HomeMy WebLinkAboutMINUTES - 01211992 - 1.1 WHEN RECORDED, RETURN RECORDED AT REQUEST OF OWNER
TO CLERK, BOARD OF at o'clock M.
SUPERVISORS Contra Costa County Records
Stephen Weir, County Recorder
Fee $ Official
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving ) RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for ) and NOTICE OF COMPLETION
(C.C. § 3086, 3093)
Loring Avenue Retaining Wall )
Project No. 0662-6U4139-90 ) RESOLUTION NO. 92/34
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on August 1, 1991 contracted with Cassidy Construction, Inc., for the
construction of a retaining wall and roadway reconstruction at Loring Avenue in Crockett, with Wausau
Insurance Company as surety, for work to be performed on the grounds of the County; and 11
The Public Works Director reports that said work has been inspected and complies with the approved
plans, special provisions and standard specifications and recommends its acceptance as complete as
of December 13, 1991.
Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County
Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on January 21, 1992 by the following vote:
AYES: Supervisors Powers, Fanden, Schroder, Torlakson and Mc Peak
NOES: None
ABSENT: None
CERTIFICATION AND VERIFICATION
I hereby certify that this Is a true and correct copy of
an action taken and enteved on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: J Q N 2 1 1992
PHIL BATCHELOR,Clerk of the Board
of Supervisors and County Administrator
By Depuw
Orig. Dept.: Public Works (Const.)
cc: Record and return
Auditor
Public Works - Accounting
R. Bruno
Contractor
RT:fp\tt
c:\B0:LRW-21.1
RESOLUTION NO. 92/34