HomeMy WebLinkAboutMINUTES - 10221991 - 1.8 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: October 22, 1991
SUBJECT: Approve Contract Change Order No. 7 (Balancing) for the Appian Way Widening Project
Project No. 0662-6R4288-84
Specific Request(s)or Recommendation(s)&Background&Justification
L Recommended Action:
APPROVE Contract Change Order No. 7 (Balancing) in the approximate amount of $17,000.00
and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor
for final quantities used on the project.,
II. Financial impact:
The project contingency funds are sufficient to cover this cost. It is funded by Federal Highway
Administration Funds (FAU 86%) and Local Road Funds (14%).
III. Reasons for Recommendations and Background:
This change order will balance quantities allotted with quantities used. Since the combined total
of change orders for this project exceeds $25,000.00 Board Approval is needed.
IV. Consequences of Negative Action:
Lack of APPROVAL would preclude payment to the contractor for work done.
Continued on attachment: _yes SIGNATURE: '
4f
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: OCT 2 2 1991 APPROVED AS RECOMMENDED ✓ OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works I hereby Y certif that this is a true and correct copy of
- Design an action taken and entered on the minutes of the
- Accounting, R. Gilchrist Board of supervisors on the data shmrL
- R. Bruno
ATTESTED: �'122-1991
PHIL BATCHELOR,Clark of the Board
Contractor of Adm� a,I'latr
aW
GB\tt By
c:BO\AP2-22.t10