HomeMy WebLinkAboutMINUTES - 02251992 - 1.32 TO: BOARD OF SUPERVISORS, as the Governing Body of the Contra Costa County Flood
Control and Water Conservation District
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: February 25, 1992
SUBJECT: Drainage Area 30A - Line A/Subdivision 7163, Oakley Area
Project No.: 7557-6D8360 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
I. Recommended Action:
A. APPROVE Right of Way Contract and ACCEPT Grant Deed dated February 4, 1992, from
Frank and Angie Domingo.
B. AUTHORIZE Chief Engineer to execute said Right of Way Contract on behalf of the
District.
C. APPROVE payment for said property rights and AUTHORIZE the Auditor-Controller to
issue a check in the amount of $5,200 payable to Frank Domingo and Angie Domingo,
Route 4 Box 394, Oakley, CA 94561, to be forwarded to the Real Property Division for
delivery.
D. DIRECT the Real Property Division to have above referenced Grant Deed recorded in the
Office of the County Recorder
II. Financial Impact:
Payment totalling $5,200 from Drainage Area 30A funds.
Continued on Attachment: X SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON FEB 2 5 1992 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT }
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
JMW:NW:fp Board of supervisors on the date shown.
c:BOc25.t2 ATTESTED: FFR u 5 1992
PHIL BATCHELOR,clerk of the Board
Orig. Div: Public Works (R/P)
of Supervisors and CAvinty Administrator
I ,
cc: County Administrator By _ ,ceputy
Auditor-Controller (via R/P)
P. W. Accounting
Recorder (via R/P)
Drainage Area 30A - Line A/Subdivision 7163, Oakley Area
February 25, 1992
Page Two
III. Reasons for Recommendations and Background:
As a condition of approval, the developer of nearby Subdivision 7163, Claremont Homes, was
required to install an underground pipeline to convey stormwaters to an existing pipe located
at the intersection of Cypress Road and Highway 4. A portion of the pipeline crosses under the
Domingo parcel in the area to be acquired.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow construction in accordance with approved