HomeMy WebLinkAboutMINUTES - 11141995 - C3 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: November 14, 1995
SUBJECT: Approve and Authorize the Chair to Execute Program Supplement No. 041 for
Phases IV and V of the Kensington Road Improvement Assessment District Project.
Project Nos.: 4500-6X5222-92 and 4500-6X5223-92, CP#91-60
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
APPROVE and AUTHORIZE the Chair of the Board of Supervisors to execute Program
Supplement No. 041 which provides $169,359 in State/Local Transportation Partnership
Program funds for Phases IV and V of the Kensington Road Improvement Assessment
District Project.
II. Financial Impact:
The supplement provides reimbursement for 19.35% ($169,359) of the County's costs for
this project. Local funding provides the remaining 80.65% of the County's costs for this
project.
III. Reasons for Recommendations and Background:
On June 21, 1977 the Board approved County/State Master Agreement No. 04-5928 for the
funding of Federal Aid Projects. The Board reviewed and approved the project on July 16,
1992, and determined the project to be exempt from the California Environmental Quality
Act as a Class 1-C Categorical Exemption.
IV. Consequences of Negative Action:
If this program supplement is not approved the County will hav absorb the entire cost
of construction and construction inspection of this project.
Continued on Attachment: SIGNATURE:
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON 11-14 -1195 APPROVED AS RECOMMENDED ✓OTHER
VOTE OF SUPERVISORS
�/ UNANIMOUS(ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct copy of
NW:ds an action taken and entered on the minutes of the
g:/transeng/dsBOps039.t11 Board of Supervisors on the date shown.
ATTESTED: �:4 '-e,6,,,, 114A 14 _ 19 9
Orig. Div: Public Works(Transportation Eng.) PHIL BATCHELOR,Clerk of the Boa d
Contact: Dave Suico,Tel. 313-2264 of Supervisors and County Administrator
cc: AccountingaAAJ`
Deputy
-3
Date: October 12, 1995
PROGRAM SUPPLEMENT NO. 041 Location: 04-CC -0-CR
to , Project Number: SB95-5928 (029)
STATE-LOCAL TRANSPORTATION E.A. Number: 04 -927889
PARTNERSHIP PROGRAM AGREEMENT NO. SLTPP-5928
This Program Supplement is hereby incorporated into the State-Local Trans-
portation Partnership Program Agreement for State Share Funds which was
entered into between the Local Entity and the State on 03/15/91 and is
subject to all the terms and conditions thereof . This Program Supplement
is adopted in accordance with Paragraph 3 of Article I of the aforemen-
tioned Master Agreement under authority of Resolution No.
approved by the Local Entity on /-iS!_ o/j (See copy attached) .
The Local Entity further stipulates that as a condition to payment of funds
obligated to this project , it accepts and will comply with any covenants or
remarks setforth on the following. pages .
PROJECT TERMINI:
Various County Roads (Phase 4 and 5)
TYPE OF WORK: Roadway reconstruction LENGTH: 0 . 0 '(MILES)
PROJECT CLASSIFICATION OR PHASE (S) OF WORK
[X] Construction
Estimated Cost State Share Funds Matching Funds
FY95 $ 0 Local OTHER OTHER
$ 875239 FY96 $ 169359 $ 705880 $ 0 $ 0
FY97 $ 0
Contra Costa County. STATE OF CALIFORNIA
Departure t of nsportation
By By
Chie District Liaison Branch
Office of Local Programs
Date env_ / 9 95" Date 12 � .
Attest
Title
I hereby Certify upon my personal knowledge thatbudgetedfunds are available for this encumbrance:
Accounting Officer �, Q, _Ct' � Date $ 169359 . 00
Chapters Statutes I Item Year I Program 1HC1 Fund Source I AMOUNT
139 1994 2660-125-042 94-95 20.25.010.100 C 258010 042-T 169359.00
_ �
VICIO iiR J. RY�GJIY."\,�
By Deputy
Page 1 of 3
04 -CC -0-CR r DATE: 10/12/95.
