HomeMy WebLinkAboutMINUTES - 10051993 - TC.2 77C, Z Contra TO: BOARD OF SUPERVISORS ,., . Costa FROM: TRANSPORTATION COMMITTEE County DATE: September 28, 1993 SUBJECT: Report on use of Measure C (1988) Funds for School Buses in the Lamorinda Area SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND JUSTIFICATION RECOMMENDATION Review response to questions on Lamorinda school bus proposal and consider action, as appropriate. FISCAL IMPACT None to County funds. BACKGROUND/REASONS FOR RECOMMENDATIONS The Lamorinda cities are requesting the Contra Costa Transportation Authority to allocate $8 million of Measure C Gateway/Lamorinda Traffic Program funds to operate a school bus system in the Lamorinda area ($500, 000 per year for the remaining 16 years of the sales tax period) . On September 14 , the Board discussed the Lamorinda school bus proposal and directed its representatives on the Contra Costa Transportation Authority not to vote on the request for funds until information was provided on certain questions raised by the Board. On September 15, the Contra Costa Transportation Authority decided to hold a special meeting on October 6 to hear more information on this proposal. The Lamorinda cities have prepared a packet responding to the issues raised (Exhibit A) and will be represented at the October 5 Board meeting. CONTINUED ON ATTACHMENT: X YES SIGNATURE RECOMMENDATION OF COUNTY ADMINISTRATOR X RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S) : �`om Powers Gayle Bishop ACTION OF BOARD ON w ' V up.0APPROVED AS RECOMMENDED OTHER 1� The Board established policy of support for the concept of using Measure C- 1988 funds for the Lamorinda school bus proposal, and directed its represen- tative to the Contra Costa County Transportation Authority to support it, and to report back for further direction after the workshop process; directed that the program be done in two steps, first with a demonstration process of 3 to 5 years, and then an ongoing program with permanent funding identified. Supervisors Smith and Bishop are to determine which of them will represent the Board at the workshop as the alternate to Supervisor McPeak. VOTE OF SUPERVISORS - - I HEREBY CERTIFY THAT THIS IS A UNANIMOUS (ABSENT TRUE AND CORRECT COPY OF AN AYES:g = :M NOES: —L. ACTION TAKEN AND ENTERED ON THE ABSENT: ABSTAIN: MINUTES OF THE BOARD OF SUPERVISORS ON THE DATE SHOWN. Orig Dept: Community Development ATTESTED OCT ` 5 199 Contact: Ernest Vovakis, 646-2131 PHIL BATCHELOR, CLERK OF cc: Supervisor McPeak THE BOARD OF SUPERVISORS Supervisor Torlakson AND OUNTY ADMINISTRATOR CCTA B , DEPUTY Lamorinda School Bus Proposal September 28, -1993 Page 2 The Transportation Committee recommends that the Board receive a report from Lamorinda representatives at its October 5 meeting and provide guidance to its CCTA representatives, as deemed appropriate. The following are the questions posed by the Board at its September 14 meeting: 1. Which roads are impacted by school traffic? Provide a map with the school locations and school-related traffic volumes. How much of that traffic is directed to the K through 8 grades (which is the target of the busing program) and how much is directed to the high schools? What impact would the school bus program have on these traffic volumes? What are the dismissal times of these schools? 2 . How have other school districts dealt with school traffic? If buses are used, what is the funding source used by these districts? 3 . Could comparable vehicular trip reductions be achieved through the regional TDM program? How would the costs compare with the school bus program? 4 . How would the school bus program impact the existing bus service in the area provided by the CCCTA? How many trips would be lost to CCCTA and how would this affect the fare-box recovery ratio of CCCTA? 5. What mechanism will be established to continue the program once the pilot program is ended and once the Measure C revenues end? CXNI$IT f� TC, 2 o September 30, 1993 S" BU lumlihm . LThis packet describes the Lamorinda Traffic Mitigation School Bus Proposal Anne Grodn jointly established and reviewed by Lafayette, Moraga and Orinda in response to Cir sound voter approval of "Measure C." Sctwd Board The Lamorinda Traffic Study is comprehensive, involving both mad Mark BressW improvements and traffic safety public measures. Much of the discussion is Public Reprsaentetnre focused on the bus proposal, and therefore our response has been to that aspect. The entire proposal is shown in Attachment "H". The school bus proposal is part of an integrated traffic mitigation program. It ChatfeGrent c should be noted that in the program description section - Transit Related Projects, of the Transportation Improvement Program developed by Barton S Board Aschman Associates dated June 29, 1993, the plan focuses on a coordinated John Cooley transit system. It has been developed as an augmentation to the TDM project Ad)&- Representadve which enhances the overall goal to mitigate traffic in the three communities. &1-06 The proposal is a direct response of community input designed to meet the voter approved language of "Measure C". The voter approved language embodied in Measure C states as follows: "To identify action/measures to mitigate the traffic density between Highway 24 and the Town of Moraga including cost benefit � analysis. Implementation of preferred project alternative (Lamorinda cities to KethY Fembecher jointly review and establish criteria for project implementation)." Public RepreasntetNs The responses to specific questions previously identified are attached as background and follow-up to our presentation. -- The Lamorinda School