THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on September 8, 1992 by the following vote:
AYES: Supervisors-Powers, Fanden, Schroder, Torlakson and McPeak
NOES: None
ABSENT: None
ABSTAIN: None RESOLUTION NO. 92/ 585
SUBJECT: A Resolution of Intent with regard to County Local Match and the
Congestion Mitigation and Air Quality Program (CMAQ) for the San Pablo
Dam Road Signals and Interconnection Project. Project # 0662-6R4275.
The Board of Supervisors of Contra Costa County RESOLVE:
WHEREAS, the County has applied and been recommended for $505,600 in
CMAQ funding for the San Pablo Dam Road Signals and Interconnection Project from
Interstate 80 to May Road in the EI Sobrante area. New signals would be installed at the
intersection of Milton Road and Clark Road. Interconnection would take place between
Interstate 80 and May Road incorporating nine signals along 2.2 miles. The project is
scheduled for the 1993 Transportation Improvement Program (TIP) adopted by the
Metropolitan Transportation Commission (MTC) and approved by the Federal Highway
Administration.
WHEREAS, a prerequisite for inclusion in the 1993 TIP is the adoption of a local
resolution stating that the San Pablo Dam Road Signals and Interconnection Project will
be constructed as described above and on the County's Intermodal Surface
Transportation Efficiency Act (ISTEA) application.
WHEREAS, MTC has indicated that CMAQ projects will be eligible for State Traffic
Management System (TSM) funds. Further, MTC has estimated that the San Pablo Dam
Interconnect project will be eligible for $78,600 in TSM funds.
WHEREAS, $99,300 local matching funds will be provided by the Richmond/EI
Sobrante Area of Benefit and that the County understands that the CMAQ funding is fixed
at$505,000, and therefore, any cost increases can not be expected to be funded with the
CMAQ funds. No General Fund money will be expended.
NOW, THEREFORE, the Board of Supervisors of Contra Costa County, by
adopting this resolution of intent, does hereby authorize the local match for the San Pablo
Dam Road Signals and Interconnection Project, and direct the Public Works Director to
construct the project as described herein.
hereby certify that the foregoing is a true and correct copy of an order entered
on the minutes of the Board of Supervisors at the aforesaid date.
CPB:pe
c:ResSanPablo.t9
I hereby certify that this Is a true and correct copy,t
an action taken and entered on the minutes of the
Orig. Div: Public Works (Road Engineering) Board of Supers on the date shown.
Contact: Heather Ballenger, Public Works
ATTESTED. ry8 1992,
cc: M. Shiu, Deputy PW Director PHIL BATCHELOR,Clerk of the Board
M. Avalon, Road Engineering of Supervisors and County Administrator
H. Ballenger, Road Engineering ^ ,
R. Gilchrist, Accounting By Deputy
S. Goetz, Community Development
C. Monsen, CCTA
RESOLUTION NO. 92/ 585