the California Environmental Quality Act. A Notice of Determination was filed with the County Clerk on December 16, 1999. A detour road will be constructed adjacent to Bailey Road to allow for the construction of the new bridge in the same location as the existing bridge. The detour road will be built west of the existing Bailey Road between Monroe Way and Myrtle Drive and will be in effect for approximately 22 weeks. IV. CONSEQUENCES OF NEGATIVE ACTION: If the project is not approved for advertising, it will not be constructedand Federal funding may be jeopardized. TO.: BOARD OF SUPERVISORS FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR DATE: January 7, 2003 SUBJECT: FY 2003/2004 Community Development Block Grant Applications Project No.: 0676-6P1028 SPECIFIC REMEST(S)OR RECOMMENDATIONS)&BACKGROUND AND JUSTIFICATION !. Recommended Action: APPROVE and AUTHORIZE the Public Works Director to submit a community Development Black Grant Application to Community Development Department in the amount of $56,800 for Fiscal Year 200312004 for the North Richmond Curb Ramps, North Richmond area. Continued on Attachment: X SIGNATURE- _RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE (S): ACTION OF BO 7DYA-J-A-NUARY , 200APPROVED AS RECOMMENDED xx OTHER I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board VOTE OF SUPERVISORS of Supervisors on the date shown. xx UNANIMOUS{ABSENT } AYES: NOES: ABSENT: ABSTAIN: JANUARY € 7 2003 ATTESTED; � JOHN SWEETEN, Clerk of the Board of Supervisors WL:jb:je and County Administrator G:\GrpData\TransEngIGRANTS\CDBG\CDBG 43-041 FY 2003-2004 North Richmond Curb Ramps\130-drat#.doc Ortg.Div:Public Works(TE) Contact: A.Schaal—Tei.813-2234 J.Bolibol—Tel.313-2315 cc: Public Warks Accounting By '' , Deputy StfBJECT: FY 2003/2004 Community Development Block Grant Applications MATE: January 7, 2003 PAGE: 2 11. Financial Impact: There will be no financial impact to the General Fund. All of the projects will be funded through Community Development Block.Grant Funds, Road Funds, and/or Redevelopment Agency Funds. III. Reasons for Recommendations and Background: Applying for and obtaining grants allows the County to construct more improvements than would be possible without obtaining grants. The North Richmond Curb Ramps project consists of installing curb ramps at intersections in the North Richmond Mousing Authority area. The curb ramps are needed to facilitate the movement of people in wheel chairs, and mobility impaired pedestrians along the streets of North Richmond. IV. Consequences of Negative Action: Failure to approve the submittal of these applications will eliminate a potential funding source and possibly delay the construction of the projects. TO: BOARD OF SUPERVISORS FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR DATE: January 7, 2003 SUBJECT: Indemnification Agreement Between Metropolitan Transportation Commission and Contra Costa County. Project Number 0676-6P4044 SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION !. Recommended Action: APPROVE and AUTHORIZE the Chair, Board of Supervisors, to execute the Indemnification Agreement with the Metropolitan Transportation Commission in the amount of$7,000 for Traffic Engineering Technical Advisory Program grant funds for the study of the intersection of Livorna Road and Wilson Road, effective January 7, 2003 through completion of project, Alamo area. (District 111) Continued on Attachment: X SIGNATURE: ,, .... °F�ECOMMENDATIOd OF COUNTY'ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE _ ' APPROVE OTHER SIGNATURE(S) ACTION OF BOR ON JANUARY 07 , 20 ROVED AS RECOMMENDED xx OTHER VOTE OF SUPERVISORS I hereby certify that this is a true and correct copy of an xx__ UNANIMOUS (ABSENT ) action taken and entered on the minutes of the Board AYES: NOES: ABSENT:- ABSTAIN: of Supervisors on the date shown, MH:,e JANUARY 07, 2003 C,:\GrpData\TransEng\AOBLALAMObAR1C1TETAP\BO torindemnSficaumdoc ATTESTED: Ortg.Div:Public Works(TE) JOHN SWEETEN, Clerk of the Board of Supervisors Contact: Mary Halle(313-2327) and County Administrator c: J.Gregory,CA© County Counsel J.$ueren,Deputy PWD J.Yee,Transportation Engineering By , Deputy S.Kowalewski,Transportation Engineering W.Lai,Transportation Engineering PW Accounting SUBJECT: Indemnification Agreement Between Metropolitan Transportation Commission and Contra Costa County. Project Number 0676-6P4044 DATE: January 7, 2003 PAGE. 2 If. Financial Impact: There will be no impact to the General Fund. The County has been awarded a grant of$7,000 from the Metropolitan Transportation Commission (MTC). Ill. Reasons for Recommendations and Background: Contra Costa County has been awarded a grant of $7,000 by MTC for Traffic Engineering Technical Assistance (TETAP)to study optimum traffic operations at the intersection of Livoma Road and Wilson Road, in the Alamo area. The grant is in the form of a $7,000 credit with an expert traffic consultant, retained by MTC.The value to the County greatly exceeds the underlying $7,000 