Bus Task Force Responses to concerns raised by CCTA regarding the Lamorinda School Bus Proposal 1. Is school busing an appropriate use for Measure C funds? The voter approved language in Measure C states that Measure C funds are to "identify action/measures to mitigate the traffic density between Highway 24 and the Town of Moraga including cost benefit analysis. Implementation of preferred project alternative (Lamorinda cities to jointly review and, establish criteria for project implementation)." The opinion of the legal counsel of CCTA has found that the school bus program is an appropriate use of these funds. (Attachment A) The three communities have met extensively over the past 2+ years to study the traffic congestion problem and to conduct public hearings. The results of these meetings and much testimony have also found school busing to be the appropriate use of these funds as defined in the Measures' language. 2. How much traffic would the proposed program take off the road? The number of vehicles reduced is a function of ridership and cars removed from the Moraga to Highway 24 traffic stream. Based c-a preliminary analysis and survey results,.it is anticipated that 1,741 cars would be removed from the streets in the morning and afternoon peaks if we achieve 37% ridership. (Attachment B) 3. How can cost-effectiveness or cost/benefit analysis be conducted? This issue will be discussed during the presentation to the CCTA on October 6th. A comparison of cost per vehicle trip reduced indicates that the Lamorinda School Bus Proposal is a cost effective traffic mitigation program with respect to other programs with similar intents. (Attachment C) 4. How does the proposal compare to other projects considered in the degree to which it will reduce congestion (mitigate traffic density) on Moraga Way,Moraga Road, and St. Mary's Road/Reliez Station Road corridors? This was addressed by Barton Aschman and Associates as part of the Lamorinda Traffic Study. (Attachment D) 5. How will the project be financed when Measure C expires? The Lamorinda School Bus Task Force is made up of elected representatives from the Cities of Lafayette, Orinda, and the Town of Moraga, as well as elected representatives from the three elementary school districts, the Acalanes High School District and public representatives. This is a separate committee from the Lamorinda Traffic Study Project Management Committee, which worked for two years to deliver the report on traffic mitigations in the Lamorinda area. The Lamorinda School Bus Task Force's sole job is to ensure success of the program. Once a coordinator is hired to begin implementation of the program, the Task Force will continue to work to make the program a success. A part of this is to establish a continuation of funding. We are not soothsayers and cannot predict exactly what dollars will be where in the year 2010,but with unswerving commitment the Task Force is dedicated to finding a solution to this problem. We have not worked this hard to achieve traffic mitigation to see it slip away in future years. Some of the possible sources of continuation monies are as follows: 1) A vote of the people to extend Measure C (this would almost ensure support from the Lamorinda area to aid other areas of the county.) 2) Specific Bond measures for local traffic mitigation. 3) Future environmental money may very well be available as student transit is recognized as an environmental alternative for reducing congestion and promoting clean air, as evidenced by the current $700,000 BAAQMD grant. Some more creative ideas are to establish a sinking fund.to build a reserve to plan a fiscally prudent operational base. Of course, parent participation is an important part of any ongoing plan. Another area of activity is to work to change federal legislation which prevents public transit from "engaging in school bus operation." (Section 3g of the Federal Transit Act). The elected officials of Lamorinda are dedicated to making this program work and continuing the program beyond the life of Measure C because of its enormous benefits in reducing traffic congestion and improving the quality of life. 6. What is the potential impact on CCCTA "County Connection" revenues? As this program is intended to work with, and not in competition with, the CCCTA service, it will serve to meet the unmet needs in our service area. The program is designed to minimally impact existing CCCTA ridership. Where existing routes are working, we will augment CCCTA service, rather than compete against it. In summary, the County Connection cannot provide the service that is needed in Lamorinda. However, the Bus Task Force wants to be very clear that it desires to strengthen CCCTA's position in Lamorinda, to encourage more buses with closer headways, and furthermore, to strengthen the existing ridership patterns of high school students through a TDM program funded though AB434 funds. Responses to questions raised by the Board of Supervisors 7. Which roads are impacted by school traffic? What impact would the school bus program have on these traffic volumes? What are the dismissal times of these schools? Please refer to attached map (Attachment E) for location of schools relative to impacted roads. Also attached is the dismissal times of the schools. The School Superintendents have all expressed a willingness to adjust the bell schedules of the schools to coordinate with the busing program. The impact of the school busing program on the traffic volumes has been preliminarily addressed by Barton Aschman in the Lamorinda Traffic Study, but until the program is further defined, exact counts are unknown and are dependent upon the level of ridership and participation in the program. 