HomeMy WebLinkAboutMINUTES - 10222002 - C80 TO: BOARD OF SUPERVISORS
FROM: MAURICE SHIU, PUBLIC WORKS DIRECTOR
DATE: October 22, 2002
SUBJECT: Terminate the emergency action regarding the repair of the erosion along Wildcat
Canyon Road as recommended by the Public Works Director, Orinda area. [CDD-
CP # 02-03] (District 11) Project Nos.: 0672-6U2550-02 & 0572-6R6387-02
Specific Request(s) or Recommendation(s) & Background & Justification
i. RECOMMENDED ACTION:
TERMINATE the emergency action taken by the Beard of Supervisors on June 18, 2002,
pursuant to Public Contract Code Sections 22035 and 22050, to repair the erosion along
Wildcat Canyon Road, Orinda area.
Continued on Attachment: X SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
TRECOMMENDATION OF BOARD COMMITTEE
®APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON1 22 02APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT I\UE )
AYES: NOES:
ABSENT: ABSTAIN:
NE_:mp
G:\GrpData\Const\BO\2002\10-October\W€ldcat Canyon Rd Siide Repair Termination.doc
Orig.Div: Public Works(Design Division)
Contact: dell Leary (313-2278) 1 hereby certify that this is a true and correct
C: E.Kuevor,CAO copy of an action taken and entered on the
Auditor-Controller
Community Development minutes of the Board of Supervisors on the
PW Accounting date Shown.
Construction
ATTESTED: OCMBM 22, 20D2
John Sweeten, Clerk of the Board of
Supervisors and County Administrator
B
Y ,
Deputy
SUBJECT: TERMINATE the emergency action regarding the repair of the erosion along
Wildcat Canyon Road, Orinda area. [CIT-CP # 02-03] (District 11) Project Nos.:
0672-6U2550-02 & 0672-6R6387-02
DATE: October 22, 2002
PAGE: 2
11. Financial impact:
Estimated cost is $542,955 (100% Local Road f=unds). Final costs pending submittal of
billing from Condon-Johnson & Associates.
iii. Reasons for Recommendations and Background:
A. On June 18, 2002, the Board of Supervisors declared an emergency and authorized
the Public Works Director to proceed in the most expeditious manner to repair the
erosion and failed pavement.
B. Repair status:
Condon-Johnson &Associates has completed the shoulder repair along a portion of
Wildcat Canyon Road consisting of stabilization piles and geogrid reinforced earth
embankment, with this work completed the shoulder repair has been repaired,
therefore the Emergency Action may be terminated.
IV. Consequences of Negative Action:
A negative action would have no impact on the replacement of the structure.