TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: FEBRUARY 13, 1996
SUBJECT: APPROVE AMENDMENT TO JOINT EXERCISE OF POWERS AGREEMENT WITH THE
CITY OF CLAYTON FOR PHASES II AND III OF SPECIAL PROJECT TO REMOVE
POLLUTANTS FROM RESIDENTIAL STORMWATER RUNOFF
Project No. 0929-6X7046, CLAYTON AREA
Specific Request(s)or Recommendation(s)&Background&Justification
I. Recommended Action:
APPROVE and AUTHORIZE Chief Engineer to amend the existing joint exercise of powers
agreement with the City of Clayton to complete Phases II and III of a special project for the design,
development and testing of control structure and filter to remove pollutants from stormwater runoff
generated by a fifty-four (54) unit residential subdivision.
II. Financial Impact:
There will be no impact to General Fund. Joint exercise of powers agreement is funded with
stormwater utility fees collected by the Flood Control District on behalf of the nineteen (19)
municipalities in the Contra Costa Clean Water Program.
Continued on attachment: x SIGNATURE: `
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: 02/13/1996 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT IV)
AYES: NOES:
ABSENT: ABSTAIN:
ELG:sl
g:\FLDCTL\BO\clayton.t2
Orig.Div.: Public Works (CCCWP)
Contact:Donald P.Freitas(510)313-2373
cc: County Administrator
Community Development Ihereby cortifythat thisIsatrusend
ee�rrectcopyof
Building Inspection an action taken and entered on the minutes of the
County Counsel Board of Superyisom on the date shown.
County Assessor ATTESTED: FEBRUARY 13, 1996
County Treasurer-Tax Collector PHIL BATCHELOR,Clerk of the Board
County Auditor-Collector of Supervisors and County Administrator
Chief Engineer
Accounting By , eputy
Engineering Services
SUBJECT: JOINT EXERCISE OF POWERS AGREEMENT WITH THE CITY OF CLAYTON FOR
SPECIAL PROJECT TO REMOVE POLLUTANTS FROM RESIDENTIAL STORMWATER
RUNOFF
Page -2-
111111. Reasons for Recommendations and Background:
The San Francisco Bay Regional Water Quality Control Board requires the nineteen (19)
municipalities in the Contra Costa Clean Water Program conduct special studies to determine
the effectiveness of best management practices (BMPs) in removing pollutants from
stormwater runoff. Runoff from new development and construction sites has proven to be an
important source of pollutants. As part of their municipal stormwater permit, municipalities
are constantly seeking effective BMPs that remove these pollutants in a cost efficient manner.
The City of Clayton contracted with Wollman & Associates to conduct a special study
evaluating control structures and filtration systems designed to remove oil and grease,
sediments and other pollutants. These control measures are incorporated into a fifty-four (54)
unit residential subdivision along Marsh Creek Road in the City of Clayton. Wollman &
Associates will conduct water quality tests to determine the effectiveness of the control
structures in removing pollutants. A written evaluation will be available for the municipalities
in the Contra Costa Clean Water Program
Phase I of the project was approved by the Board of Supervisors on June 20, 1995. Phase
was recently completed. The purpose of this amendment is to extend the joint exercise of
powers agreement to include Phases II and Ill.
All nineteen (19) municipalities in the Contra Costa Clean Water Program will jointly fund this
study through this agreement between the City of Clayton and the Flood Control District. The
Clean Water Program municipalities approved Phase II of the project on September 20, 1995.
The Contra Costa Clean Water Program municipalities will approve Phase III costs at a later
date.
IV. Consequences of Negative Action:
The San Francisco Regional Water Quality Control Board may find the Contra Costa Clean
Water Program is not conducting special studies as required in its Municipal NPDES
Stormwater Permit. The Regional Board has the authority to fine municipalities in.the Contra
Costa Clean Water Program up to $10,000 per day and $10 per gallon of discharge for non-
compliance with the permit.
�-13 - 9,6
AMENDMENT TO
JOINT EXERCISE OF POWERS AGREEMENT
BETWEEN CONTRA COSTA COUNTY FLOOD CONTROL
AND WATER CONSERVATION DISTRICT
AND CITY OF CLAYTON
Special Project to Remove Pollutants
from Residential Stormwater Runoff
1. Parties:
Effective June 18 , 1996 , the CONTRA COSTA COUNTY FLOOD
CONTROL AND WATER CONSERVATION DISTRICT, a body, corporate and
politic, hereinafter referred as "DISTRICT," and the CITY OF CLAYTON, a
municipal corporation, hereinafter referred as"CITY,"pursuant to Government Code
Section 6500 and following, mutually agree and promise to amend the Joint
Exercise of Powers Agreement Between Contra Costa County Flood Control and
Water Conservation District and City of Clayton, adopted July 18, 1995, as follows:
2. Change to Section 5 - Financial Responsibilities:
Add "DISTRICT shall pay for Phases II and III of the project as set forth in attached
Exhibit "A" which is incorporated here by this reference. Phase III costs will be
approved by the Contra Costa Clean Water Program Management Committee."
