HomeMy WebLinkAboutMINUTES - 12091997 - D15 � Contra
Costa
TO: BOARD OF SUPERVISORS _
County
FROM: DENNIS M. BARRY, AICP
COMMUNITY DEVELOPMENT DIRECTOR
DATE: DECEMBER 9, 1997
SUBJECT: REPORT ON ORDINANCE 96-50 (CHAPTER 84-63) [LAND USE PERMITS FOR
DEVELOPMENT PROJECTS INVOLVING HAZARDOUS WASTE OR HAZARDOUS
MATERIALS] CODE COMPLIANCE ISSUES
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
ACCEPT Report from the Community Development Director.
FISCAL IMPACT
None
BACKGROUND
!, Status of Complaints & Investigations: The County has received two letters alleging
!, violations of the Good Neighbor Ordinance, i.e., Chapter 84-63 of the County Code,
as amended by Ordinance 96-50. One letter (September 5, 1997) from
Communities for a Better Environment, alleges that Shell Martinez Refining
Company (Shell) is conducting a major maintenance project without a land use
permit in violation of Chapter 84-63. The second letter (November 11, 1997) from
four parties alleges that there are (or are about to be) similar violations at both Tosco
refineries and an additional violation at Shell.
CONTINUED ON ATTACHMENT: YES SIGNATURE
ACTION OF BOARD ON December 9, 1997 APPROVED AS RECOMMENDED x OTHER_
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A TRUE
x UNANIMOUS (ABSENT ------ ) AND CORRECT COPY OF AN ACTION TAKEN
AYES: NOES: AND ENTERED ON THE MINUTES OF THE
ABSENT: ABSTAIN: BOARD OF SUPERVISORS ON THE DATE
SHOWN.
Contact: Debra Sanderson, CDD (510/335-1208) ATTESTED December 9, 1997
cc: Community Development Department (CDD) PHIL BATCHELOR, CLERK OF
County Administrator THE BOARD OF SUPERVISORS
County Counsel AChristine
UNTY AD INIST R
Health Services Director
DS\
aw\misc-1:\code.bo m er
aw\misc-1:\code.bo
Good Neighbor Ordinance-Code Enforcement
December 9, 1997
Page 2
Investigations of the complaints against Shell have recently been completed. This
first investigation has been complex and time consuming due to the issues described
below. The investigation of the complaint against Tosco has just begun. There are
18 process units involved on the Shell site. We have yet to determine the numbers
involved on the Tosco sites.
Regulatory Background: Chapter 84-63 requires land use permits for certain
development projects involving hazardous waste or hazardous materials.
• Effective Date: The law took effect April 1, 1997.
• Exemption during the first year: Section 63.604(h) exempts from this chapter
a "major maintenance project for which construction has commenced prior to
June 1, 1997, and is completed by January 1, 1998." These deadlines were
tolled 70 days by court order signed on April 1, 1997. Thus the applicable
deadlines are August 9, 1997 and March 12, 1998, respectively.
• Major Maintenance Project: Chapter 84-63.421.5 defines a major
maintenance project as "the scheduled, periodic cleaning, inspection, repair
of process units, piping, or process or storage vessels which handles
hazardous materials or hazardous waste. . . . "
Issues: The two complaints against Shell have raised the following key issues:
1. What constitutes a single a major maintenance project: The definition specifies
those activities included within a major maintenance project (i.e., cleaning,
testing, and repair) and indicates that a single project may involve multiple
units, vessels and piping. However, County code does not provide guidance
on how to determine if a group of units scheduled for maintenance is one or
more such projects.
County Precedent. There is no precedent under the revised Chapter 84-63.
