HomeMy WebLinkAboutMINUTES - 11191991 - 1.6 WHEN RECORDED, RETURN RECORDED AT REQUEST OF OWNER
TO CLERK, BOARD OF at o'clock M.
SUPERVISORS Contra Costa County Records
Stephen Weir, County Recorder
Fee $ Official
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving ) RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for ) and NOTICE OF COMPLETION
(C.C. § 3086, 3093)
Camino Tassajara Overlay-North )
Project No. 0662-6114102-88 ) RESOLUTION NO. 91 739
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on June 25, 1991 contracted with North Bay Construction, Inc., for asphalt
concrete resurfacing of Camino Tassajara, with The American Insurance Company as surety, for work
to be performed on the grounds of the County; and
The Public Works Director reports that said work has been inspected and complies with the approved
plans, special provisions and standard specifications and recommends its acceptance as complete as
of October 3, 1991.
Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County
Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on November 19, 1991 by the following vote:
AYES: Supervisors Fanden, Schroder, McPeak, Torlakson and Powers
NOES: None
ABSENT: None
CERTIFICATION AND VERIFICATION
I hereby certify that this is a true and correct copy of
an action taken and entered an the minute@ o4 the
Board of Supervisors on the date @hown.
ATTESTED: N O V 19 1991-
PHIL BATCHELOR,Clark of the Board
of Supervisors and County Administrator
By @Sputy
Orig. Dept.: Public Works (Const.)
cc: Record and return
Auditor
Public Works - Accounting
R. Bruno
Contractor
JBM/tt
c:\BO:CTN-19.t11
RESOLUTION NO. 91 739