8. How have other school districts dealt with school traffic? If buses are used, what is the funding source used by these districts? Attached is a graph (Attachment F) indicating the levels of funding of other schools districts. By using Measure C funds to reduce congestion we are providing school buses in the Lamorinda communities. Other communities currently receive school bus funding from the State and other sources. However, Lafayette and Orinda are not eligible to receive this funding due to bus service being discontinued as a result of Proposition 13. • The San Ramon Valley Unified School District receives $425,000 for busing from the State. Of this, three-quarters of these funds must be spent on transporting special education students. Parents collectively contribute $126,000; the fee to parents for one year of round trip transportation is $370.00 At this co-payment rate, there is currently 10% participation in the program. • In Pittsburg there is no charge to the parents. The state contributes $300,000 for non-special education busing and $600,000 for special education busing. Richmond receives funding through safety grants. • The Mt. Diablo School District receives 1.1 million from the state for busing and contributes $750,000 from their general fund. Parents contribute $200 per year for the first child, $300 for 2 children and $350 for 3 children. • Brentwood and Oakley currently charge $270/year per student and is subsidized through State Bus Replacement and Air Quality funds. • Byron pays for school buses from their General Fund and charges parents $175 per year. 0 Antioch charges $2.00 per day per student , with any deficit being funded out of the General Fund. 9. Could comparable vehicular trip reductions be achieved through the regional TDM program? How would costs compare with the school program? The Southwest Area Transportation Planning Committee has approved hiring a full time employee to coordinate a Transportation Demand Management Program for the jurisdictions of Lafayette, _Moraga, Orinda, Danville, Alamo and Blackhawk. This position will be funded through Bay Area Air Quality Management District AB434 40% funds. This program will be directed towards large employers (100 employees or more) and multi-tenant complexes, as well as student and teacher commuters to high schools. This coordinator will work with each of the high schools in this area to develop programs to encourage commute alternatives to single occupant vehicles. Alternatives may include the promotion and implementation of a carpool/rideshare program, distribution of information regarding transit, and working with CCCTA to increase service and promote existing transit routes. The general intent is to educate the students about the need to eliminate vehicle trips as well as to promote the existing alternatives. Funding for this position totals $70,500 for the first year. The Lamorinda School Bus Program is a supplement to our regional TDM program and an attempt to achieve a broader based mitigation effort. The Lamorinda School Bus Program will allow children to become accustomed to using buses in the hope they will continue to use transit as they advance to high school and into adulthood. The BAAQMD Bay Area '91 Clean Air Plan states: "In addition to addressing the immediate transportation needs of youths, we must look to the future. Since today's youths will be the commuters of tomorrow, it is important to educate them about the needs to reduce motor vehicle travel to combat traffic congestion and air pollution ... according to MTC travel data, school trips account for 2-3% of total vehicle miles traveled in the Bay Area. In addition to its direct impact on school trips, buses may also have an impact on commute trips. If additional school bus service is provided, parents who must now drop off their children at school while in route might be able to commute via ridesharing or transit." 10. How would the school bus program impact the existing bus service in the area provided by CCCTA? How many trips would be lost to CCCTA and how would this affect the fare-box recovery ratio of CCCTA? The proposal would not be in competition with CCCTA. Conversely, the Lamorinda School Bus Program would augment CCCTA's existing service in Lamorinda to fill in the gaps to meet the unmet existing need. The Lamorinda School Bus Task Force has proven it can have a cost of approximately $1.05 per one way trip as opposed to the $3.08 for CCCTA (fully loaded figures). (Attachment G) In the program description of Measure C, page 7, Lamorinda is tasked to "Identify actions/measures to mitigate traffic density between Highway 24 and the Town of Moraga including cost benefit analysis." The County Connection admits that our program would be a "low-cost alternative"; it would be irresponsible to support anything else. The Federal Transit Act, amended 1992, Section 3, g. states: "No federal financial assistance shall be provided under this Act ... in providing public mass transportation ...unless such applicant ...shall have first entered into an agreement that such applicant will not engage in school bus operations, exclusively for the transportation of students and school personnel, in competition with private schoolbus operators." In summary, the County Connection cannot provide the service that is needed in Lamorinda. However, the Bus Task Force wants to be very clear that it seeks to strengthen CCCTA's position in Lamorinda, to encourage more buses with closer headways, and furthermore, to strengthen the existing ridership patterns of high school students through a TDM program funded though AB434 funds. As stated in the Lamorinda Traffic Study, the Transit Relaied Projects include: "Develop a plan and fund school buses to grade and intermediate schools; study the feasibility of providing expanded bus service to high schools; increase CCCTA bus service in Lamorinda; and provide BART shuttle service." 