SUBJECT: Authorize the Amendment of a Purchase Order to Santa Fe Pacific Pipelines, Inc. for a
Utility Relocation, San Pablo Creek Channel Improvements Project, North Richmond Area,
(Project No. 7567-6D8607)
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
Authorize the amendment of an existing purchase order to Santa Fe Pacific Pipelines, Inc.
(SFPP) to increase the purchase order by $32,000 to the total amount of $183,000, for the
relocation of a petroleum pipeline for the San Pablo Creek Channel Improvements Project in the
North Richmond area.
II. Financial Impact:
The total relocation cost of $183,000 is reimbursable from the California Department of Water
Resources at the rate of 70.0°/x. The total local share of$54,900 will be paid from Drainage Area
73 (No. 7567-6D8607).
III. Reasons for Recommendations and Background:
By order of the Board of Supervisors, dated June 17, 1986, the Flood Control District approved
an agreement with the Corps of Engineers, the terms of which require the relocation of utility
facilities for construction of the Wildcat Creek and San Pablo Creek Channel Improvements
project. The required relocations included the facility owned by Santa Fe Pacific Pipeline, Inc.
crossing San Pablo Creek. On February 4, 1992 the Board authorized the initial purchase order
4
Continued on Attachment: X SIGNATURE: `a
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
_APPROVE _ OTHER
SIGNATURE(S):
ACTION OF BOARD ON OCT 6 11992,
APPROVED AS RECOMMENDED V OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT 1
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this Is a true and correct copy Y
an action taken and entered on the minutes of the
JJ:jlg Board of Supervisors on the date shown.
C\BO:bo6.t10 ATTESTED: n aT o 199E
PHIL BATCHELOR,Cierk of the Board
Orig. Div: Public Works (Design Division) of Supervisors and County Administrator
Contact: J. Johnson, 313-2311 a
County Administrator By �'��� n�� Deputy
Auditor-Controller
PW Accounting: W. Quever
tet.
Authorize the Amendment of a Purchase Order to Santa Fe Pacific Pipelines, Inc.for a Utility Relocation,
San Pablo Creek Channel Improvements Project
Page 2
October 6, 1992
in the amount of$151,000 which was the estimated cost provided by SFPP. The work has been
completed. However, due to unexpectedly high groundwater, the Contractor for SFPP was
required to perform extra work which included installation of additional sheet piling, a pumping
system and 24-hour monitoring.
IV. Consequences of Negative Action:
The petroleum pipeline has already been relocated. If the purchase order is not amended for