HomeMy WebLinkAboutMINUTES - 10222002 - C79 TO: BOARD OF SUPERVISORS
FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR
GATE: October 22, 2002
SUBJECT: TERMINATE the emergency action regarding the repair of the erosion along
Carquinez Scenic Drive as recommended by the Public Works Director,
Crockett area. [CDD-CP # 02-02] (District Il) Project No.:, 0672-6U2526-02
SPECIFIC REQUEST(S)OR RECOMMENDATIONS)&BACKGROUND AND JUSTIFICATION
1. Recommended Action:
TERMINATE the emergency action taken by the Board of Supervisors on June 4,
2002, pursuant to Public Contract Code Sections 22035 and 22050, to repair the
erasion along Carquinez Scenic Drive, Crockett area,
Continued on Attachment: X SIGNATURE:
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
—APPROVE �OTHER
SIGNATURE(S)-
ACTION OF BOARD ON ocTO BEP, 22, 2002 APPROVED AS RECOMMENDED OTHER
OTE OF SUPERVISORS
UNANIMOUS (ABSENT NOW )
AYES: NOES:_
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct copy of an
G:\G p action taken and entered on the minutes of the Board
RepairDermin tion.d\2JC72i1�-Octo�er\Oarquinez Scenic Drive SI deo f Supervisors on the Gate shown.
Repair"rermination.doc p
Orig.Div:Public Works(Design)
Contact: B.Louis-313-2245
c: M.Hollingsworth,Design ATTESTED: OCTOBER 22, 2002
Public Works Accounting JOHN SWEETEN, Clerk of the Board of Supervisors
and County Administrator
e �
By Deputy
SUBJECT: TERMINATE the emergency action regarding the repair of the erosion along
Carquinez Scenic Drive be terminated, Crockett area. [CDD-CP # 02-02]
(District ll) Project No.: 0672-6U2526-02
DATE: October 22, 2002
PANE 2
II, Financial Impact:
Estimated cost is $215,500 (100% Local Road Funds). Final costs pending
submittal of billing from Up Grade Construction & Drilling, Inc.
Ill. Reasons for Recommendations and Background:
A. On June 4, 2002, the Board of Supervisors declared an emergency and
authorized the Public Works Director to proceed in the most expeditious mariner
to repair the erosion and failed pavement.
S. Repair status:
Up Grade Construction & Drilling, Inc. has completed the erosion repair
along Carquinez Scenic Drive consisting of constructing a cantilever retaining
wall with concrete piles, therefore the Emergency Action may be terminated.
Ill. Consequences of Negative Action:
A negative action would have no impact on the replacement of the structure.