11. What mechanism will be established to continue the program once the pilot program is ended and once the Measure C revenues end? Please refer to Question 5 above. _..1 REC E IVE1 D AWACHNUENT "A- J U L 2 1 1993 LAW o•rICES CITY OF LAFNYETTE NOSSAMAN, GUTHNER, KNOX & ELLIOTT rr. wrr•rouwr►. r�oow Commissioners Contra Costa Transportation Authority 1340 Treat Blvd. Ste. 150 Walnut Creek, CA 94596 RE I vse o! Gateway/L&ncrinda Traffic prograsi category funds for funding school bus Programs Ladies and Gentlemen. This is in response to your request for our opinion with respect to the availability of funds under the "Gateway/Lamorinda Traffic Program, category of the Measure- C Expenditure Plan of the Contra Costa Transportation Authority (•Authority•) for the purpose of funding school bus programs for the school districts within the cities of LafAyette, Orinda and Moraga. 0VZZTT No pR3sa]�'!'sa 1. Does the "Gateway/Lamorinda Traffic Program, description prohibit use of categorical funds for the purpose of funding a school bus program? 1, The `Gateway/Lamorinda Traffic Program, category description authorizes expenditure of Measure C funds under the category for the purpose of identifying and implementing projects to •mitigate the traffic density between Highway 24 and the Town of Moraga* . Assuming that the school bus program is designed to have such a purpose, and subject to the analysis which follows, 1 be inconsisite t with the 2ancuace of the Expenditure Plan. To the—extent t at a sc o us program may Piave t�enom" c' iid-ental effect of alleviating congestion in that portion of the cities of Lafayette and Orinda north of Highway 24 (but not in the Moraga to Highway 24 corridors) , a question is presented with respect to consistency with the project category description, and we offer no opinion at this time as to the appropriateness of such expenditure under the Expenditure Plan. . _ We note that the Expenditure Plan can be amended by the Authority with the concurrence of the cities and the county, should the Authority wish to resolve any ambiguity in this regard. The positioning of the category under the heading *Highways and Arterials' in the Expenditure Plan and under the heading "Projects' in the Project and Program Descriptions of the Expenditure Plan, as well as internal references in the program description, create conflicting implications with respect to the intent of the drafters regarding authorized uses of the category funds. Based on the conflicting references, we are unable to determine any clear intent, and conclude that the use of funds from the category for the intended purpose would not be in conflict with any clear intent as to the use ofsuch fun3T. ATTACHMENT "B" LAMORINDA SCHOOL BUS PROPOSAL TOTAL K-8 SCHOOL POPULATION 6,800 RIDERSHIP 20% 30% 40% 50% 60% 70% STUDENTS 1,360 2,040 2,720 3,400 4,080 4,760 VEHICLES 944 19416 1,888 2,361 2,833 3,305 REDUCED* * Assumes a 1.44 student per vehicle ratio, based on survey results, Spring 1993 ATTACHMENT "C" _ c0 c 0 = d OM � ONO r 0) X O m N N Oc6 O W O M O T N to -O O r` Ca M CO O ? O cri T CL CL N O C'0 0 CO O O O U) O CN OOi O ItO M CD c 0Mit O *- o O O C•9 M r N •N O r` T Qd O CO Q V N mw a) N O (O_ N O � � CO 06 c0 O tOD T r _c O N c o Ca et mU � 000lqt on 0 Lf) 00 >. O O N O OD r O 0 r C7 (O O N r r (� > O N 0 m N m D. N L OOOo ro r00 C 0co 0 � MCOOT CO) O r r N V ` O O N N N c � E a' LQ LO N .c- (tiO n CO) J O m V Q CO) C lD = .L cc O d N 00 CO NCD NCO c � � c> > C g`� O O 00 N (OO CCD O 1: � a t, c •O `O `O N r T r T LLIL 0 cCD c tA CU O O O .O V) 0 (� CL Cu > y `+ O H L :3a m (D c m o j t0 o o aD O LO o (n C «- a N cn O o Co r- co m Co m c c cts m •` :O o o r N r N r N E Vt5m «N- E CL 0 " co N r: 0 CL0) rn o t a J N N J CD CL cm 0 D U O m O O m E B .a Q) m c � m a. a � O m > o cc Q p C c N ` m V N Q >+ o � O m m : d C`n CC Q N r 0E >. >1 " � w LO M 0 Cc aCL QQ myco TEa� W �+ T d 'O V 'O V V `, N O c C m O N o d (D d d (D a cr 7 r F- V CL C1 O. C1 C. C. (D c to CO - O F, cc w :� (n Q o U oCVVVUUS ZarN@7 Q ATTACHMENT "D" ie ie is IL 3 E � � E = a = 8 IL E Oh iiia Z3E $ la isl ple I Eva • �w „ Da V e ♦ i • • i � NIC � g %AA Nll ` O c N i -IN - tg g C � 1A IS` � � �� r O b G$, ¢ oiai d N � V r 32 A 32 21 cmc Y! •cS a$ � F- a E Com ¢ o � � m cr 35 LF 3 .- 8A -s w p a g E sro 32 boa a q o y � � Ir b E 0 3 N c� A IL C w c3 15 m3 N O m m t � � H Z N •� N C C Q � a � $ � m ad Eb >o ¢ � a CIO Ilk 7 aCC 4i oc TJ J .271LCL r � � s y � W � W IL s IL CL. JC4 0 c t y C S w CLcc 2� b c cif = — ►- S t H V ATTACHMENT "E" 1 It 0D D a r c s m rr ` 10, PON, � Oi� p o pp yC� p rl.a. 0 0 o s . RO M N N O to ' M fr O N N O r1 O r •, i a c _ •` -5 "tel s? � , Cn"' k'w•,/� 4 p h � as: -I• .-arm_'Jp *• a a 1. �� 1 � /, >_. � i 10 fit N� / t !` N �+ � -ti s .t.•.�4, .. '\�,. D�• ff � •�.:� R , r. a - ` Z'3 ao �'► � 3b oar MINER RD 3 :ENc�N�;s. � • m 'ate•-':-:: � C7 z 0 '-GL JETTA BLVD �4c,O x RqN S � •:• p f v CIAO VA () 0 0 ` < .mss' o .�.: jrf�• y�Eyr N Od .a HILL RD a2r: STREEZ CANYON RA RD O� Y 0 r } Q o �a RY'q r� 00 n O �. rn rnn, to � � o to 0 .