HomeMy WebLinkAboutMINUTES - 11051991 - 1.3 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: November 5, 1991
SUBJECT: Approval of Contract Change Orders Nos. 3, 4, and 5, for the Willow Pass Road
Widening Project in the West Pittsburg Area,
Project No. 0662-6R4134-86
Specific Request(s)or Recommendation(s)&Background&Justification
I. Recommended Action:
AUTHORIZE the Public Works Director to execute Contract Change Orders Nos. 3, 4, and 5, in
the approximate amounts of$38,000.00,$7,000.00, and$14,000.00 to compensate the contractor,
Hess Construction, for additional roadway construction, signal modifications and installing
sections of chain link fence throughout areas along Willow Pass Road.
II. Financial Impact:
The project contingency funds are sufficient to cover the change order costs. The source of
funds is the West Pittsburg Area of Benefit.
III. Reasons for Recommendations and Background:
The cumulative total of Contract Change Orders exceeds $25,000.00, requiring Board Approval.
Design additions and the increased complexity of the project required additional road work, signal
modifications, chain link fencing and additional labor.
IV. Consequences of Negative Action:
The lack of approval would preclude payment for work required.
Continued on attachment: _yes SIGNATURE:*^44C4
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: NOV 5 1991 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller I hereby certify that this is a true and correct copy of
Public Works an action taken and entered on the minutes of the
Design Board of supervisors on the date shown.
- Accounting, R. Gilchrist ATTESTED: .N l I L 1991
- R. Bruno PHIL BATCHELOR,Clerk of the Board
of Supervisors and County Administrator
Contractor ' n
KE\tt Sy ih�i,b , �C�yAi -- .Deputy
c:BO\WPR-5.t11