HomeMy WebLinkAboutMINUTES - 10051993 - 1.3 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: October 5, 1993
SUBJECT: APPROVAL OF PROJECT CONTINGENCY FUND INCREASE FOR THE NORTH
RICHMOND AREA, Project No. 0662-6R4223-92.
specific Request(s)or Recommendation(s)&Background&Justification
1. Recommended Action:
Approve project contingency fund increase of $10,000 for work, resulting from differing field
conditions, in excess of the available project contingency funds.
II. Financial Impact:
This project is funded by SB-300 (15%) and Measure C (85%). The contingency fund increase
will be funded in the same manner.
III. Reasons for Recommendations and Background:
Because Contract Change Order No. 1 would cause the project costs to exceed the contract cost
plus the contingency fund, an increase in the project contingency Jund is required.
IV. Consequences of Negative Action:
Without approval the contractor will not receive payment for work required.
Continued on attachment: _yes SIGNATUR �
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: OCT 5 1993 APPROVED AS RECOMMENDED ✓ OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
--AVES: NOES:
ABSENT: ABSTAIN:
Contact: B.J. Kerekes, (510) 313-2321
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works i hereby certify that this Is a irW and correct Copy of
- Design an action taken and entered on the minutes of ttrs
- Accounting, R. Gilchrist Board of Supervisors on the i.do"shown.
1d�
- R. Bruno ATTESTED: 9.g3_-_��.
Contractor PHIL BATCH€I bR,clerk of the Board
of Supervisors and Cou Administrator
TJ\mgg Br • I ,t`teputy