HomeMy WebLinkAboutMINUTES - 12061994 - 1.4 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: December 6, 1994
SUBJECT: Increase in Project Contingency Fund for the Bay Point Feeder Trail Project,
Project No. 0662-6R4137-93, Bay Point area
Specific Request(s)or Recornmendation(s)&Background&Justification
1. Recommended Action:
Approve Project Contingency Fund increase of$7,000.00 to compensate the contractor, Eugene
G. Alves Construction Company, Inc. for contract item increases.
II. Financiallmpact:
The increase in the contingency fund will be funded by Transportation Development Act funds.
III. Reasons for Recommendations and Background:
The additional money is needed to pay the contractor for authorized additional work and quantities
added to the original contract.
IV. Consequences of Negative Action:
The lack of Approval would preclude payment to the contractor for work required for the successful
completion of the contract.
Continued on attachment: _yes
SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: DU 6 APPROVED AS RECOMMENDED_ X OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS(ABSENT
—AYES: NOES:
ABSENT: ABSTAIN:
Contact: Joseph P. Murphy, (510) 313-2321
Odg. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller 1 hereby certify that this is a true and correctcopyof
Public Works an action taken and entered on the minutes of the
Design Board of Su n the date shown.
- Accounting, R.Gilchrist ATTESTED: '
R. Bruno PHIL BATCHELOR Clerk of the Board
Contractor of Supervisors andunty Administrator
DG\tt By 'Deputy
g:\const\BO\BPT-6.t12