3. Change to Section 9 -Agreement Expiration:
Add "DISTRICT financial responsibility for Phase II of PROJECT shall expire on
June 30, 1997. DISTRICT financial responsibility for Phase III of PROJECT shall
expire on June 30, 1998."
CONTRA COSTA COUNTY CITY OF CLAYTON
FLOOD CONTROL AND WATER
CONSERVATION DISTRICT
By:
Michael ord. Yep=` ngineer Mayor
ATTEST: ATTEST: S' C ityrk
Phil Batchelor, Cler of the Board
of Supervisors and ounty
Administrator By:�
RECOMMENDED FOR APPROVAL RECOMMENDED FOR APPROVAL
J. Michael Walford, Chief Engineer
B By:
Deputy C of Engineer
By: By:
FORM APPROVED: ORM APPROVED:
Victor J. Westman, County Counsel IC A ey
S.By\ By:
Deputy
ELG:sl
g:\FLDCTL\NPDES\Contract\JEPACLA
04/15/96
STRANAHAN SPECIAL STUDY
PROJECT YEAR 2 WORK TASKS
Proposal time period: May 1996 to June 1997
PHASE H.
Task A: Testing of water quality during construction and initial occupancy of homes.
Includes,test during wet weather.
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $3,500
• City Engineer(contracted) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $750
• � City oversight of testing and review of results . . . . . . . . . . . . In-kind
Time period: May 1996 -March 1997
TotalTask A . ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . $4,250
Task B: Monitoring/Maintenance of control structure, cleaning/replacing filters as needed.
Assume three (3) full service cleanings at $1100 each: one (1)at start of rainy
season(October 1996), one (1) after first significant storm(November 1996-
January 1997), and one (1) in spring(February-April 1996)
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $3,300
• City maintenance staff inspect control structure for
proper operation monthly and after significant storms
(monthly inspection: October,November,December,January,
February,March,April) (Assume six(6) significant storms
October-April). Total inspections: thirteen(13) . . . . . . . . . In-kind
• City maintenance staff at the three full service cleanings
for education and training . . . . . . . . . . . . . . . . . . . . . . . . . . . . In-kind
• City staff preparation of public education material for
home buyers to be distributed at move-in . . . . . . . . . . . . . . . . In-kind
Time period: October 1996 -April 1997
Total Task B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3,300
Task C: Preparation of report on operation of control structure and results of construction/
initial occupancy period testing.
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $1,750
• City staff . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . In-kind
Time period: June 1997
Total Task C . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $1,750
Sub-totals by participant:
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $8,550
• City Engineer(contracted) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $750
Total . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $9,300
DATES 96\0695STRN.SS
STRANAHAN SPECIAL STUDY
PRELIMINARY YEAR 3 PROPOSAL AND WORK TASKS
Preliminary time period: July 1997 to June 1998
PHASE M.
Task A: Testing of water quality post construction after occupancy. Including, one test in
Fall 1997 and one in Spring 1998.
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $5,000
• City Engineer(contracted) . . . . . . . . . . . . . . . . . . . . . . . . . . . $1,000
• City oversight of testing and review of results . . . . . . . . . . . . In-kind
Time period: fall 1997-spring 1998
Total Task A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $6,000
Task B: Monitoring/Maintenance of control structure, cleaning/replacing filters as needed.
Assume three (3) full service cleanings at$1000 each: one (1) prior to rainy season
(September 1997), one(1) after first significant storm(November-December 1997),
and one(1) in spring(February-April 1998)
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $3,000
• City maintenance staff inspect control structure for
proper operation monthly and after significant storms
(monthly inspection: October,November,December,January,
February,March, April) (Assume six(6) significant storms
October-April).
Total inspections: thirteen(13) . . . . . . . . . . . . . . . . . . . . . . . In-kind
• City maintenance staff at the three full service cleanings
for education and training . . . . . . . . . . . . . . . . . . . . . . . . . . . . In-kind
Time period: October 1997-April 1998
Total Task B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3,000
Task C: Preparation of report on operation of control structure and results of post
construction period testing.
