Loading...
HomeMy WebLinkAboutMINUTES - 11141995 - C8 C-2, TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: November 14, 1995 SUBJECT: Approval of Contract Change Order No. 2 for the San Pablo Dam Rd. Slide Repair at Station 252+00, Project No. 0672-6R6523-93, EI Sobrante area. Specific Request(s)or Recommendation(s))&Background 8 Justification I. Recommended Action: APPROVE Contract Change Order No. 2 in the approximate amount of $800.00 and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, Kulchin-Condon and Associates for the placement of structural concrete fill. II. Financial Impact: The project contingency funds are sufficient to cover the change order cost. The project is funded by Federal Aid Storm Damage Repair Funds (65.8%) and County Road Funds (34.2%). III. Reasons for Recommendations and Background: The cumulative total of Contract Change Orders Nos. 1 and 2 exceeds $25,000.00, requiring Board approval. IV. Consequences of Negative Action: Without approval the contractor will not receive payment. Continued on attachment: _yes SIGNATOR RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON: Il- /� _ 199,5 APPROVED AS RECOMMENDED ✓ OTHER VOT�,OF SUPERVISORS UNANIMOUS (ABSENT AYES: NOES: ABSENT: ABSTAIN: Contact: Joseph P. Murphy, (510) 313•-2321 Orig. Div.: PW(Constr) cc: County Administrator Auditor-Controller Public Works I hereby certify that thfa N s to and correct copy of - De sign,V.Germany an action taken and entered on the minutes of the - Accounting, R. Gilchrist Board of Supervisors On the date shown. - R. Bruno ATTESTED: Contractor PHIL BATCHELOR,Clerk of the Efoard Of SupeMsore and County Administrator CB:tt g:\CONST\BO\SPDR-14.t11 � ,Deputy