TO: BOARD OF SUPERVISORS, as the Governing Body of the Contra Costa County Flood
Control and Water Conservation District
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: February 4, 1992
SUBJECT: DRAINAGE AREA 30A - LINE A, OAKLEY AREA
Project No.: 7557-6D8448 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
I. Recommended Action:
A. APPROVE Amendments to Right of Way Contracts as listed below:
GRANTOR DATE PAYEE AMOUNT
Cutino, et. al. 2-4-92 Tony Cutino $220
Lois Cutino
Dominick Vitale
Irene Vitale
c/o Cutino Feed & Supply
P.O. Box 5, Oakley, CA 94561
Points, et al. 2-4-92 Henry Alexander Points $110
Norma Lee Points
Rt.4, Box 354, Oakley, CA 94561
B. AUTHORIZE Chief Engineer to execute said Amendments to Right of Way Contracts on
behalf of the District.
C. APPROVE payment as listed above for said property rights and AUTHORIZE the Auditor-
Controller to issue checks in said amounts payable to the listed payees, to be forwarded
to the Real Property Division for delivery.
Continued on Attachment: x SIGNATURE: XCF4, &,.&
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON FEB 4 1992 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct copy of
in action taken and entered on the minutes of the
NW:glo 3oard of Supervisors on the date Shown.
c:BO14DA30.t2 A-TESTED: FER 4 1992
PHIL BATCHELOR,Clerk of the Board
Orig. Div: Public Works (R/P) of Supervisors and County Administrator
J
cc: County Administrator BY A " ,Deputy
Auditor-Controller (via R/P)
P. W. Accounting
AW .ry
II. Financ.-illImpact:
Payment totalling $330.00 from Drainage Area 30A funds.
III. Reasons for Recommendations:
These property rights are required for the completion of the Drainage Area 30A-Line A project
in accordance with approved plans and specifications.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow construction in accordance with the
approved plans and specifications.