TO: BOARD OF SUPERVISORS
FROM: MAURICE SHIU, PUBLIC WORKS DIRECTOR
DATE: October 8, 2002
SUBJECT: CONTINUE the emergency action originally taken by the Board of Supervisors on
June 18, 2002 regarding the repair of the erosion along Wildcat Canyon Road, as
recommended by the Public Works Director, Orinda area.
[CDD-CP # 02-03] (District 11) Project Nos.: 0672-602550-02 & 0672-6R6387-02
Specific Request(s) or Recommendations) & Background & Justification
1. RECOMMENDED ACTION:
DETERMINE that there is a need to continue the emergency action taken by the Board of
Supervisors on June 18, 2002, pursuant to Public Contract Code Sections 22035 and
22050, to repair the erosion along Wildcat Canyon Road, Orinda area,
Continued on Attachment: X SIGNATURE: >j
ECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S): -`'
ACTION OF BOAR6 t N APPROVED AS RECOMMENDED X OTHER
October 8, 2002
VOTE OF SUPERVISORS
X UNANIMOUS(ABSENT Ione }
AYES: NOES:
ABSENT: ABSTAIN:
NL:mp
G:\GrpData\Const\BO\2002\10-October\Wildcat Canyon Rd Slide Repair 5.doc
Orig.Div: Public Works(Design Division) I hereby certify that this is a true and correct
Contact: Neil Leary (313-2278) Copy of an action taken and entered on the
C: E.Kuevor,CAO minutes of the Board of Supervisors on the
Auditor-'Controller
Community Development date shown.
PW Accounting
Construction
ATTESTED: October 8, 2002
John Sweeten, Clerk of the Board of
Supervisors and County Administrator
By
Deputy
SUBJECT: CONTINUE the emergency action originally taken by the Board of Supervisors on
June 18, 2002 regarding the repair of the erosion along Wildcat Canyon Road, as
recommended by the Public Works Director, Orinda area. [CDD-CP # 02-031
(District 11) Project Nos.: 0672-6U2550-02 & 0872-6R6387-02
DATE: October 8, 2002
PAGE: 2
H. Financial Impact:
The total estimated contract cost is $616,000, funded by Local Road Funds (100%).
Ill. Reasons for Recommendations and Background:
A. On June 18, 2002, the Board of Supervisors declared an emergency and authorized
the Public Works Director to proceed in the most expeditious manner to repair the
erosion and failed pavement.
B. Repair status:
The project was awarded to Condon-Johnson of Oakland, construction
began August 8, 2002.
This project is approximately 75% complete.
IV. Consequences of Negative Action:
Non-concurrence of the above recommendation will significantly delay repair of the
roadway, prolonging impacts to local access and could result in the loss of the entire
traveled way.