-► 0. O a Z N 4 Zq Z� o O / LA 0 n a3 a 00� TOTAL NUMBER OF STUDENTS SCHOOL MIES Lafayette Schools 742 Burton Elementary 8:30 - 2:30 468 Happy Valley Elementary 8:30 - 2:30 409 Lafayette Elementary 8:30 - 2:30 445 Springhill Elementary 8:30 - 2:40 1,062 Stanley Intermediate 8:15 - 2:45 3,126 Total Orinda Schools 454 Del Rey 8:30 - 3:10 500 Glorietta 8:30 - 3:10 528 Sleepy Hollow 8:30 - 3:10 669 Orinda Intermediate 8:15 - 3:00 2,151 Total Moran Schools Grades 1-2 (earl,, /mote) Grades 3-4-5 552 Camino Pablo 8:10 - 1:32 / 9:10 - 2:40 / 8:10 - 2:40 605 Rheem 8:30 - 1:50 / 9:30 - 3:00 / 8:30 - 3:00 553 Joaquin Moraga Intermediate 7:50 - 2:24 1,710 Total * School Superintendents have indicated a willingness to adjust bell times to meet bus schedules. ATTACIBINd T ffl b9 d4 ffl -� 1 N .A O 00 O N O O O O O O O O O O O O ® {fl O O O O O O O O O O O O O co I CD f/ ?3/� /�/� i�/li'i jYi V/ Oiip 'Fi : !' +,c• n ! { fi a O1 1 I 1 1 co 1 1 1 1 ; 1 I 1 / • V/ 1 1 1 1 1 O 0 , 1 I ' I O• _� 1 1 • I I VI oi CD 3 1 1 1 1 1 V I 1 1 1 O 1 1 O 1 1 1 x CD m) 1 r m d i 1 61 :.0. i, of • I C G 1 1 CD 0 0 0 0 0 0 0 0 00 0o 00 O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 r a i • i • y �l/% f%�?/ G S 1 • 1 1 1 t / 1 1 • 1 . 1 cn 1 • 1 1 1 I 1 O t i t • t • . , 1 1 • r . r • r 1 1 1 1 , ` ' i t t • r t I �� Nr a i • • a a 1 I 1 1 1 I 1 a / i • t 1 1 1 1 1 1 1 N CD ./r cif C%�/f%' //�,y'7'>� �/r i 1 � • tf I i.. •� / I I ` 1 • • • t / . • clime r t t r • • a /+� [rpt f r�/ 1 1 1 1 t 1 [ ] • CD r�• iiiiJ� V t t I r r f A t t a a t a a �}x+� v o ,.. Q i t t i' • i • 1 • • r 1 • 1 � • 1 1 1 l: O •'� • � 1 1 1 r p :.� � i . • r • 1 1 • 1 • • i a i • • a • ATTACHMENT "U" Ft6 bait OpwW" uxpenee ppw . raft 1982-q A4�� now vow POWWVw ~ Pmew4w bw AC Transit 33% 469 $2 County Gonna Ors 17.5% 8f $3.08 San Francesco Muni 37% $1.10 BART 50% 228 52.83 Caltrain 35% 209 $4.58 Golden Gere 34% 730 $7.86 Trareporlatiotl OWYIM kitty SamTrans. buses 25.3% 394 5210 ' Source: Agencies listed above Source: Federal Mass Transit Admirlistratlott, 1991 rqM The Lamorinda School Bus program is estimated to cost $1.05 per trip. This includes the BAAQMD Grant and anticipated parent contributions--- - --- -- ATTACHMENT "H" t amork7da Tr*ft Study— Draft Fred Report Transportation Improvement Program LAMORINDA INTEGRATED TRAMC PROGRAM June 29' 1993 Table 1` Lamorinda Transportation Improvement Program Project Ust cls 1993 Strategic Plan Program Cost Program Elements (1988 5's) c2s Joint Jurisdiction Projects Transit Related Proiects. Develop a plan and fund school buses to $500,000/year<72' grade and intermediate schools; study the feasibility of providing expanded bus service to high schools; increase CCCTA bus service in Lamonnda; and provide BART shuttle bus service. Policies and Strategies. Adopt standardized Lamorinda definitions of $52,000 + significant impacts; Develop a coordinated Lamorinda TDM program; $1,000/year work with schools to stagger school start times, review school bound. aries to minimize trip lengths; develop and Implement a coordinated Lamorinda emergency evacuation plan; support BART,CCCTA, Caltrans, and CCTA planning programs; and support independent carrier commuter bus service. Tota!Jofrd Jurisdcdon Request 52,000+ $501,000 year Orinds Projects Coordinate Camino Pablo signals at Santa Maria, Brookwood, and $40,000 Camino Encines. Provide dual fight-turn lanes from NS Camino Pablo to the WS SA-24 $1288,000 on-ramp. Restripe the right-tum lane as a throughlright on northbound Camino $32,000 Pablo at Santa Maria Provide a third westbound lana on Sarna Maria at Camino Pablo. $152,000 Extend the third northbound through lane on Camino Pablo from $160,000 Brookwood to south of Camino Encinas. Extend the southbound merge an Moraga Way at Camino Enc km to $344,000 Overhill and nestripe northbound lanes. Balance approach delay at the Moraga Way/Giorietta intersection. $800 Add a right-turn lane to the northbound and westbound approaches at $680,000 Moraga Way/Gioriem Boulevard intersection. Add carpool parking bb: Camino Pablo @ Sarna Maria; Odnda Way $72,000 + north of Santa Maria $3,400/year Modify Moraga Way/G{orietta intersection to include a grade correction $240,000 at the Glorietta Boulevard approach to Moraga Way. Improve pedestrian access at all bus stops. Provide designated carpool $24,000 parking and bike lockers at selected stops. Add a traffic signal at the Gkxietta/Rheem Intersecdom $80,000 Barton Aschman Associates, Inc. 9 Lamodnda Traffic Study_— Draft Final Report Transportation Improvement Program June 29, 1993 Table 1 (Continued) Lamorinda Transportation Improvement Program Project List <1> 1993 Strategic Pian Program Cost (1988 $'s) <23, Relocate the bike lane from Highway 24 to Brookwood. Modify striping $416,000 on Highway 24 to allow shoulder use for an exit only lane. Study the need for pedestrian walkways on Moraga Way. Qs <43o- $50,Q00 Total Orinda Request $2,418,800 + $3,4001year Moraga Projects Modify access to Campolindo High School at Moraga Road. $32,000 Total Moraga Request $32,000 Lafayette Projects Signalize the Moraga Road/Hamlln-Tanglewood Irtersectkxt. 5208,000 Coordinate traffic signals on Mt Diablo Boulevard and on Moraga $220,000 Road. Modify the right-tum lane from First Street to eastbound SR-24 on- 532,000 ramp. Re-design the right-tum lane from SR-24 eastbound oft ramp to Oak $16,000 Hill. Add a left-tum lane at Moraga Road/Madrone Drive intersection. <42, $40,000 Modify the Brook-School/Moraga Road Intersecdon to separate through $2,064,000 and left-tum movements on Moraga Road. 453, Restrict left tum access at Moraga Road/Moraga Boulevard. <43. $8,000 Eliminate the insufficient bike lane on Moraga Road. 44> $1,600 Add a third eastbound through lane an Mt Diablo between Oak Hifi and $824,000 Moraga Road. 443, Add carpool parking lots at Pleasant HIP at Olympic, Deer Hifi and $572,000 + Lafayette Community Center. $1,700/year Feasibility study and preliminary engineering of a project to reduce $120,000 traffic congestion in downtown Lafayette through the Moraga Road/ML Diablo Boulevard Intersection. 