HomeMy WebLinkAboutMINUTES - 01141997 - C98 • TO: BOARD OF SUPERVISORS 0. 67F FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: JANUARY 7, 1997 SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of"Hill 310" Land Creep, Bay Point Project No.: 4500-6G5094 SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION 1. Recommended Action: DETERMINE that there is a need to continue the emergency action taken by the Board of Supervisors on June 4, 1996 pursuant to Public Contract Code Sections 22035 and 22050, to repair the "Hill 310" Land Creep, Bay Point. II. Financial Impact: Total cost of repairs cannot be fully determined at this time, but staff is developing an estimate for completion of the repair. III. Reasons for Recommendations and Background: A. On February 26, 1996, Public Works and Building Inspection were notified that cracks were occurring in Beaulieu Court. The County hired a geotechnical firm to identify the cause of the slide, and recommend and direct remedial actions to mitigate land movement. B. On March 19, 1996 the Board of Supervisors concurred in the County Administrator's proclamation of a local emergency. C. On June 4, 1996 the Board of Supervisors declared an emergency and authorized the Public Works Director to proceed in the most expeditious manner to repair the area subject to creep. Continued on Attachment: X SIGNATUR _RECOMMENDATION OF COUNTY ADMINISTRATOR _RECOMMENDATION OF BOARD COMMITTEE —APPROVE —OTHER SIGNATURE (S): ACTION OF BOARD ON ®t—I "1 9 APPROVED AS RECOMMENDED_OTHER_ VOSE OF SUPERVISORS �/ UNANIMOUS (ABSENT ) AYES: NOES: ABSENT: ABSTAIN: JPM:tt g\const\BO\H310-7.t1 Orig.Div: Public Works(Construction) I heraby ewft that trate h a true and Dopy Contact: Joseph P.Murphy(313-2320) at action taken and entered on the mtnutee of j�a cc: CAO Board of Supervlsora on the date shown. Auditor/Controller ATTESTED County Counsel atg 0 uMtyAdmen ' boaW GMEDA , Design Div. Construction Div. 0 Maintenance Div. Determine the Need to Continue the Emergency Action Regarding the Repair of"Hill 310"Land Creep January 7, 1997 Page Two Ill. Reasons for Recommendations and Background (cont'd): D. Repair status: 1. Ford Construction Company, Inc. has completed the earth buttress and only a minor contract item remains. 2. Judd Drilling is under contract to complete the second phase of the repair consisting of a drainage gallery. This work began September 25, 1996 and about eighty-five percent of the work has been completed. Due to inclement weather and the unavailability of specialized equipment, the completion of this project will be delayed. IV. Consequences of Negative Action: Repair work would not be completed before next winter.