HomeMy WebLinkAboutMINUTES - 01091996 - C2 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: January 9, 1996
SUBJECT: Approval of Contract Change Order No. 2 for the Kirker Pass Road Median Barrier
Extension Project, Project No. 0662-6R4260-94, Pittsburg area.
Specific Requests or Recommendation(s)&Background&Justification
I. Recommended Action:
APPROVE Contract Change Order No. 2 in the approximate amount of $22,000.00 and
AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, M.
Bumgarner, Inc. for additional work performed.
II. Financial Impact:
The project contingency funds are sufficient to cover the change order costs. The project is funded
by HES (90%) and Local Road Funds (10%).
III. Reasons for Recommendations and Background:
The cumulative total of Contract Change Orders Nos. 1 & 2 exceeds $25,000.00, requiring Board
approval. Additional work was done to provide public safety.
IV. Consequences of Negative Action:
The lack of approval would preclude payment for work that was performed in good faith.
Continued on attachment: _yes
SIGNATOR
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: 4 APPROVED AS RECOMMENDED ✓ OTHER
VOT�F OF SUPERVISORS
UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
Contact: Joseph P. Murphy, (510) 313-2321
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller 1 hereby cortify that this is a true and correct copy of
Public Works an action taken and entered on the minutes of the
- Accounting, R. Gilchrist Bourd of Supe isors on the date shown.
- Construction, R. Bruno ATTESTED:
- Design of Supervvi rss and C my of
nstra or
Contractor
By .Deputy
JF:tt
g:\CONST\BO\KPM-9.t1