43, <4> <43, 46.v- Total 6>Total Lafayette Request $4,105,600+ $1,7001year Safety Improvement Program Increase yellow/red time at Camino Pablo/Santa Maria; $500 Split north and south signal phases at First Street; $2,000 Extend red and yellow phases at Pleasant HiiVML Diablo and Pleasant $500 Hill/Tunnel Road; Barton-Aschman Associates, Inc. 10 Lamorinde Traffic Study— Draft Final Report Transportation Improvement Program June 29, 1993 Table 1 (Continued) Lamorinda Transportation Improvement Program Project List <1> 1993 Strategic Plan Program Cost Program Elements (1988 $'s) <2> Eliminate Plaza Drive crosswalk; $2,500 $500 Install raised pavement markers through the Oak HIIVML Diablo inter- section; Trim vegetation restricting sight distance at Moraga Way/Brookside, $2,000 Moraga Road/Corliss, Moraga Road/Alta Mesa, and Moraga Road/Ascot: Remove the eucalyptus tree at Rheem/St Mary's; $3,000 Repaint lines and legends at Moraga Road/Moraga Boulevard, Moraga $3,000 Road/Alta Mesa, and Rheem/St Mary's Road; Eliminate insufficient bike lane on Moraga Road; $2,000 Implement school safety programs including Suggested Route to School $24,000 Plan and bike rodeos. Total Safety Improvement Request $40,000 Total Areawide Improvement Costs One-time Costs $6,648,400 Annual Costs $506,100 Total Cost to 2001 $9,685,000 Total Cost to 2010 $14,746,000 Remaining Measure C Funds <4> $2,034,000 Barton-Aschman Associates, Inc. 1 Lamorinda Traffic Study- Draft Final Report Transportation Improvement Program June 29, 1993 Table 1 (Continued) Lamorinda Transportation Improvement Program Project List <1> 1993 Strategic Plan Program Cost Program Elements (1988 $'s) <23, c1> The LTIP Projects were approved by each council and then submitted to SWAT on June 7, 1993. cZ> The funding request through the Gateway/Lamorinda Traffic Program in the Lamorinda Traffic Study were projected in January 1993 dollars. The - - shown in this column are 20 percent less to reflect 1988 dollars, which is how the Strategic Plan funding is determined. c3> The criteria to be used in the study analysis,the consultant selection, and report review will be the joint responsibility of the three communities through the LPMC. 4" The Lamorinda community projects that impiementation of the following projects will use the remaining GatewayA amonnda Measure C funds. Preliminary costs in 1988 dollars are: Moraga . Way signals-$600,000; Moraga Way pedestrian walks--$800,000: and downtown Lafayette congestion relief-$2,000,000-Implementation will recognize the need for consensus, impact, and equity. <& Includes funding to coordinate this project with the Lafayette General Plan circulation element <f!> This study replaces the two Moraga Road/ML Diablo Boulevard By-pass major capital investment projects that were not adopted because of conflicts with land-use and the uncertainty of blti" downtown land use planning. <7> This cost does not provide for fufi funding. Additional binding sources (e.g., parents) will be required to implement an arsawide school busing program. Barton•Aschman Associates, Inc. 12 Lamonndi Trafllc Study— Draft Fns/Report Transportation Improvement Program June 29, 1993 PROJECT DESCRIPTION FROM LAMORINDA TRAFFIC STUDY Descriptlon of LhP Program Components The LTIP projects are described below. They have been grouped under joint jurisdiction projects. Orinda projects, Morags projects, and Lafayette projects and Safety projects corresponding to Table 1 (Page 9). Joint Julisdidtlon Pro/acts TronsIt Program There are three components to the Transit Program. These Component include (a) providing a school bis system, (b) providing a BART shuttle bus system, and(e)expand inglmaintaining the CCCTA bus system. The three Lamorinda councils identirzed the School Bus Program as deserving the highest priority for funding and implementation. Each is discussed below. • Implement a School Bus System This proposal, as ap- proved by the three city councils,will provide school bus service to the tamorinda grade schools and intermediate schools. The high schools will continue to be served by CCCTA buses. Current K through 8th enrollment is ap• proximately 8,880 students in the three school districts. The actual operating plan will be established during a for- mal school bus study that the three school districts will direct.This study will be the first step in implementing a school bus program. Decisions that must be made during this study include: who will operate and manage the program; how will the three districts work together to provide a coordinated plan; what routing structure will be followed;will there be central bus stops or will buses cover most streets; how much will the system cost and what portion of the cost will have to be covered by funds from sources other than GatewaylLamorinda funds,etc. The costs associated with the operation of a school bus system depend upon the density of children, the efficiency of the road network, the number of students served, the geographical area served, labor costs, start-up costs,etc. In the Lamorinds area, all of these factors tend to in- crease.costs: The density of school children is low, the road network is not efficient, the geographical area is fairly Barton-Aschman Associates, Inc. 16 Lamorinda Traflk Study— Draft Final Report • Transportation Improvement Program June 29, 1993 large, and start-up costs are likely to be high. Administra- tive costs could be reduced if the bus system is owned and operated by one school district. If each L,amorinda district