APPROVING AND AUTHORIZING EXECUTION OF CHANGE ER NO. 7,
SUBJECT: CONTRACT FOR BID PACKAGE NO. 3-CONSTRUCTION OF NEW HOSPITAL, 2500
ALHAMBRA AVENUE, MARTINEZ (WH580B)
SPECIFIC REQUEST(S)OR RECOMMENDATIONS)&BACKGROUND AND JUSTIFICATION
I . RECOMMENDATION
1 . APPROVE Change Order No. 7 to the Contract dated February 7,
1995, for the Construction of a New Hospital, Associated Site
and Hardscape and Landscape at 2500 Alhambra Avenue,
Martinez, and AUTHORIZE the County Administrator or his
designee to execute the Change Order, which provides for post
bid review changes-Miscellaneous architectural revisions .
II . FINANCIAL IMPACT
Funds in the capital account established for the project are
sufficient to . cover the amount encumbered by this contract, from
bond proceeds specified to the project. Bond financing for the
total project cost was secured in May, 1992 in accordance with the
Board of Supervisors direction.
CONTINUED ON ATTACHMENT: YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON APPROVED AS RECOMMENDED V1 OTHER
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A TRUE
--- UNANIMOUS(ABSENT ) AND CORRECT COPY OF AN ACTION TAKEN
AYES: NOES: AND ENTERED ON THE MINUTES OF THE BOARD
ABSENT: ABSTAIN: OF SUPERVISORS ON THE DATE SHOWN. ff
ATTESTED
Contact: D. Bell, CAO PHIL BATCHELOR,CLERK OF THE BOARD OF
cc : Auditor-Controller SUPERVISORS AND COUNTY ADMINISTRATOR
GSD (Accounting)
O' Brien-Kreitzberg(via CAO)
Contractor (via CAO) BY A 41DEPUTY
Board Order to Approve November 7, 1995
Change Order No. 7 for
Bid Package No. 3
III . REASONS FOR RECOMMENDATION
On February 7 , 1995, the County awarded the contract to the lowest
responsive and responsible bidder, Centex Golden Construction Co.
Since the last Board Order, the following Change Orders have been
approved: No. 1 through No. 6 . Change Order No. 7 is for Post Bid
Review Changes-Miscellaneous Architectural Revisions in the amount
of $59, 047 . 00 . The new guaranteed maximum cost will exceed the
total estimated cost stated in the construction contract agreement
approved by the Board on February 7, 1995 . The new guaranteed
maximum cost will be $39, 607, 575 . 00, an increase of $123 , 575 . 00 .
Change Order No. 1 $ 2, 592 . 00
Change Order No. 2 2, 093 . 00
Change Order No. 3 5, 692 . 00
Change Order No. 4 23 , 646 . 00
Change Order No. 5 14, 096 . 00
Change Order No. 6 16, 409 . 00
Change Order No. 7 59 , 047 . 00
$123 , 575 . 00