HomeMy WebLinkAboutMINUTES - 12201994 - 1.3 /,3
WHEN RECORDED, RETURN RECORDED AT REQUEST OF OWNER
TO CLERK, BOARD OF at o'clock M.
SUPERVISORS Contra Costa County Records
Stephen Weir, County Recorder
Fee $ Official
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving ) RESOLUTION OFACCEPTANCE
Notice of Completion of Contract for ) and NOTICE OF COMPLETION
Neroly Road and Live Oak
at Highway 4 Project ) (C.C. § 3086, 3093)
Proiect No. 0662-6R4009-91 ) RESOLUTION NO. 94/ 621
Federal Project No. STPLH-5928 (10)
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on July 6, 1994, contracted with Redgwick Construction Company, for the
road widening and signal modification at Neroly and Highway 4 and road widening at Live Oak and
Highway 4, with Safeco Insurance Company as surety, for work to be performed on the grounds of the
County; and
The Public Works Director reports that said work has been inspected and complies with the approved
plans, special provisions and standard specifications and recommends its acceptance as complete as
of November 3, 1994.
Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County
Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on December 20, 1994, by the following vote:
AYES: Supervisors Smith, Bishop, DeSaulnier, Torlakson and Powers
NOES: None
ABSENT: None
CERTIFICATION AND VERIFICATION
thereby certify that this is a true and correcteopyof
an action taken and entered on the minutes of the
Board of Sup�{s{ n We,�jpJJ
�shown.
ATTESTED: �IU�JJ�I��c
PHIL BATCHELOR, 01cri, of the Board
Contact: Joseph P.Murphy, (510) 313-2321 of Supervisors and County administrator
Orig.Dept.: Public Works(Const.) ,
cc: Record and return By ��-�� Deputy
Auditor
Public Works - Accounting
- Construction, R. Bruno
- Traffic,S.Kersevan
Contractor
bm/mw
G:\CON ST\BO:nloh420.tl 2
RESOLUTION NO. 94/ 621