HomeMy WebLinkAboutMINUTES - 01261999 - C12 To: BOARD OF SUPERVISOR, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: JANUARY 26, 1999
SUBJECT: Approve Plans and Specifications and Advertise for bids for the San Raman Creek
Improvements -- Phase 2 Project, in the Alamo area.
Project No. 7520-688562, CDD-CP# 95-64
Specific Request(s) or Recommendation(s) & Background & Justification
I. RECOMMENDED ACTION:
APPROVE the Plans and Specifications for San Ramon Creek Improvements ® Phase 2 Project
and
ADVERTISE for bids to be received on Tuesday, March 2, 1999; at 2:00 p.m.
DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with
Section 22037 of the Public Contract Code at least 21 days prior to bid opening.
Continued on Attachment: X SIGNATURE.
RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON ! q I APPROVED AS RECOMMENDED
VOTE OF SUPERVISORS
— UNANIMOUS (ABSENT �t )
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct
copy of an action taken and entered on the
G:1Grp1,a1a\,esignTCRMS1B0forms1,31A minutes of the blsoarU of Supervisors on the
Orig.Div: Public Works(Resign Division) date shown.
Contact: Diane Soc o(313-2308)
cc: CountyAd„inishator - - :
Attn: E K evor
Auditor-controller PERIL. BAT i EL.OR, irk of tine Board
PW Accounting
Construction of f Supervisors and C unt Administrator
Community Development
By � .' Deputy
SUBJECT: Approve Plans and Specifications and Advertise for bids for the San Ramon geek
Improvements — Phase 2 Project, in the Alamo area.
Project No. 7520-688562, CUD-CP# 95-64
DATE: JANUARY 26, 1999
MAGE: 2
11. FINANCIAL IMPACT:
The estimated contract cost of the project is $1,350,000, funded by Flood Control Zone 3B Funds
(100%).
111. REASONS FOR RECOMMENDATIONIBACKGROUND:
The project is needed to reduce flooding potential and bank erosion within and downstream of the
project area.
The Chief Engineer has filed with the Board of Supervisors the Plans and Specifications for the
project.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have
been filed with the Clerk of the Board and copies will be made available to any interested party upon
request.
The Board reviewed and approved the final EIR for the San Ramon Creek Chaney Road to Livorna
Road Improvement Project (PW85-55) on June 16, 1987 and Addendum #1 (1/12/93, CP92-84),
Addendum #2 (5/2/95, CP95-29), Addendum #3 (10/17/95, CP95-58) and Addendum #4 (12/12/95,
CP95-64) and certified that the Final Environmental Impact Report for the project was completed in
compliance with the California Environmental Quality Act. The Final EIR was presented to the
Board and the Board reviewed and considered the information contained in it, and found that the
project will have significant effects on the environment, each of which is determined to be mitigated
or unavoidable. The findings for the San Ramon Creek Flood Control Project between Chaney and
Livorna Roads were made by the San Ramon Valley Regional Planning Commission to comply with
Section 15091 of the CEQA Guidelines and incorporated herein by reference.
IV. CONSEQUENCES OF NEGATIVE ACTION:
If the project is not approved for advertising, it will not be constructed.
Project Name: SAN RAMON CREEK IMPROVEMENTS -PHASE 2
Project Number: 7520-688562
Contra Costa County
Flood Control and Water Conservation District
255 Glacier Drive,Martinez, California 94553-4897
NOTICE TO CONTRACTORS
The Chief Engineer will receive sealed bids at the Public Works Department, C.C. Rich
Building, 255 Glacier Drive, Martinez, California 94553-4897, until 2 o'clock p.m., on March 2,
1999 at which time they will be publicly opened and read, for: SAN RAMON CREEK
IMPROVEMENTS—PHASE 2.
General work description: The work to be done consists, in general, of mass excavation and
placing rock slope protection, constructing gabion walls, concrete walls, a drop structure;
constructing fencing and such other items or details, not mentioned above, that are required by the
plans, Standard Specifications, or these special provisions to be performed, placed, constructed or
installed.
Engineer's cost estimate: $1,350,000
A pre-bid meeting will be held on Tuesday, February 16, 1999 at 10:00 a.m. at the project site
(San Ramon Creek at the Livorna Road Bridge). Prospective bidders attendance is recommended
but not mandatory.
Contract Documents, including plans and specifications, may be viewed and/or obtained at the
Public Works Department, C.C. Rich Building, 255 Glacier Drive, Martinez, California 94553-
4897, Monday - Thursday (7:00 a.m. - 12 Noon and 1:00 p.m. - 5:00 p.m.) (closed Fridays). To
obtain a bid packet, including plans, specifications, cross sections and geotechnical data, a service
charge is required in the amount of$45 (sales tax included). The bid packet mamas he ordered bX
mail for an additional_shipping and handling fee of $5,00. Checks shall be made payable to
'The County of Contra Costa' and be mailed to the above address. The Agency does not guarantee
the arrival of the bid packet in time for bidding. The bid packet will not be sent overnight mail.
This contract is subject to state contract nondiscrimination and compliance requirements
pursuant to Government Code, Section 12290.
The Contractor shall possess a Class A or Class C-12 Contractor's License at the time the
Contract is awarded.
Bids must cover the entire project, and neither partial nor contingent bids will be considered.
The successful bidder shall furnish a payment bond and a performance bond.
The Board has ascertained the general prevailing rate of wages applicable to this work. The
prevailing rate of per diem wages is on file with the Clerk of the Board of Supervisors, and is
incorporated herein by reference thereto, the same as if set forth in full herein. For any
classification not included in the list, the minimum wage shall be the general prevailing rate for
Contra Costa County.
The bid opening date may be extended by addendum issued by the Agency no later than
February 26, 1999, in which case any bids submitted for the original bid opening will be
returned unopened and sealed bid proposals for the extended bid opening shall be submitted
on or before March 16, 1999 at 2:00 p.m., and will be opened, read and recorded at the
same place specified above. All proposals received late will be returned unopened.
The said Board reserves the right to reject any and all bids or any portion of any bid
and/or waive any irregularity in any bid received.
For questions regarding the project contact Diane Spoto, Design Division, at (925) 313-
230$.
By order of the Board of Supervisors as the governing body of the Contra Costa County
Mood Control and Water Conservation District
Phil Batchelor
Clerk of the Board of Supervisors and County Administrator
By
Deputy
Dated:
Publication dates: