TO: REDEVELOPMENT AGENCY/BOARD OF SUPERVISORS • , Costa
FROM: Phil Batchelor, Executive Director ouf•y
Dennis M. Barry, AICP, Director of Community Development
DATE: October 24, 2000
SUBJECT: Parker Avenue Reconstruction, Rodeo
SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
APPROVE and AUTHORIZE the Deputy Director-- Redevelopment to sign a contract not to
exceed$1,300,000 between the Redevelopment Agency and Contra Costa County forfunding
of the design and construction of the Parker Avenue reconstruction project, Rodeo.
APPROVE and AUTHORIZE the Director of Public Works to sign a contract not to exceed
$1,300,000 between the Redevelopment Agency and Contra Costa County for funding of the
design and construction of the Parker Avenue reconstruction project, Rodeo.
FISCAL IMPACT
No General Fund monies are involved. The total contract amount is$1,300,000 and will come
from the Rodeo Redevelopment Project Area capital portion of the tax increment and bond
proceeds funds. This project is included in the Agency's budget. The project is to be
combined with the Parker Avenue utility under grounding project to realize economic
efficiencies.
CONTINUED ON ATTACHMENT: X YES SIGNATURE: eel
� COMMENDATION OF COUNTY ADMINISTRAOFqtXECUTI DIRECTO
RECOMMENDATION OF BOARD/AGENCY COMMITTEE -A ROVE OTHER
SIGNATURE( :
ACTION OF CY/ BOARD ON Octnha 24, 2MQ APPROVED AS RECOMMENDED
OTHER
VOTE OF COMMISSIONERS/SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A
X UNANIMOUS (ABSENT none ) TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVISORS/AGENCY ON THE
Contact: Jim Kennedy DATE SHOWN.
3-1255
cc: County Administrator ATTESTED Otto er 2A, 20QO
County Counsel PHIL BATCHELOR, CLERK OF
Public Works - TE THE B RD OF(SUPERVISORS/
orifi: Redevelopment Agency AG SECR RY
BY A DEPUTY
W: \Personal\BoardOrders\9.26.tollagreement
BACKQROUNb/REASONS FQR RECOMMENDATHORS
The reconstruction of Parker Avenue, including the undergrounding of utilities, has
long been a desire of the community of Rodeo. The 1997 Rodeo
Downtown/Waterfront Specific Plan also contemplated the provision of streetscape
improvements (street furniture, decorative street lighting, and landscaping) as an
initial step to revitalizing the downtown area. An opportunity to combine Agency
Funds, Utility Undergrounding Funds, and Tosco Transportation Mitigation Funds to
accomplish this approximate $2.9 million project exists at this time. The project
design phase is expected to take the bulk of 2001, with an anticipation of
construction in the spring/summer of 2002.
JK:ln