LETTER OF PROTEST
Da te: February 8, 199.3
To: Contra Costa County
Project: Improvements at Fire Station No. 7U - San Pablo
Re: PROTEST OFAWARD OF CONTRACT
Dear Ms. Maglio
This firm was third-lower bidder on the above-named project
and as such as a substantial , economical, financial and business
.interest in the proposed announced intention of awarding the
contract on the above-named project to: SAUSAL CONSTRUCTION
We hereby claim the alleged low-bidder 's bid was non-
responsive as required . by the specifications for the foilowing
reasons:
1;. Lower-bidder did not meet MBE/Wl3E goals.
Z. Lower-bidder did not meet the good .faith effort.
Now, therefore, we hereby protest any award to above firm and
allege that our firm submitted the lowest responsive bid and
request a hearing for determination. You are obligated by law to
defer the contract award until a hearing for the resolution and
determination of this protest.
Please be informed that this firm will be present at the
hearing and request the opportunity to present further evidence and
information.
Please send this firm notice of time and place of the hearing.
Very truly yours,
Kam W. Leung
General Contractor