HomeMy WebLinkAboutMINUTES - 12121995 - D5 TO: BOARD OF SUPERVISORS - Contra
FROM: TRANSPORTATION COMMITTEE o - ._ !s Costa
County
DATE: December :4, '1995
SUBJECT: SELECTION OF TRANSPORTATION PROJECTS AND PROGRAMS, FUNDED BY KELLER
CANYON LANDFILL AND ACME TRANSFER STATION REVENUES
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
1 . Refer Exhibit B to the Finance Committee to refine revenue
projections and allocations for FY 95/96 and 96/97
Transportation Programs and Projects;
2 . Request that the County Work-Fare and Sheriff' s Office
representatives discuss their activities of the Roadside
Litter Clean-up and Route Restriction Enforcement Programs,
respectively, at the Finance Committee; and
3 . Request that the Public Works Department to report to the
Finance Committee with the highest priority road projects in
Exhibit B, supported by the appropriate Bay Point Advisory
Committee, for funding with any remaining revenues .
CONTINUED ON ATTACHMENT: x YES SIGNATURE
RECOMMENDATN rith
O Y MINISTRATOR x RECOMMENDATION OF BOARD COMMITTEE
APPROVE O ER
SIGNATURE (S) : J f Tom Torlakson
ACTION OF BOARD ON December 12, 1995 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS ~
I HEREBY CERTIFY THAT THIS IS A
X UNANIMOUS (ABSENT ------------- TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVISORS ON THE DATE SHOWN.
Contact: Daniel J. Pulon (510/646-2378) ATTESTED'`12-12-1, 5..
cc: Community Development Department (CDD) PHIL BATCHELOR, CLERK OF
CAO THE BOARD OF SUPERVISORS
PWD WANDCY ADMINISTRATO
Sheriff' s office
Social Services Department
EPUTY
DP\ :KC-FEE. 95 "
Transportation Projects for Keller Canyon Landfill and Acme Transfer Station
Revenues
page two
FISCAL IMPACT
None to the General Fund. Based on the tonnage of waste received from the
landfill and Acme Transfer Station, the Keller Canyon Landfill Company is
required to pay mitigation fees to the County for general impacts of landfill
generated traffic . The Finance Committee is currently in the process of refining
these revenue projections for FY 95/96 and FY 96/97 for funding transportation
programs and road projects .
BACKGROUND/REASONS FOR RECOMMENDATIONS
The Keller Canyon Landfill Land Use Permit established a Transportation System
Impact Fee, as a condition of a approval designed to mitigate the general
impacts of the landfill on the County' s road system.
To mitigate the landfill' s transportation impacts, the Board of Supervisors, on
August 11, 1992, adopted policies and procedures that annually charge the
Transportation Committee to consider and recommend to the Board appropriate
allocation of the transportation mitigation fees to:
• implement litter control and patrol programs;
• repair road damage;
• enforce route restrictions;
• enhance public safety and protection; and
• address congestion relief measures related to transportation of waste
to the landfill .
The policies, in addition, stipulated that any recommended transportation
project or program, funded with mitigation revenues, requires public input for
the allocation of monies in the Transportation Trust Fund.
For the last two fiscal years, the Board of Supervisors approved the allocation
of transportation mitigation revenues for several projects . Exhibit " A " is
listing of those projects, coupled with a brief project implementation status
report .
During the Transportation Committee meeting, December 4, 1995, there was the
discussion that the Finance Committee is continuing its efforts in developing
revenue projections for Fiscal Years 95/96 and 96/97 . The Transportation
Committee, with this in mind, discussed that the revenue projections and
allocations to programs and projects in Exhibit B should be referred to the
Finance Committee . The Transportation Committee registered its commitment to
continue to fund the Transportation Programs, with any remaining revenues to
fund the highest priority road projects supported by the various Bay Point
Advisory Committees . The Transportation Committee also requested that the County
Work-Fare and Sheriff' s Office representatives discuss their respective
transportation program activities with, the Finance Committee.
Exhibit A
Name Description Amount Allocated Remaurmg
Balance
93/94 94/95
Roadside Litter Funded County Work-Fare crews who 180,000 180,000 40,000
Clean-up periodically clean-up litter on roadsides
throughout the County
Route Restriction Funded Deputy Sheriff personnel who enforce 70,000 70,000 0
Enforcement route restrictions on vehicles traveling to and
from the landfill
Roadside Litter Funded increased dumping fees for litter 22,000 22,000 0
Clean-up collected by the County Work-Fare crews.
Roadside Hazard Funded costs of cleaning hazardous materials 12,000 12,000 0
Clean-up illegally dumped along roads in the County or
leaked from abandoned vehicles.