SB95-5928 (029)
SPECIAL COVENANTS OR REMARKS
1 . It is mutually understood between the parties that this
contract may have been written before ascertaining the
availability of legislative appropriation of funds, for
the mutual benefit of both •parties, in order to avoid
program and fiscal delays that would occur if the
agreement were executed after that determination was
made .
The total amount of State-Local Transportation
Partnership funds payable by the State shall not exceed
$169359 to be encumbered and reimbursed as follows :
FY 94-95 $ 0
FY 95-96 169359
FY 96-97 0
Any increase in State Partnership funds will require a
revised program supplement .
Any decrease in State Partnership funds will require a
revised finance letter.
2 . The State Funds Share is calculated based on the lower of the
approved eligible application amount or the eligible award
amount .
3 . SPECIAL COVENANTS FOR SLTPP PROJECTS UNDER EARLY
REIMBURSEMENT PLAN AND UNDER $300, 000 STATE SHARE
These Covenants supersede any conflicting provisions of the
Master Agreement :
A. The LOCAL ENTITY agrees that the payment of State Share
Funds will be limited to the lessor of the product of
multiplying the calculated pro rata percentage as determined by
the STATE by either:
(a) The eligible award amount or
(b) The total eligible State/Local Partnership Project cost
in the approved State/Local Partnership Program Application and
accepts any consequent increase in LOCAL ENTITY funding
requirements .
B . The LOCAL ENTITY will invoice the State for the full "State ' s
Share" after the contract award or upon the State Budget Act
appropriation of funds, whichever occurs later. 'State ' s Share"
is considered a grant and will be reimbursed as a lump sum
payment regardless of final project cost .
Page 2 of 3
04 -CC -0-CR DATE: 10/12/95,
SB9S-5928 (029) ,
SPECIAL COVENANTS OR REMARKS
C. Prior to reimbursement under this Program Supplement, a
Request For Early Reimbursement form, executed by the LOCAL
ENTITY, must be on file with the STATE.
D. The financial audit and Final Project Expenditure Report
provisions of Sections 9 and 10 of ARTICLE I of the Master
Agreement are ,not applicable to this PROJECT.
4 . The Reimbursement Ratio for this Cycle 5 (94/95) Project is
19 . 350 .
S . In accordance with the State-Local Transportation Partnership
Program Guidelines dated June 8, 1994 the 'project eligibility for
Cycle 5 projects is limited to contract items plus locally funded
State or Local Entity furnished materials and Supplemental Work.
Supplemental Work eligibility is futher defined under t•he Project
Eligibility section of the Guildelines as limited to certain
maximum costs and to non-early reimbursement projects of $300, 000
or less .
r
Page 3 of 3
STATE OF CALIFORNIA-BUSINESS,TRANSPORTATION AND HOUSING AGENCY PETEWILSON,'Govemor.-
DEPARTMENT OF TRANSPORTATION
STATE AND LOCAL PROJECT DEVELOPMENT PROGRAM
1120 N STREET
P.O.BOX 942874
SACRAMENTO CA94274-0001
TDD(916)6544014
P16) 654-3151 _AX(916) 654-2409 3 19,96G
4, ENGINE
December 26, 1995 ER1NG
File: 04 - CC -0-CR
SB95-5928(029)
Various Co Roads (Phase 4 &5) -
Roadway reconstruction
Mr. Michael Walford
Director of Public Works
County of Contra Costa
255 Glacier Drive
Martinez, CA 94553-4897
Attention: Nancy Wein
Dear Mr. Walford :
Enclosed is your fully executed copy of Program Supplement Agreement Number 041
to State-Local Transportation Partnership Program Agreement No. SLTPP-5928 covering
construction for the above-referenced project.
Sincerely,
AHER�BREINL, Chief
Office of Local Programs
Project Implementation
Enclosure
cc:OLP AE project files
DLAE- 04