were to operate a separate system, costs would be greater. These costs will be determined during the preliminary school bus study that will establish an operating program for the school bus system. The funding request for this project recognized that it would not be fully funded through the Measure C Gateway/Lamorinda Traffic Pro- gram • Implsn ent BART Shuttle#. Work with BART to implement the shuttle service plan serving the Orinda and Lafayette BART stations developed by the BART Planning Depart- ment. The program would use 17-passenger vane that would operate from 6 AM to 9 AM and 4 PM to 7 PM, • Expand/Maintain CCCTA Bus Service. Work with CCCTA to maintain existing bus service in Lamorinda. Where possible, expand existing service on Moraga Road and 3t. Mary's Road to 16-minute headways during peak periods. Consider providing new bus service to Rheem Boulevard. Particular emphasis should be placed on providing service to the high schoolr. THE REVISED CONTRA COSTA TRANSPORTATION IMPROVEMENT AND GROWTH MANAGEMENT PROGRAM "From Measure C" PROJECT AND PROGRAM DESCRIPTIONS PROJECTS Interstate 680 Corridor: Widen and improve Interstate 680 between the Alameda County Line and the Benicia-Martinez Bridge, and Route 242 between. Route 4 and Interstate 680. Project involves interchange, arterial and access improvements necessary to supplement already funded improvements. On Interstate 680, the project includes, but is not limited to, interchange improvements at Concord Ave., Willow Pass Road, and North Main St.; auxiliary lanes between El Cerro Blvd. and Bollinger Canyon Rd.; and the Fostoria Overcrossing. On Route 242, the project includes, but is not limited to, interchange improvements at Solano Way, Concord Ave., and Clayton Rd. The Authority may loan funds to the State to speed completion of already funded improvements to Interstate 680. North Richmond/Interstate 80 Bypass (Route 93): Complete an expressway between Interstate 580 (the Knox Freeway) near the Richmond-San Rafael Bridge and Interstate 80 at a new Atlas Road interchange near Hilltop. Route 4 (east): Widen and improve Route 4 between Willow Pass Road in Concord to at least Railroad Avenue in Pittsburg. Project includes freeway widening, lowering the grade over the Willow Pass, and interchange improvements at various locations. Route 4 (west): Widen and improve Route 4 to a full freeway between Interstate 80 and Cummings Skyway. Project includes reconstruction of the Route 4/Interstate 80 interchange. Gateway/Lamorinda Traffic Program: To identify action/measures to mitigate the traffic density between Highway 24 and the Town of Moraga including cost benefit analysis. Implementation of preferred project alternative (Lamorinda cities to jointly review and establish criteria for pro'ect irnglementation). Major Arterials - Southwest Region: Funds to improve major arterials as jointly determined by the local jurisdictions of the Southwest Region (Danville, Lafayette, Moraga, Orinda, San Ramon, and the portions of the County). It is the intent of the Authority that local jurisdictions give priority to the follow- ing projects: Widen San Ramon Valley Blvd. from Hartz to Alcosta; widen Dougherty Road from the County line to Crow Canyon Rd.; widen Crow Canyon Rd. from the County line to Bollinger Canyon Rd.; widen eastbound Route 24 off-ramp at Brookwood and up-grade signals; and improve the St. Marys Rd.-Glenside Dr.-Reliez Station Rd. corridor. Camino Pablo (San Pablo Dam Road Corridor): Improve and realign Camino Pablo in Orinda as a two-lane roadway with protected left turn lanes and separated pedestrian and bicycle paths. Rail extension from Concord to North Concord and Eastern Contra Costa: Extend rail transit (BART or light rail) from the Concord BART Station to North Concord and over the Willow Pass Grade to eastern Contra Costa. Contra Costa Regional Commuterwar. Develop bus/van commute lanes connecting the residential areas of eastern and central Contra Costa with job centers in central and southern Contra Costa. The project will use available rights-of-way and planned highway widening along the Route 4 and Interstate 680 corridors. Project shall use the Interstate 680 right-of-way in southern Contra Costa. Development of the project shall be sensitive to adjacent land uses, including a study of route realignment in Walnut Creek as part of mitigation of impacts. Project includes constructing park and ride lots, including those at Sycamore Valley and Bollinger Canyon Roads. Project also includes planning and right of way preservation for future connections to western Contra Costa. �,... . 131-VE AIR QUALITY 4 � ♦ MANAGEMENT DISTRICT ALAMEUA COUNTY Edward CampW Loci Haacuk August 4, 1993 (secretary) Greg Harper Don Perata Kelly C. Sills, Management Assistant City of Orinda CONTRA COSTA COUNTY 26 Orinda Way Pave L.Cooper Orinda, CA 94563 &UM wr%k McPeak Tom rowers Dear Mr. Sills: MARIN COUNTY I am pleased to inform you that the'Board of Directors of the Bay Area Air Quality Harold C.Brimu,Jr. Management District approved the City of Orinda's application for 5700,000 from the Transportation Fund for Clean Air (AB 434) for the La Morinda School Bus NAPA COUNTY project. The District received 101 applications for the discretionary funding Paw Battistl category, requesting a total of nearly $18.2 million. This year we are funding 39 of W"Cbairp"Sw these projects, totalling $8.2 million. SAN FRANCISCO COUNTY The District is looking forward to working with you and your agency to implement Roberta AchwaWn the project as quickly as possible. Enclosed is a proposed funding agreement for Carole Wqdm review and signature. As the agreement