HomeMy WebLinkAboutMINUTES - 12071993 - 1.5 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: . December 7, 1993
SUBJECT: Approve Port Chicago Highway/Pacifica Avenue Traffic Signal Project,
Bay Point (West Pittsburg) Area.
Project No. 0662-6R4226-93, CP # 93-65.
Specific Request(s) or Recommendations) & Background & Justification
1. RECOMMENDED ACTION:
APPROVE Project, and
DETERMINE that the project is a California Environmental Quality Act Class 1 C Categorical
Exemption, and DIRECT the Public Works Director to prepare contract plans and specifications
for construction.
DIRECT the Director of Community Development to file a Notice of Exemption with the County
Clerk.
DIRECT the Public Works Director to arrange for payment of the $25.00 handling fee to the
County Clerk for filing of the Notice of Exemption.
FIND that the project will not have a significant effect on the environment.
II. FINANCIAL IMPACT:
The estimated project cost is $336,000, funded by SB 300 (9%) and Bay Point (West Pittsburg)
AOB (91%).
111. REASONS FOR RECOMMENDATION/BACKGROUND:
The project includes the installation of a traffic signal at the intersection of Port Chicago Highway
and Pacifica Avenue.
Continued on Attachment: X SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE _ OTHER
SIGNATURE(S):
ACTION OF BOARD ONDEC 7 1993 APPROVED AS RECOMMENDED OTHER _
VOTE,OF SUPERVISORS
V— UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
KF:ilg
c\BO:bo9365.t11
` I hereby certify that this is a true and correct copy 2f
Orifi. Div: Public Works (Design Division) an action taken and entered on the minutes of 11%
Contact: Kathleen Fudge(313-2249) Board of Supervisors on the date shown.
cc: County Administrator ATTESTED: nE C 1 1993
Attn: E.Kuevor PHIL BATCHELOR,Clerk of the Board
Auditor-Controller of Supervisors and County Administrator
PW Accounting � //JJ
Construction By ,.-71�vn&aJ 1/_�__fell/ ----,.Deputy
Community Development
Approve Port Chicago Highway/Pacifica Avenue Traffic Signal Project
December 7, 1993
Page 2
III. REASONS FOR RECOMMENDATION/BACKGROUND: (Cont.)
It is needed to improve the flow of traffic through the intersection.
The project has been determined to be in compliance with the General Plan and is exempt from
CEQA because it consists of minor alterations of existing public facilities involving no expansion
of use per Section 15301 of the CEQA Guidelines.
IV. CONSEQUENCES OF NEGATIVE ACTION:
Delay in approving the project will result in a delay of design and construction and may
jeopardize funding.