The administrative practice for previous refinery land use permits (I. e., the
Clean Fuels Projects) treated as one project all changes in the refinery
necessary and essential to construct and operate the proposed modification
or expansion of the facility. Thus, these projects included changes in
throughput, changes in types of materials to be stored in existing tanks, wharf
modifications to receive or ship products, as well as tank and unit construction
and modifications. If the activities were broadly linked and would occur in a
closely related time frame, then the administrative practice was to treat the
activities as one project. Under CEQA, the project definition is drawn broadly,
so as to avoid "piecemealing", since "piecemealing" projects can make it
difficult to assess the full impacts of proposed actions.
2. What constitutes "commencement of construction" for a major maintenance
project? In essence, what activities are considered "construction" for a major
maintenance project? County code provides no definition of construction, and
major maintenance projects do not contain grading, which often triggers the
beginning of construction for a major development project.
A broad interpretation of construction would include on-site activities
necessary and essential to the shut-down, such as installation of temporary
electrical services, temporary piping, on-site fabrication, and testing. It would
include any activities — such as testing —which are included in the definition
of a major maintenance project and are directly related to the project in
question. In addition, it appears that a broad interpretation is necessary to
make the exemption in Section 63.604(h) meaningful. The exemption requires
aMmisc-1 Acode.bo
Good Neighbor Ordinance-Code Enforcement
December 9, 1997
Page 3
commencement of construction prior to August 9 (the original language
required it prior to June 1, 1997) and completion prior to March 12, 1998
(originally January 1, 1998). It is staffs understanding that local refineries do
not schedule unit shut-downs in the summer, since that is their peak
production period, although they do engage in pre-shutdown construction-type
activities during the summer. Thus, if unit shut-down is required to trigger this
exemption, then no refinery can avail itself of this exemption and the
exemption becomes meaningless.
A very narrow interpretation of construction would only include activities
triggered by unit shut-down, such as opening and replacing valves, cleaning
opened equipment, replacing pipes, etc. This interpretation assumes that the
only construction activities within a maintenance project are those that involve
direct changes to operating equipment. The Ordinance defines a major
maintenance project to include actions (such as testing) taken prior to unit
shut-down. (See 84-63.421.5, quoted above.)
County Precedent. There is no precedent under the recently revised Chapter
84.63. The administrative practice for previous refinery land use permits (I.
e., the Clean Fuels Projects) used a broad definition of construction activities.
Enforcement of these permits treated as construction the installation of
temporary electrical service, construction contract firm traffic, installation of
temporary construction offices, and the use and location of project "lay down"
and fabrication areas. These activities were evaluated under the Projects'
EIRs and controlled by the permits' conditions of approvals. The
administrative practice was to treat the whole of the project as construction,
until the new or modified units were fully incorporated into refinery operations.
However, on-site testing, engineering, and planning would not previously have
been considered "construction".
3. Current County Staff Approach:
Consistent with previous administrative practice, County staff currently
considers the scheduled maintenance of a number of units as a single project
if the units are functionally related, if the work is scheduled for approximately
the same time frame, and if the work is continuous.
County staff currently uses a broad interpretation of construction activities for
the following reasons: (1) A broad definition is more consistent with previous
Community Development Department administrative practices than a narrow
one, (2) a narrow interpretation would seem to render the exemption
meaningless, which appears to contradict the legislative intent of Ordinance
96-50, and (3) activities defined by the Ordinance to be part of the major
maintenance project (i.e., testing and cleaning) should be considered in
determining when construction has commenced on that type of project.
Based upon a careful review of Shell's records, and given the foregoing
analysis of Sections 84-63.4 and 84-63.604(h), staff has concluded that Shell
is not currently in violation of the provisions of Ordinance 96-50 (Chapter 84-
63). Investigation of the two Tosco refineries is ongoing. Staff anticipates
being able to provide a further status report in six to eight weeks time in
conjunction with a report requested in the December 2, 1997 Board Order
introduced by Supervisor Gerber.
It is likely that staffs determination will be appealed to the Board of
Supervisors. If so, it will be scheduled for hearing consistent with existing
administrative procedures.
aw\misc-1 Acode.bo