HomeMy WebLinkAboutMINUTES - 10211997 - C6 C.V
gTO: BOARD OF SUPERVISORS, AS GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: October 21, 1997
SUBJECT: Approval of the project contingency fund increase for the San Ramon Creek Slide Repair
project, Project No. 7520-61391-74-97, San Ramon area.
Specific Request(s) or ecomrnen a tons Background us i tca ton
I. Recommended Action:
APPROVE a project contingency fund increase of$20,000.00.
II, Financial Impact:
The project contingency fund needs to be increased to cover the cost of necessary additional
work. The source of funds is Flood Control District Zone 3B.
Continued on attachment: X yes SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: /b -Al —/71), APPROVED AS RECOMMENDED_ OTHER
t hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supervors on L7o date shown.
xms'mo:n C� 9 97
PHIL BATCHELOR,Clerk of tho oard
�offsu�pervisors acid County Administrator
VOT OF SUPERVISORS "''"""
UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
Contact: Joseph P. Murphy, (510) 313-2321
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works
- Accounting, R. Gilchrist
- Construction, R. Bruno
- Design
Contractor
TT:tt
G:\CONST\BO\SRS-21.T10
game: San Ramon Creek Slide Repair c@ Drop Structure 8 L�t6i
Proj. No. 7520-6B91-74-97
Board Date: October 21, 1997
Page: 2 of 2
III. Reasons for Recommendations and Background:
The cost of necessary additional work exceeds the project contingency fund and Board
APPROVAL is necessary to increase the contingency fund.
IV. Oonsequences of Negative Action:
The lack of approval would preclude payment for work that was performed by the contractor in
good faith.