SUBJECT: Approve Drainage Area 44B Line C Project, Pleasant Hill Area.
Project No. 7547-6D 8455-92, CDD-CP # 93 - 74.
Specific Request(s) or Recommendations) & Background & Justification
I. RECOMMENDED ACTION:
APPROVE Project, and
FIND, on the basis of the initial study and all comments received, that there is no substantial
evidence that the project will have a significant effect on the environment,
ADOPT the Negative Declaration in compliance with the California Environmental Quality Act, and
DIRECT the Chief Engineer to begin right of way acquisition and to prepare contract plans and
specifications for construction.
DIRECT the Director of Community Development to file a Notice of Determination and a
Certificate of Fee Exemption: De Minimis Impact Finding with the County Clerk.
DIRECT the Chief Engineer to arrange for payment of the $25.00 handling fee to the County
Clerk.
II. FINANCIAL IMPACT:
The estimated project cost is $366,700, funded by Drainage Area 44B (100%).
Continued on Attachment: X SIGNATURE: �1. c
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JAN 111994 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT ZL )
AYES: NOES:
ABSENT: ABSTAIN:
ES:jlg
c\BO:bo11.t1
i hereby certify that this is A true and correct copy 21
an action taken and entered on the minutes of the
Orig. Div: Public Works (Design Division) Board of Supervisors on the date shown.
Contact: Elmer Schaal (313-2234)
cc: County Administrator ATTESTED: �.
Attn: E. Kuevor GNII I(TL'I'iELCfH,G`ler bf the Board
Auditor-Controller 7"I"JI
of Supervisors andmy Administrator
PW Accounting
Construction 6y , .Deputy
Community Development
Approve Drainage Area 44B Line C Project, Pleasant Hill Area
January 11, 1993
Page 2
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The project includes installing approximately 2,000 feet of 60" and 72" storm drain pipe and
appurtenances.
It is needed to provide the storm drain capacity needed for a 10-year storm.
The project has been determined to be in compliance with the General Plan. A Negative
Declaration of environmental significant pertaining to this project was published November 15,
1993 with no protest, and the Board has considered the negative declaration with all comments
received during the public review period.
IV. CONSEQUENCES OF NEGATIVE ACTION:
Delay in approving the project will delay completion of the project design.