indicates, the District will begin dispersing funds to your agency after finalizing the agreement and receiving notice that all SAN HIATEo COUNTY other funding commitments have been secured. Janet Fogarty If you have any questions about the process or suggested changes to the funding Michael D.Nevis agreement, please contact Mr. Michael Murphy, Supervising Environmental Planner, at (415) 749-4644. If the funding agreement is acceptable, please sign two originals SANTA CLARA COUNTY for each project and return them to Mr. Murphy, care of the Planning Marge Bttaoo Division/Environmental Review Section, BAAQMD, 939 Ellis Street, San Rod Diridan Francisca, CA, 94109. Joe Herd Sincerely, Barbara Koppel SOLANO COUNTY Sam Caddk Milton Felstein Air Pollution Control Officer SONOMA COUNTY ren Harbersom RECEIVED ( ► 'S`'`� AUG 5 - 1993 CITYR �MANAGTy OF E +CLERK 939 ELLIS STREET • SAN FRANCISCO, CALIFORNIA 94109 (415) 771-6000 • FAX (415) 928-8560 Ilq° DATE: � REQUEST TO SPEAK '' ORM (THREE (3) MINUTE LIMIT Complete this form and place it in the box near the speakers' rostrum before addressing the Board' V(-C�Q-�-)L- l`, IZ��i �JV ' t� �� PHONE: ��NAME: A(i ADDRESS: 02-. ` 'i.Uwe � \ (L I PA) Cmr: I am speaking formyself OR organization: Q �— C(�V� OF qFk�KNITNTION) _ Check one: I wish to speak on Agenda Item # My comments will be: general for against I wish to speak on the subject of I do not wish to speak but leave these comments for the Board to consider. DATE: REQUEST TO SPEAK FORM (THREE (3) MINUTE LIMIT) Complete this form and place it in the box near the speakers' rostrum before addressing the Board. NAME: �i'D/` S� lC 5 PHONE: l7 8 l ADDRESS: 9 C! «S CITY: I am speaking formyself OR organization: S�4---1 Check one: (NAME OF ORGANIZ-VION) I wish to speak on Agenda Item # My comments will be: general for against I wish to speak on the subject of �AA I do not wish to speak but leave these comments for the Board to consider. jr 101-01, _ on DATE: !� 3 REQUEST TO SPEAK FORM (THREE (3) MINUTE LIMIT) Complete this form and place it in the box near the speakers' rostrum before addressing the Board. NAME: i 61 e-, �G.Y .�`S 1PHONE: ADDRESS:4�S �!�- �S C. I am speaking formyself OR organization: Li- Check one: N OF ORGANIZATION) I wish to speak on Agenda Item # My comments will be: general for against I wish to speak on the subject of I do not wish to speak but leave these comm nts for the Board to consider. SPEAKERS 1. Deposit the "Request to Speak" form (on the reverse side) in the box next to the speakers' microphone before your item is to be considered. 2. You will be called to make your presentation. Please speak into the microphone. 3. Begin by stating your name and address; whether you are speaking for yourself or as a representative of an organization. 4. Give the Clerk a copy of your presentation or support documentation, if available. 5. Please limit your presentation to three minutes. Avoid repeating comments made by previous speakers. (The Chair may limit'length of presentations so all persons may be heard.) DATE: l� REQUEST TO SPEAK FORM (THREE (3) MINUTE LIMIT) Complete this form and place it in the box near the speakers' rostrum before addressing the Board. NAME: r r�!X t t PHONE: ADDRESS: � l �2 U G' �' `.� � �- CITY: I am speaking formyself OR organization: 1 (NAME OF ORCA!Vllal'lOti) Check one: __ I wish to speak on Agenda Item # 2- My comments will be: general for against I wish to speak on the subject of :'/' S r L =� I do not wish to speak but leave these comments for the Board to consider. DATE: REQUEST TO SPEAK FORM (THREE (3) MINUTE LIMIT Complete this form and place it in the box near the speakers' rostrum before addressing th ard. NAME: PHONE: ADDRESS: 14 A, CITY: I am speaking formyself OR organization: Ch C one: NAME OF ORGANIZATION) I wish to speak on Agenda Item # ( . My comments will be: general for against I wish to speak on the subject of I do not wish to speak but leave these comments for the Board to consider. DATE: `A s 3 REQUEST TO SPEAK FORM (THREE (3) MINUTE LIMIT) Complete this form and place it in the box near the speakers' rostrum before addressing the Board. NAME: � �Z(i� P PHONE: !3f-- 6 710 ADDRESS: 4-/, 6 TH? -r " ��2 r CITY: Mw'�1-y+ I am speaking formyself OR organization: (NAME OF ORGANIZV ION) Check one: 76- Z - I wish to speak on Agenda Item # �. My comments will be: general for against I wish to speak on the subject of I do not wish to speak but leave these comments for the Board to consider. ley F(T94L TO y17i t Ms DATE: \O �Z REQUEST TO SPEAK FORM (THREE (3) MINUTE LIMIT) Complete this form and place it in the box near the speakers' rostrum before addressing the Board. ! NAME: \ >\-) (�. Ll 0 . T,-x r o PHONE: ro S (. C n � ADDRESS: �) UA- SA 1- LF, �E-- (�CrIY: �1 ' o I am speaking formyself OR organization: CX-- W 7,°A". Check one: (NAME OF ORG&NIZATION) I wish to speak on Agenda Item # My comments will be: general for against I wish to speak on the subject of I do not wish to speak but leave these comments for the Board to consider. SPEAKERS I. Deposit the "Request to Speak" form (on the reverse side) in the box next to the speakers' microphone before your item is to be considered. 2. You will be called to make your presentation. Please speak into the microphone. 3. Begin by stating your name and address: whether you are speaking for yourself or as a representative of an organization. 4. Give the Clerk a copy of your presentation or support documentation, if available. 5. Please limit your presentation to three minutes. Avoid repeating comments made by previous speakers. (The Chair may limit'length of presentations so all persons may be heard.) 1 J VV