Loading...
HomeMy WebLinkAboutMINUTES - 12162003 - C102 TO: REDEVELOPMENT AGENCY , ,3 Contra .pax FROM: JOHN SWEETEN � COSLCI EXECUTIVE DIRECTOR • County DATE: December 16, 2003 ,,� SUBJECT: Rodeo Waterfront Predevelopment Assessment Consultant Contract with Ninyo and Moore SPECIFIC REQUEST(S)OR RECOMMENDATION{S}&BACKGROUND AND JUSTIFICATION RECOMMENDATION: APPROVE and AUTHORIZE the Director of Redevelopment to execute a contract with Ninyo and Moore, in the amount of $300,000 to provide a predevelopment assessment for the Rodeo Waterfront, for the period 'December 15, 2003 through December 31, 2005. FINANCIAL IMPACT: NO General Funds are involved. The Contractor will be funded through U.S. Environmental Protection Agency (EPA) grant funds, Community Development Block Grant (CDBG) funds, and Rodeo Redevelopment Project Area funds. CONTINUED ON ATTACHMENT: Z YES SIGNATURE: w 2-RECOMMENDATION OF EXECUTIVE DIRECTOR ❑ RECOM EN ATION AGENCY C MITTEE a-APPROVE ❑OTHER SIGNATURE{S}: I ACTION OF AG ON ijac 16 2003 I APPROVED AS`I`tECOMMENDED E] OTHER ❑ VOTE OF SUPERVISORS: I HEREBY CERTIFY THAT THIS IS A TRUE AND CORRECT COPY OF AN ACTION TAKEN AND X UNANIMOUS{ABSENT Dane } ENTERED ON THE MINUTES OF THE REDEVELOPMENT AGENCY ON THE DATE AYES: NOES: SHOWN. ABSENT: ABSTAIN: ATTESTED Contact: Dwc r 16, 2003 JOHN SWEETEN,AGENCY SECRETARY cc: CAO County Counsel Redevelopment Agency ,' By: eputy BACKGROUND: The Rodeo Waterfront is critical component of Rodeo's revitalization effort. The Waterfront was identified as a priority for Redevelopment during the Redevelopment Pian Adoption process. The County adopted the Rodeo Downtown/Waterfront Specific Plan (Specific Plan) in 1991 that outlined broad goals and policies for revitalization that include capitalizing on Rodeo's waterfront location as a major focal point, visitor attraction, community gathering place and amenity to commercial and residential uses. In 2001, the Agency brought together representatives from the Rodeocommunity, regulatory agencies, developers, and other interested parties to identify the barriers to implementation of the Specific Plan. The primary obstacles included uncertainty related to environmental contamination, the regulatory environment and const associated with dredging the marina, and the economic feasibility of a revitalization plan. The Redevelopment Agency has secured funding from the US Environmental Protection Agency (EPA) and the County Community Development Block Grant Program (CDBG) to further study the environmental contamination and the marina siltation. The Agency issued an RFP for a Predevelopment Assessment team on September 17, 2003 that included an environmental consultant, a marina engineer, and an economic consultant. The goal of the Predevelopment Assessment is to provide necessary resources needed to create a development plan for a revitalized waterfront that is a regional destination with an active marina, waterfront recreation activities, retail opportunities, and parks. 'Through written proposals and an interview process, a selection team chose Ninyo and Moore as the team leader for the waterfront predevelopment assessment. The consultant team also includes Moffat and Nicol Engineers for the marina study and Keyser Marston as the economic consultant. Ninyo and Moore was selected because of their strong understanding of the relationship of this project to the overall community revitalization goals, project management skills, and working relationship with the Environmental Protection Agency Brownfields program. The Scope of Work for the Predevelopment Assessment process includes: o Project management; o A community outreach program; a Phase I and If Environmental Assessment; o Preparation of an environmental remediation plan; o A marina study which will evaluate the feasibility and process to dredge the Rodeo marina and a plan to maintain the marina in a sustainable manner; and o A detailed economic strategy to implement the team's recommendations.