• Wollman Associates(contracted) . . . . . . . . . . . . . . . . . . . . . . . $1,500
• City staff . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . In-kind
Time period: June 1998
Total Task C . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $1,500
Sub-totals by participant:
• Wollman Associates (contracted) . . . . . . . . . . . . . . . . . . . . . . . $9,500
• City Engineer(contracted) . . . . . . . . . . . . . . . . . . . . . . . . . . . $1,000
Total . . . . . . . . . . . . . . . . . . $10,500
DATES96\0695strI SS
. . �-13-9b C • I -7
AMENDMENT TO
JOINT EXERCISE OF POWERS AGREEMENT
BETWEEN CONTRA COSTA COUNTY FLOOD CONTROL
AND WATER CONSERVATION DISTRICT
AND CONTRA COSTA COUNTY
Special Project To Develop Alternative Roadside
Vegetation Management Practices
1. Parties:
Effective May 21, 1996 , the CONTRA COSTA COUNTY FLOOD
CONTROL AND WATER CONSERVATION DISTRICT, a body, corporate and
politic, hereinafter,referred as"DISTRICT,"and the COUNTY OF CONTRA COSTA,
a political subdivision of the State of California, hereinafter referred as "COUNTY,"
pursuant to Government Code Section 6500 and following, mutually agree and
promise to amend the Joint Exercise of Powers Agreement Between Contra Costa
County Flood Control and Water Conservation District and Contra Costa County,
adopted July 20, 1995, as follows:
2. Change to Section 5 - Financial Responsibilities:
'Add "DISTRICT shall pay for Phases II and III of the project as set forth in attached
Exhibit "A" which is incorporated here by this reference. Phase III costs will be
approved by the Contra Costa Clean Water Program Management Committee."
3. Change to Section 9 -Agreement Expiration:
Add "DISTRICT financial responsibility for Phase If of PROJECT shall expire on
June 30, 1997. DISTRICT financial responsibility for Phase III of PROJECT shall
expire on June 30, 1998."
CONTRA COSTA COUNTY CONTRA COSTA COUNTY
FLOOD CONTROL AND WATER
CONSERVATION DISTRICT
By: By-
J'. ichael Wa , E neer -_ J_' ichael - order y
Public s Dire or
ATTEST: ATTEST:
Phil Batchelor, Clerk of the Board Phil Batchelor, Clerk of the Board
of Supervisors and County of Supervisors and County
Administrator Administrator
RECOMMENDED FOR APPROVAL RECOMMENDED FOR APPROVAL
J. Michael Walford, Chief Engineer J. Michael Walford, Public Works Director
B By:
Deputy C ief Engineer Be #jr Public Works Director
By: By:
FORM APPROVED: FORM APPROVED:
Victor J. Westman, County Counsel Victor J. Westman, County Counsel
By: ` A- Q&-
:/-� B YY
Deputy Deputy
ELG.sl
g:\FLDCTL\NPDES\Contract\JEPAccc.t1
April 15, 1996
CONTRA COSTA COUNTY PROPOSAL Januai:y 4 , 1995
PUBLIC WORKS DEPT. 7
METHODS:
I. EXTENSIVE SURVEY;field investigation; x 3 / year. . .YEAR I
A. identify potential beneficial & weedy species
B. quantify potentially weedy species
C. choose 8 test plot sites; four on San Pablo Dam
Road, and four on Bear Creek Road, which will be .used
to demonstrate revegetation.
D. analyze soil for pesticide residues to verify
suitability of planting.
E. analyze soil for textural and fertility parameters
II. LOCAL PLANT COLLECTIONS & PROPAGATION; for use in
revegetation. . .seeds collected in late summer-fall. . . . . . . . .YEAR 1
Propagated. . .
III. PLOT PREPARATION PRIOR TO PLANTING to reduce weed plant
population & seedbed reservoir. Test and quantify alternative
measures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . .YEAR 1
A. Cultivation
B. Hot water method
C. Flaming
D. Mowing
E. Wicking E
F. Spot Spraying
IV. PLANTING TECHNIQUE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .YEAR 2
A. SEEDS
B. PLUGS
C. 1 GALLON POTS
V. SPECIES MIMES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .YEAR. 2
A. GRASSES
B. FORBS
C. SHRUBS (upslope)
D. TREES (upslope)
VI. -MAINTAIN PLOTS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .YEAR 2-3
PRODUCTS: A. 8 DEMONSTRATION TEST PLOTS
B. MANUAL; *-HOW TO SET-UP A STUDY FOR VEGETATION
/REPORT MANAGEMENT USING DESIRABLE VEGETATION'
C. MANUAL; `HOW TO MAINTAIN DESIRABLE VEGETATION DURING
/REPORT ESTABLISEMENT'
D. MANUAL; `HOW TO IMPLEMENT VEGETATION MANAGEMENT
/REPORT USING DESIRABLE PLANT SPECIES'
COSTS NOT INCLUDING PROPOSED WORK IN KIND
YEAR 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ... . . . . . . . . . �6 4 .156.53 (Phase I)
YEAR 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $58 .176.53 (Phase II)
YEAR 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $49 ,062.50 (Phase III)
BAEFSKY & ASSOCIATES -2- RESOURCE MANAGEMENT CONSULTANTS
Exhibit "A"