Transportation and Funded costs of preparing environmental 100,000 0
Congestion Relief documentation for updating the Airport Master
Loan Fund Plan for the Contra Costa-Byron Airport. The
administrative draft document is currently being
development for internal review
Evora Road Funded costs of preparing environmental 110,000 0
Extension/Willow documentation for Evora Road
Pass Corridor Extension/Willow Pass Corridor improvements.
Improvements The County,in conjunction with neighboring
jurisdictions,is currently developing study
alternatives in preparation of environmental
administrative draft document.
Signage Funded costs of placing signs(such as Do not 6,000 0
litter;Keep Contra Costa County Beautiful;No
Dumping Nor Littering;etc.)At various
locations in Bay Point. Completion Date:
Feb.1996.
Alves Lane Funded transportation and community 100,000 0
Improvements improvements in the Bay Point area,including
but not limited to:sidewalks,curb,gutter,
landscape,and drainage improvements. Several
community improvement projects are currently
in the project design stages.
Project Leverage The Board of Supervisors allocated the funded 36,000 36,000
amount to leverage projects identified by local
traffic committee and municipal advisory council
for implementation. There have not been any
projects identified at this time for leveraging.
Alternative options for consideration:allocate
the amount to the Alves lane improvements,or
future year projects in the area.
DP2\tpproj93-95.fis
EXHIBIT B
KELLER CANYON AND ACME TRANSFER STATION TRANSPORTATION MITIGATION REVENUE
FISCAL YEAR 95/96 AND 96/97 TRANSPORTATION COMMITTEE BUDGET RECOMMENDATIONS
PROGRAM DESCRIPTION AMOUNT
RECOMMENED
FY95/96 FY96/97
1. Roadside Litter Clean-up ($360,000 REQUESTED, RECEIVED $180,000 FY 93/94, 94/95) $180,000 $180,000
Funds County Work-Fare crews who periodically
clean-up litter on roadsides throughout the County.
2. Roadside Litter Clean-up ($44,000 REQUESTED, RECEIVED $22,000 FY 93/94, 94/95) $22,000 $22,000
Funds increased dumping fees for litter
collected by the County Work-Fare crews.
3. Roadside Hazard Clean-up ($24,000 REQUESTED, RECEIVED $12,000 FY 93/94, 94/95) $12,000 $12,000
Funds costs of cleaning hazardous materials
illegally dumped along roads in the County
or leaked from abandoned vehicles.
4. Route Restriction Enforcement ($140,000 REQUESTED, $70,000 $70,000
RECEIVED $70,000 FY 93/94,94/95)
Funds Deputy Sheriff personnel who enforce
route restrictions on vehicles traveling to
and from the landfill.
ROAD PROJECT DESCRIPTIONS
1. Willow Pass Road Sidewalk Improvements ($75,000 REQUESTED, COMPLETED PROJECT)
The Redevelopment Agency initially funded the project
with Redevelopment funds. The improvements included curb,
gutter, sidewalks, and paving. This improvement project,
however, incurred cost over runs to complete the improvements.
2. North Broadway Avenue ($200,000 REQUESTED, NEW PROJECT)
Transportation and community improvements in
the Bay Point area, including but not limited
to: sidewalks, curb, gutter, and drainage
improvements.
3. Suisun Avenue ($100,000 REQUESTED, NEW PROJECT)
Transportation and community improvements in
the Bay Point area, including but not limited
to: sidewalks, curb, gutter, and drainage
improvements.
4. Acme Transfer Station Area/Arthur Road ($50,000 REQUESTED, NEW PROJECT)
Transportation and community improvements in
the area, including but not limited
to: resurfacing, sidewalks, curb, gutter, drainage, bicycle lane,
and lighting improvements.
5. Signalize Evora Road/Willow Pass Road (West)($200,000 PREVIOUSLY REQUESTED)
Funds the costs of a traffic signal at the intersection of
Evora Road and Willow Pass Road in Concord to relieve traffic
congestion.
6. Driftwood Drive Improvements ($200,000 PREVIOUSLY REQUESTED )
Funds the Transportation and community improvement costs, between the Contra Costa Canal
bridge and Port Chicago Highway, including but not limited to: bicycle paths,
sidewalks, curb, gutter, and drainage improvements.
7. Alves Lane Improvements ($100,000 REQUESTED, RECEIVED $100,000 FY 94/95)
Transportation and community improvements in the Bay Point area, including but not limited
to: sidewalks, curb, gutter, landscape, and
drainage improvements.
* Road projects are listed in priority order.