HomeMy WebLinkAboutMINUTES - 10171995 - C1 TO: BOARD OF SUPERVISORS (J
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: October 17, 1995
SUBJECT: Approve Consulting Service Agreement with Hultgren Geotechnical Engineers for
Geotechnical Services for the Delta Road Bridge Replacement Project.
Project Nos.: 0662-6R4216-95
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
APPROVE and AUTHORIZE the Public Works Director to execute the Consulting Services
Agreement with Hultgren Geotechnical Engineers to provide a geotechnical site analysis and
recommendations for the above-referenced project.
II. Financiallmpact:
The estimated contract cost is $23,600 funded by Highway Bridge Rehabilitation and
Replacement Program (80%) and County Road Funds (20%).
III. Reasons for Recommendations and Background:
The existing Delta Road bridge over Rock Slough in the Knightsen area is currently in a
deteriorated state requiring regular inspection and maintenance. The bridge has qualified for
replacement under the Federal Highway Bridge Rehabilitation and Replacement Program.
The services of a consultant are needed to provide field investigations, laboratory tests, and
conclusions and recommendations regarding soil characteristics related to the replacement of the
Delta Road Bridge, Hultgren Geotechnical Engineers was selected from a group of several firms
solicited to provide these services.
Hultgren Geotechnical Engineers has declared their intent to meet the County's DBE goals
through the use of subconsultants.
Continued on Attachment: X SIGNATURE:
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
—APPROVE _OTHER
SIGNATURE(S):
ACTION OF BOARD ON�'�lI7� 19-9g-APPROVED AS RECOMMENDED_OTHER
VOTE OF SUPERVISORS
/ UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
BF:jlg i hereby certify that this Is s true and correct copy of
c\BO:BO17.t9 an action taken and entered on the minutes of the
Board of Supe ors on the date shown.
Contact: Joe Yee 313-2323
Orig.Div: Public Works(Design Division) ATTESTED:
cc: Auditor Controller PHIL BATCHELOR,Clerk the Board
E.Kuevor,CAO Of Supervisors and County Administrator l
P.W.Accounting
ey - Deputy
Approve Consulting Service Agreement with Hultgren Geotechnical Engineers for Geotechnical Services
for the Delta Road Bridge Replacement Project
.Page 2
October 17, 1995
IV. Conseauences of Negative Action:
If the Consulting Services Agreement with Hultgren Geotechnical Engineers is not approved,
design of the project cannot be completed and the County may lose the federal matching funds.