dollar value as MTC retains the traffic consultants for the overall grant program. In addition to the consulting services,the County gains value from the administrative time and cost provided by MTC to advertise, interview, select and administer the consulting services contract. Execution of the Indemnification Agreement is a requirement for the grant award. The agreement waives the Counties right to file a claim against MTC and agrees to indemnify and hold harmless MTC from third party claims resulting from or in connection with the traffic engineering services under contract to MTC. IV. Consequences of Negative Action: Failure to approve the agreement will result in forfeiture of the grant funding. INDEMNIFICATION AGREEMENT Between METROPOLITAN TRANSPORTATION COMMISSION And CONTRA COSTA COUNTY THIS AGREEMENT is made and entered into as of the7nt day of_ January_ ,2003, by and between the Metropolitan Transportation Commission, a regional transportation planning agency established pursuant to California Government Code § 66500 et seq., (herein called "MTC'), and CONTRA COSTA COUNTY(herein called"COUNTY"). WITNESSETH WHEREAS, MTC has entered into technical services agreements with a number of traffic engineering firms under which such firms will provide traffic engineering assistance to various Bay Area cities(herein called"the Project"); and WHEREAS, COUNTY is participating in the project by receiving traffic engineering assistance from one of MTC's consultants ("the Traffic Engineering Consultant"); NOW, THEREFORE,the parties hereto agree as follows: 1.0 WAIVER OF MTC LIABILITY COUNTY waives all claims by COUNTY against MTC, its commissioners, officers,and employees for damages, loss,injury and or liability, direct or indirect, resulting from COUNTY's participation in the Project and/or the services provided to COUNTY by the Traffic Engineering Consultant under contract to MTC. 2.0 INDEMNIFICATION AND DEFENSE COUNTY agrees to indemnify,hold harmless and.defend MTC, its Commissioners,officers, and employees from any and all third party claims,demands, lawsuits, liability, loss and/or damage(including any and all cost and expenses in connection therewith), resulting from or in connection with provision of traffic engineering services to COUNTY by the Traffic Engineering Consultant under contract to MTC,to the extent such claims, demands,etc. are not covered by the Traffic Engineering Consultant's indemnification of MTC in its contract with MTC. IN WITNESS WHEREOF,this agreement has been executed by the parties hereto as of the date first written above. METROPOLITAN TRANSPORTATION CONTRA COSTA COUNTY COMMISSION Steve Hem' ger, cutive Director �CI�AIR, BOA 1) Off' SUPERVISORS TO: BOARD OF SUPERVISORS . FROM: MAURICE M. SHIU,PUBLIC WORKS DIRECTOR DA'T'E: January 7, 2003 SUBJECT: State Route 4 East,Railroad Avenue to Loveridge Road,Pittsburg Area. SCH#200011207 Project No.:4660-6X4287 Task: ACCO Account: 3540 SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUS'T'IFICATION I. Recommended Action: A. APPROVE the Relocation Assistance Claims listed below: CLAIMANT CLAIM DATE PAYEE AMOUNT SkyTel Moving Expense 12102102 SkyTel $ 3,222.50 Bishop Wisecarver Moving Expense 12102102 Bishop Wisecarver $51,586.27 B. AUTHORIZE the Principal Real Property Agent to sign said claim forms on behalf of the County. C. AUTHORIZE the Auditor-Controller to issue checks in the amounts of $3,222.50 payable to SkyTel, 4709 Evora Road, Concord, CA 94520, and Bishop Wisecarver for $51,586.27, 2104 Martin Way, Pittsburg CA 94565 for moving expenses, to be forwarded to the Real Property Division for delivery. II. Financiallmpact: Payment totaling $54,808.77 to be made from the State Route 4 East Widening Project, Railroad Avenue to Loveridge Road,which is 100%reimbursable from Contra Costa Transportation Authority. III. Reasons for Recommendations and Bacl�ground: SkyTel had radio equipment mounted on a building from which they have been displaced. Bishop Wisecarver is located in a building from which they are being displaced because of the highway- widening project. The payments are part of the relocation entitlement required by government Code § 7260, et. Seq. IV, Consequences of Negative Action: The County will not be in.compliance w' tate and Federal law. Continued on Attachment: SIGNATURE: COMMENDATION OF COUNTY AD ST OR RECOMMENDATION OF BOARD COM ✓APPROVE OTHER SIGNATURES}: . ACTION OF BO ON I A N F I A R V 7 2 0 0 3�,PPROVED AS RECOMMENDED X X OTHER VOTE OF SUPERVISORS XX UNANIMOUS(ABSENT ) 1 hereby certify that this is a true and correct AYES: NOES: copy of an action taken and entered on the ABSENT: ABSTAIN: minutes of the Board of Supervisors on the CS:eh date shown. G:\GrpData\RealProp\2002-Files\B©s&RES\\BOBishopWisecarver.doe JANUARY 07 Div: Public Works(R/'} ATTESTED � 03 Contact: Cheryl Sousa(313-2223) JOHN SWEETEN,Clerk of the Board of cc; County Administrator Supervisors and County Administrator Auditor-Controller(via R/P) P.W.Accounting B De L.Dalziel,Adm. y �" Deputy